BDR MANAGER UPDATE REPORT
BDR WASTE PFI BDR M AN AGER UPD ATE REPORT 14 MA RCH 2014
1.0Governance
A site visit for Joint Waste Board members took place on 3 February 2014, all who attended were pleased with progress.
Paul Castle joined the BDR Steering Committee in his new role as Assistant Director, Operational Services for BMBC.
2.0Project Delivery
2.1Bolton Road
Item Percentage Target Actual Comments Complete Completion Completion Date Date Discharge of 95% 1/7/2015 Outstanding conditions: planning • Biodiversity conditions • Flood management plan • Traffic management plan The above have now all been submitted to RMBC planners SWM awaiting comments.
Fire Strategy 85% ITS Fire strategy in place. Jones Celtic FS completed is under review and once completed a final review of the inter relationship will be undertaken. Power on to 90% 26/8/2014 Majority of electricity sub-station works permanent complete. works Buildings 74% 29/9/2014 Workshop and visitors centre steelwork complete erected and majority of cladding excluding complete. ITS groundwork complete, planting steelwork and cladding for bio drying area progressing well. Roads and 60% 01/10/2014 Several slab pours completed, 2 of 3 weighbridge weighbridge foundations in progress. AD complete slab pours commenced Intelligent 60% 7/4/2015 Steelwork erection commenced, Transfer Station refinement, bio drying halls, reception hall (ITS) commenced. Construction ITS 0% 24/2/2015 Commissioning ITS Acceptance 0% 20/5/2015
1 Tests Anaerobic 0% 12/10/2014 Digestion (AD) Commissioning FITs application 0% 12/10/2014
Animal By- 0% 12/5/2015 Products Regulations (ABPR) Compliance AD Acceptance 0% 16/6/2015 Tests Progress 30% 1/7/2015 Estimate 2 weeks of float in current towards Service programme, though this is not translating Commencement yet to an early ecodecco start date
2.2Ferrybridge
Item Percentage Target Actual Comments Complete Completion Completion Date Date Enabling works 95% 17/12/2012 Cricket Pavilion completed, new car Ferrybridge parking area completed, work on access underway outstanding work on tank but this will not effect the main works commencing Main Works Hot 0% 12/10/2014 This date has slipped into January 2015 at Commissioning last update Operational 0% 5/4/2015 Testing Facility 0% 5/4/2015 Operational
3.0Technical
3.1Bolton Road
The Environment Agency (EA), Jones Celtic Bio Energy and Shanks Waste Management have discussed the bunding requirement for the percolate tank and a thicker membrane is to be used around the tank.
The introduction of a membrane rather than a bund and the requirements of the Industrial Emissions Directive will require Shanks to apply for a bespoke Permit rather than a Standard Rules Permit. The final design of the AD is not yet complete due to issues around the positioning of the stack. A section 73 planning application is to be considered the permit will be changed from Standard Rules to Bespoke following this. Shanks have submitted an application to vary the planning conditions around Sunday working to allow work that does not involve deliveries of materials or movements to and from the site to be undertaken. The application RB2014/0057 was considered by RMBC Planning Committee on 20th February 2014 and permission has been granted.
Work continues on the verge/footpath and utility connections. These will require temporary lights on Bolton Road. Shanks Waste Management are providing information to Community Liaison Group members andlocal businesses and updates are provided on the website.
3.2Ferrybridge
The stack is complete on the build at Ferrybridge and the structural steel work on the air- cooling condenser is in place. The boilers are to be in place early in the New Year. The plant commissioning date is now early 2015 and the full service commencement date is anticipated to be June 2015. SSE will continue to provide monthly updates on progress.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
BDR Manager's ReportReport | 41 KB | DownloadRead as text |
Follow Barnsley, Doncaster and Rotherham Joint Waste Board at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Nov 2026 | Minutes of the previous meeting held on (copy attached)That the minutes of the meeting of 3 February 2026 be approved. | Approved | Open |
| 16 Nov 2026 | BDR Managers ReportThat the budget for 2026/27 be agreed. 2. That the report be noted. | Agreed | Open |
| 16 Nov 2026 | BiffaThat the update be noted. | Noted | Open |
| 16 Nov 2026 | Risk RegisterThat the report be noted. | Noted | Open |
| 3 Feb 2026 | Minutes of the previous meeting held on 7 October 2025 (copy attached) and any matters arising- That the minutes of the meeting held on 7 October 2025, be approved as a true and correct record of the proceedings. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.