Courtesy Consultation from Sheffield City Council regarding a planning application for the 'Erection of a community renewable energy centre on land at rear of Hadee Engineering Co Ltd, Rother Valley Way, Sheffield (RB2010/0493)
DecidedPlanning1 paper
Planning Board decided this item on Thursday 28 June 2012. Below is the council's own wording, with the papers it was decided on.
Resolved :- (1) That Sheffield City Council be thanked for giving the Council the opportunity to comment on the planning application. (2) That Sheffield City Council be advised that this Council had no objections to the proposed development.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
That Sheffield City Council be informed that the Council has no objections to the proposals.
Background
Rotherham MBC has been consulted on the above planning application submitted to Sheffield City Council. This is a ‘courtesy’ consultation as required due to the close proximity of Rotherham Borough to the application site which is across the boundary in Sheffield. RMBC must provide SCC with comments on the application and the impact of the proposal on Rotherham in terms of planning related issues such as the environment and traffic.
Site Description & Location
The site is located within the Sheffield City Council’s administrative boundary. The application site is situated in the long established Holbrook Industrial Estate, located approximately 1.4km north-west of Killamarsh and 1.4km north east of Halfway, Sheffield.
Proposal
The proposed development is essentially for the construction and operation of a community renewable energy centre within the confines of Holbrook Industrial Estate.
The facility will be a combined heat and power plant which will use prepared recycled wood chippings as a fuel to generate electricity and heat for the local community benefit. The proposal is a renewable energy development and provides a viable alternative for the use of wood chippings that may otherwise be treated as a waste material. The applicant has indicated that they expect 8 in and out lorry movements in a day, with deliveries of wood restricted between 8am – 5pm. The facility will generate electricity which will be transferred to the National Grid via an on site substation and underground cabling. The plant will also produce heat which will be made available for use within the local community.
Total savings of CO2 from the proposed energy facility amount to approximately 18,000 tonnes per annum, which over time will go a significant way to meeting the Government’s (both local and national) broader aims for energy generation and climate change reduction.
The energy centre will be fully enclosed within a single structure. The footprint of the proposed building will be 3,650 sqm., with width of 48.5m and length of 84.5m. The maximum height of the building will be 15.6m, with a chimney stack of 25m.
Consultations
Transportation Unit: Notes from the submitted Transport Statement that 16 No. two way trips per day (HGV’s) are anticipated ie. 8 in and 8 out and does not consider this would have a material adverse impact on highways in the Rotherham area eg. A618 Mansfield Road and A57 (Aston By Pass).
Neighbourhoods (Environmental Health):
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Courtesy Consultation from Sheffield City Council regarding a planning application for the 'Erection of a community renewable energy centre on land at rear of Hadee Engineering Co Ltd, Rother Valley Way, Sheffield (RB2010/0493)Report
11Courtesy Consultation from Sheffield City Council regarding a planning application for the 'Erection of a community renewable energy centre on land at rear of Hadee Engineering Co Ltd, Rother Valley Way, Sheffield (RB2010/0493)This decision
Courtesy Consultation from Sheffield City Council regarding a planning application for the 'Erection of a community renewable energy centre on land at rear of Hadee Engineering Co Ltd, Rother Valley Way, Sheffield (RB2010/0493)This decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.