Resolved :- (1) That Barnsley Metropolitan Borough Council be thanked for giving this Council the opportunity to comment on this planning application. (2) That Barnsley Metropolitan Borough Council be informed that this Council has no objections to the proposed development which was within the Dearne Valley Nature Improvement Area which also covered some of Rotherham and Doncaster Councils.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
To the Chairman and Members of the PLANNING REGULATORY BOARD Date 18th September 2014
Report of the Director of Planning and Regeneration Service
ITEM NO. SUBJECT
1 Ref: RB2014/0785
Erection of a Renewable Energy Park comprising of a Timber Resource Recovery Centre and Anaerobic Digestion facility at Land off Houghton Main Colliery Roundabout, Park Spring Road, Barnsley.
2 DCLG Technical Consultation on Planning - response ROTHERHAM METROPOLITAN BOROUGH COUNCIL PLANNING REGULATORY BOARD
PLANNING AND REGENERATION SERVICE REPORT TO COMMITTEE 18TH SEPTEMBER 2014
Item 1 Ref: RB2014/0785 Proposal and Erection of a Renewable Energy Park comprising of a Timber Location Resource Recovery Centre and Anaerobic Digestion facility at Land off Houghton Main Colliery Roundabout, Park Spring Road, Barnsley. Recommendation No objections
Site Description & Location
The application site lies on Park Spring Road near Great Houghton within Barnsley Borough, approximately 3.2km to the north of the Rotherham Boundary.
The application site covers approximately 4.4ha and comprises of a vacant reclaimed site to the south of Park Spring Road. The River Dearne lies to the west of the site and a curved flood defence bund to the north and west follows the alignment of a disused railway line. There are existing industrial/commercial premises to the north and further along Park Spring Road.
The site is relatively remote from any residential properties with the closest being a few scattered farms within Barnsley Borough. The closest settlement within Rotherham is Brampton which lies approximately 3km to the south. Background
RMBC has been consulted on the above planning application submitted to Barnsley MBC. This is a ‘courtesy consultation’ as required due to the close proximity of Rotherham Borough to the application site which is across the boundary in Barnsley. RMBC are invited to provide Barnsley MBC with comments on the application and the impact of the proposal on Rotherham in terms of such planning related issues as the environment, flooding, ecology and traffic within Rotherham.
Proposal
The application proposes to develop a renewable energy park comprising of a 150,000 tonnes per annum Timber Resource Recovery Centre and a 60,000 tonnes per annum Anaerobic Digestion Facility. The development of the site will create two distinct but compatible energy generation facilities with the potential to generate 23 megawatts of electricity and to provide direct heat and/or electricity to appropriate off takers in the local area.
The Anaerobic Digestion Facility will be located on the northern and eastern part of the site and will receive 60,000 tonnes per annum of material (from commercial and municipal food waste) to generate an estimated 3mw of electrical energy. The biomethane fuel will be derived via anaerobic digestion.
The Timber Resource Recovery Centre will be sited on the southern and western portion of the site and will receive 150,000 tonnes per annum of biomass which may include waste timber derived primarily from the commercial and industrial sectors and will subject it to a process that recovers clean ferrous and non-ferrous material for recycling and generates approximately 20mw of renewable electrical power.
The constituent individual buildings and their sizes are listed below: Length (m) Width (m) Height (m) TRRC Reception Hall 65 45 11.4 Process Bldg 102 30 30 Stack 2.5 diameter 45 Turbine Hall 25.7 18 17.9 Offices/workshop 12.3 18 17.9 Condensors 53.7 13.4 23 Ash Storage Silos 6.6 diameter 14.8 Fire Water Tank 13 diameter 7.0 Fuel Oil Storage 3 2.4 2.5 Tank Standby 13.2 3.2 2 Generator Fire Water 4 3 2.5 Pumps Enclosure AD Process Bldg 42 28 12.5 Admin/Welfare n/a (within process building) Filters 12.2 7.2 5 Storage Tanks 21.1 diameter 15.7 Buffer Tanks 10.1 diameter 16 Gas Holder 8 diameter 7.8 CHP Engines 12.2 2.5 3 Oil Store 12.2 2.5 3 Flare 1 diameter 9 Weighbridge 1.8 1.2 2.5 Kiosk
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
31Courtesy Consultation - Erection of Renewable Energy Park - Land off Houghton Main Colliery Roundabout Park, Spring Road, Barnsley (RB2014/0785)This decision
Courtesy Consultation - Erection of Renewable Energy Park - Land off Houghton Main Colliery Roundabout Park, Spring Road, Barnsley (RB2014/0785)This decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.