Resolved
Resolved :- That the forecasted outturn position for the 2010/11 Environment and Development Services Capital programme be noted.
The Former Regeneration Scrutiny Panel noted this item on Wednesday 24 November 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved :- That the forecasted outturn position for the 2010/11 Environment and Development Services Capital programme be noted.
The purpose of this report is to provide details of the current monitoring position at the end of September 2010 for the Environment and Development Services 2010-11 capital programme.
As part of it’s deficit reduction plan the Government reduced grant funding previously announced as being available to fund capital projects. The Environment and Development Services 2010/11 programme has therefore been adjusted to reflect the reduced funding levels. The effect of this is detailed in the body of this report.
Cabinet will shortly be asked to approve a revised capital programme, and for EDS the forecasted outturn position in this report will form the basis of the revised programme.
That the forecasted outturn position for the 2010/11 Environment and Development Services Capital programme is noted. 7. Proposals and Details
The budget process that led to the original capital programme for 2010/11 to 2012/13 ensured that the Council’s capital investment plans were aligned with it’s strategic priorities. The financial implications of the programme are reflected in the Council’s Medium Term Financial Strategy (MTFS) and Treasury Management and Investment Strategy.
The summary expenditure plans and profiles are reflected in the table presented below. A detailed copy of the programme is attached at Appendix 1.
2009/10 2010/11 2010/11 2011/12 2012/13 Outturn Original Revised Estimate Estimate Estimate Estimate £m £m £m £m £m Environment & 47.072 37.822 37.776 16.227 0.695 Development Services
7.2Environment and Development Services Capital Programme 2010/11
A copy of the full programme is attached to this report at Appendix 1.
The Government’s in year budget savings amounted to £3.495m for the Directorate. The programme has therefore been adjusted to reflect the decreased funding. The impacts of the reductions are explained below.
Narrative on the progress of the programme is also shown below:
Waste Management • The Council is currently in the process of procuring a new waste disposal facility in conjunction with Doncaster and Barnsley Councils. The costs of developing Rotherham’s share of the scheme have been added to the programme to the value of £365k in 2010/11 funded utilising Prudential Borrowing.
Minor Strategic Maintenance • The estimates for the Highthorne Road barrier adjacent to the railway line at Swinton have been revised upwards from the original budget of £78k to £312k. This is due to the Council revising the scheme to reflect the accessing of additional external funding. • Significant schemes amounting to £425k in total have also been added to the programme for essential health and safety works. These works include flood prevention works at Aston, works on retaining walls at Masborough and Legionella prevention works at the Millennium Centre at Clifton. These are funded utilising Prudential Borrowing.
Rotherham Economic Regeneration Fund • The remaining funding of £405k for development projects has been deleted from this part of the programme and has been reallocated to the Priority A schemes block. It is being used as part of the funding package for the purchase of the land for the Community Stadium.
Highways • As a result of the in year cuts to previously announced capital funding, expenditure on Highways has been reduced by £1.405m. The major scheme that has been deleted is the Waverley Link road. This scheme amounted to £335k of expenditure in 2010/11, £1.4m in 2011/12 and £7m in 2012/13. The balance of the £1.4m of deleted schemes consists of various schemes that were intended to improve footpaths and junctions, traffic calming and local safety schemes throughout the Borough.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
10-11 Capital Q2 Appendix 1Appendix | 6 pages | Download |
PDF |
Capital Programme Monitoring Quarter 2: 2010/11Report | 6 pages | DownloadRead as text |
Follow The Former Regeneration Scrutiny Panel at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Mar 2011 | Minutes of the previous meeting of the Regeneration Scrutiny Panel held on 23rd February, 2011Resolved :- That the minutes be approved as a correct record. | Approved | Open |
| 23 Mar 2011 | Pedestrian Crossing Assessment Method and Costs- (1) That a scrutiny review take place on this subject and that a scoping meeting take place as soon as possible. (2... | Noted | Open |
| 23 Mar 2011 | Road Safety Education, Training and Publicity updateResolved :- (1) That the Senior Engineer be congratulated for his informative report and concise presentation. (2) Th... | Noted | Open |
| 23 Mar 2011 | Environment & Development Services Performance Report 3rd Quarter 2010 - 2011- That the content of the report be noted. | Noted | Open |
| 23 Mar 2011 | Minutes of the Performance and Scrutiny Overview Committee- That the content of the minutes be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.