Minded to Grant Decision :- (1) That the current forecast outturn position for the 2015/16 Capital Programme and the update to the approved Programme for 2016-2018 be noted. (2) That, in conjunction with Advisory Cabinet Members, a further review of the 2015/16 Capital Programme be undertaken and when complete this work should contribute to the long term Capital Strategy. Reason :- To provide details of the current forecast outturn for the 2015/16 capital programme and to enable Commissioners and the Council to review the existing approved Capital Programme for the financial years 2016/17 to 2017/18. Date of Publication of the Minded to Grant Decision :- Friday, 9 th October, 2015. Representations upon the decision are invited from Councillors, members of the public, partner agencies and any interested body or individual within five working days from the date of publication and must be received by Debbie Pons [email protected] no later than 5.00 p.m. on Friday, 16 th October, 2015. Date Representations Received :- None Representations Received :- None Date of Commissioner Manzie’s Final Decision :- Monday, 19 th October, 2015. - (1) That the current forecast outturn position for the 2015/16 Capital Programme and the update to the approved Programme for 2016-2018 be noted. (2) That, in conjunction with Advisory Cabinet Members, a further review of the 2015/16 Capital Programme be undertaken and when complete this work should contribute to the long term Capital Strategy.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
The purpose of this report is to provide details of the current forecast outturn for the 2015/16 capital programme and to enable Commissioners and the Council to review the existing approved Capital Programme for the financial years 2016/17 to 2017/18. The Capital Programme 2015-2018 was approved at the Commissioners’ Meeting of the 27th February 2015. Further, Commissioner Manzie’s meeting of the 9th July 2015 approved the individual scheme carry forward requests from 2014/15 into the 2015/16 Capital Programme.
SLT will be aware from the report presented to the meeting of the 16th September 2015 that Council officers are currently engaged in developing a five year Capital Programme, spanning the period 2016-2021. This work will ensure that the Council’s capital expenditure plans are aligned with its strategic priorities and vision for Rotherham. The development of the Capital Programme is being done in tandem 1 with the development of the Council’s Capital Strategy, and new standardised arrangements for the governance of the programme.
Recommendations
Commissioner Manzie is asked to :
1. Note the current forecast outturn position for the 2015/16 Capital Programme, and the update to the approved Programme for 2016-2018.
2. In conjunction with Advisory Cabinet Members, to determine as part of the work that is being undertaken on the 2016-2021 Capital Programme, if any urgent condition projects should be brought into the 2015/16 Capital Programme.
List of Appendices Included
Appendix 1 – Children and Young People’s Services Capital Programme Appendix 2 – Environment and Development Services Capital Programme Appendix 3 – Neighbourhoods and Adult Services Capital Programme Appendix 4 – Resources Capital Programme
Background papers
Report to Commissioners Meeting – 27th February 2015 Report to Commissioner Manzie’s Meeting – 9th July 2015 Report to SLT – 29th September 2015
Consideration by any other Council Committee, Scrutiny or Advisory Panel
N/A
Council Approval Required
Yes
Exempt from the Press and Public No
2 Title (Main Report)
Capital Programme Monitoring 2015/16 and Capital Programme Budget 2016/17 to 2017/18
Commissioner Manzie is asked to :
1.1Note the current forecast outturn position for the 2015/16 Capital Programme, and the update to the approved Programme for 2016- 2018.
1.2In conjunction with Advisory Cabinet Members, to determine as part of the work that is being undertaken on the 2016-2021 Capital Programme, if any urgent condition projects should be brought into the 2015/16 Capital Programme.
2. Background – The Capital Programme 2015/16 – 2017/18
2.1It is vital that the Council’s Capital Programme and Capital Strategy maintains a strategic link with the Council’s Corporate Plan, as capital projects play a key role in delivering the Council’s strategic priorities. In addition, key themes within the Rotherham Improvement Plans (Children and Young People’s and Corporate) are predicated on capital projects.
2.2In order to ensure that the Council makes efficient and effective use of the capital resources available to it, it is important that the existing approved Capital Programme is kept under regular review and where necessary revisions are made. This programme was last reviewed in July 2015, and has now been the subject of a further quarterly review.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.