The Former Regeneration Scrutiny Panel noted this item on Wednesday 24 November 2010. Below is the council's own wording, with the papers it was decided on.
- That the current forecasted year end outturn position of an under spend of £177,000 for the Environment & Development Services Directorate based on expenditure and income as at September 2010 and forecast expenditure and income to 31st March 2011, be noted.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
Report to The Former Regeneration Scrutiny Panel, 5 pages
Summary
To report on performance against the revenue budget for the Environment and Development Services Directorate as at the end of September 2010 and to provide a forecast outturn for the whole of the 2010/11 financial year.
Recommendations
That the current forecasted year end outturn position is an under spend of £177,000 for the Environment & Development Services Directorate based on expenditure and income as at September 2010 and forecast expenditure and income to 31st March 2011, be noted. 7. Proposals and Details
Following the September cycle of budget monitoring the Directorate has identified that it is likely to deliver an under spend of £177,000 (-0.38%) against its total net revenue budget of £46,041,577.
Current projections for EDS Revenue Budget Monitoring at the end of September 2010
The table below shows the monitoring figures reported for April – July and an updated position for April – September, with narratives explaining the current projections.
April-July April- Movement September Service £000 £000 £000 Asset 609 310 -299 Management Business Unit 49 0 -49 Culture -142 -273 -131 &Leisure Regeneration 200 70 -130 & Planning Streetpride -121 -284 -163 TOTAL 595 -177 -772
Asset Management £310k+
The key pressures for this Service remain Office Accommodation costs as £300k above budget, the vacancy management target which the Service may find difficult to achieve in the year (£85k), and the impact on revenue of property related costs which are unfunded (£85k). However, these pressures are partially mitigated by savings identified across the Service due to staffing reductions and additional income generation (-£160k).
Business Unit £0k+
This Service is reporting a balanced budget.
Culture and Leisure £273k-
The improving position for Culture and Leisure is mainly due to the inclusion of staff savings as a result of retirements and voluntary severance, and a one- off saving of £70k from the Materials Fund. Regeneration and Planning £70k+
The Service continue to work through the reductions in grant funding from Yorkshire Forward and reductions in fees that are claimable against capital projects, and have managed to reduce this to a pressure of £74k. The vacancy management target of £129k is still proving difficult to achieve in year due to the other pressures within Services. There is a pressure of £45k within Building Control as the income target is not being achieved due to the continued economic climate. These pressures are being mitigated by some in year savings offered, reducing the use of RERF (Rotherham Economic Regeneration Fund) by -£50k, reduced use of LDF (Local Development Framework) budget -£65k, along with staff savings due to vacancies, maternity & retirement -£63k.
Streetpride £284k-
The key pressures identified remain on Street Cleansing (£25k+) and emergency maintenance (£32k+). These are being mitigated by savings across the Service and include staffing costs savings, as a result of retirements and voluntary severance, and these are in addition to in year savings/additional income totalling -£255k.
EDS have now offered some additional in year savings/income which have been reviewed, and the total included in this months monitoring is £522k.
The following pressures due to in-year grant cuts remain included within the EDS report. • Cost of offering free swimming for August & September after the Government grant ceased at the end of July (£40k). • Pressure on staffing costs in RIDO as a result of reduced funding from Yorkshire Forward (£100k).
The Regeneration Scrutiny Panel has requested an update on Agency and Consultancy
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow The Former Regeneration Scrutiny Panel at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.