Resolved
- That the report and the revised budget position be noted.
Safe and Attractive Neighbourhoods (August 2010-February 2015) noted this item on Monday 12 November 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
- That the report and the revised budget position be noted.
This report presents progress to date on the 2012/13 Capital Programme, together with a forecast out-turn position to the end of the financial year.
Based upon activity to date, the forecast out-turn position is that spend can be contained within the revised budget of £24.554m.
That Cabinet Member receives and notes the revised budget and the financial forecast to year end. 7.0 Proposals and Details
7.1The revised 2012/13 HIP was approved by Cabinet Member on the 30 July, 2012 with a total programmed spend of £25.020m.
7.1.2 Since that date 2 custom built pilot projects have been slipped into 2013/14 resulting in a budget reduction of £145k
In addition there has been substantial slippage on 2 private sectors regeneration schemes.
In all cases, funding for the proposed works has been transferred into 2013/14 which has led to a revised 2012/13 HIP of £24.554m as shown in the table below, a reduction of £466k.
7.1.3 Budget Monitoring for 2012/13 is therefore against the revised budget of £24.554m as detailed in Appendix A of this report.
7.1.4 Based upon spend and commitments to date, the forecast overall spend on the revised budget, is that spending will be in line with budget.
Adj Revised Forecast Variance Budget Budget Out-turn To £000s £000s £000s revised Budget £000s Refurbishments 12,124 12,124 12,108 -0,016
Other Capital Works 5,590 5,590 5,606 +0.016
Total Capital Works to properties 17,714 17,714 17,714 0
Fair Access to All 3,270 3,270 3,270 0
Regeneration Renewal 2,791 2,470 2,470 0
Other Public Sector 1,245 1,100 1,100 0
Total Capital Programme 25,020 24,554 24,554 0
7.1.5 The balance of this report will provide an overview on the forecast out- turn position, together with a narrative on the changes on budget provision. 7.2 Details
7.2.1 Total Capital Works to Properties
It can be seen from Appendix A and the table above that the forecast out-turn on Capital Works to Properties is £17.714m which is in line with the revised budget
This budget sum can be analysed further, as follows:
Refurbishments
A total of £12.124m was budgeted for refurbishments and, based upon activity to date, the forecast out-turn is £12.108m a minimal underspend of £16k which is broadly in line with Quarter 1 forecast. Work is planned as follows.
• Internals
A total of £3.7m has been allocated for internal works to be delivered through the partnering contracts with Willmott Dixon and Morrison.
A total of 542 are now scheduled to receive Internal Works and to date 202 have been completed, with a further 102 in progress.
As in previous years tenant refusal rates remain high, therefore replacement schemes are being developed to take up any budget savings as they arise.
• Externals
A further £5.7m has been identified for planned external works. Since the last report roofing and external works to blocks of flats at Rockingham have been identified as high priority and therefore funding has been redirected from combined external works to properties to address these issues. £3.3m has been issued to the partner contractors with a further £2.4m to be delivered through Lovells with a planned start on site immediately after Christmas.
However, there is a high percentage of leaseholders within the blocks (25%) and the consultation process is currently being planned. In addition, the delivery of the works will be weather dependant all of which potentially creates a risk of not delivering full spend to budget. These works will be monitored closely, and any forecast underspend will be mitigated, where possible, by accelerating works to flat doors and communal doors and windows. • Central Heating/Boiler Replacement
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HIP AppendixAppendix | 1 pages | Download |
PDF |
Housing Investment Programme (HIP) 2012-13 Quarter 2 MonitoringReport | 10 pages | DownloadRead as text |
Follow Safe and Attractive Neighbourhoods (August 2010-February 2015) at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Feb 2015 | Local Plan Evidence Base - Joint Sheffield and Rotherham Employment Land ReviewResolved :- (1) That the report be received and its contents noted. (2) That the proposed appointment of Nathaniel Li... | Noted | Open |
| 2 Feb 2015 | Minutes of the previous meeting held on 12th January, 2015- That the minutes of the previous meeting be agreed as a correct record. | Agreed | Open |
| 2 Feb 2015 | Housing Investment Programme 2014/15 update- That the report be received and its content noted. | Noted | Open |
| 2 Feb 2015 | Housing Revenue Account Budget Monitoring Report 2014/2015- That the report be accepted and the latest financial projected outturn based on forecasts to end of December, 2014,... | Noted | Open |
| 2 Feb 2015 | Neighbourhoods General Fund Revenue Budget Monitoring 2014/2015- That the report be received and the latest financial projection to the end of December, 2014, against the budget fo... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.