Minded to Grant Decision :- (1) That the land on St Leonard’s Road adjacent to St Ann’s Primary School currently owned by Rotherham College of Arts and Technology be purchased by the Local Authority for a sum of £95,757 inclusive of legal fees and this be funded from the project contingency and from savings made to the contract through value engineering. (2) That the land on St. Leonards Road be developed for the provision of allotments to accommodate all tenants displaced from the former Eldon Road allotments for the sum of £157,370 and this be funded from the project contingency and from savings made to the contract through value engineering. (3) That the purchase of the land referred to as Donfield Tavern as approved by Cabinet on the 18th September, 2013 Minute C81, for £135,000 be noted and this be funded from the project contingency and from savings made to the contract through value engineering. (4) That the cost to provide the operational resources to the new school equating to ICT £50k and for the furniture £60k be noted and for this to be funded from the project contingency and from savings made to the contract through value engineering. Date of Publication of the Minded to Grant Decision :- 20 th April, 2015. Representations upon the decision are invited from Councillors, members of the public, partner agencies and any interested body or individual within five working days from the date of publication and must be received by Debbie Pons [email protected] no later than 5.00 p.m. on 27 th April, 2015. Date Representations Received :- None. Representations Received :- None. Date of Commissioner Manzie’s Final Decision :- 28 th April, 2015.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
On the 18th July 2013 the Local Authority was informed that a bid to the Department for Education (DfE), Targeted Basic Need Programme to fund a new 1.5 form entry primary school at Eastwood in Rotherham had been successful.
On the 20th August 2013 the Education Funding Agency (EFA) informed the Local Authority that a provisional funding grant of £3,216,064 had been awarded with a further £150,000 project support funding. This grant is time constrained and must be spent by the 31st August 2015.
A further £3.05m is being funded by the Local Authority. The total approved expenditure for the new school is £6,416,064.
There has been further additional expenditure which has arisen as a result of the school development. These are:
• Statutory allotment provision. (This is a mandatory provision) • Purchase of land belonging to the Donfield Tavern • Operational issues relating to the school
Recommendations
That the Commissioner agrees:
• That the land on St Leonards Road adjacent to St Ann’s Primary School currently owned by Rotherham College of Arts and Technology is purchased by the Local Authority for a sum of £95,757 inclusive of legal fees and this is funded from the project contingency and from savings made to the contract through value engineering. • The land on St Leonards Road is developed for the provision of allotments to accommodate all tenants displaced from the former Eldon Road allotments for the sum of £157,370 and this is funded from the project contingency and from savings made to the contract through value engineering.
• The Commissioner notes the purchase of the land referred to as Donfield Tavern as approved by Cabinet on the 18th September 2013 Minute C81, for £135,000 and this is funded from the project contingency and from savings made to the contract through value engineering.
• The Commissioner notes the cost to provide the operational resources to the new school equating to ICT £50k and for the furniture £60k and this is funded from the project contingency and from savings made to the contract through value engineering. 7. Background
On the 18th July 2013 the Local Authority was informed that a bid to the DfE Targeted Basic Need Programme to fund a new 1.5 form entry Primary school (ages 3 to 11) had been successful. The new school will provide a long term solution to pupils needing to access school places within the central catchment areas of the Authority and is located within Eastwood Village.
On the 20th August 2013 the Education Funding Agency (EFA) informed the Local Authority that a provisional funding grant of £3,216,064 had been awarded with a further £150,000 project support funding. This grant is time constrained and must be spent by the 31st August 2015.
A further £3.05m is being funded by the Local Authority. The total approved expenditure for the new school is £6,416,064. This was approved by Cabinet at the meeting of the 17th December 2014.
Construction work started on site on the 20th October 2014 and will be completed in two phases: Phase 1 on the 24th August 2015 and Phase 2 on the 14th September 2015.
There has been a requirement for further additional expenditure which has arisen as result of the school development. These are:
• Statutory allotment provision • Purchase of land belonging to the Donfield Tavern • Operational issues relating to the school
7.1Statutory allotment provision
The new school is being constructed on a site that was classified as a Statutory Allotment (known as Eldon Road Allotments).
Under Section 8 of the Allotments Act 1925 the Local Authority (LA) is required to obtain approval from the Secretary of State for Communities and Local Government to change the use from a statutory allotment to an alternative use; in this instance, education.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.