Overview and Scrutiny Management Board, Wednesday 27 September 2017

Rotherham Construction Partnership Framework

Noted Scrutiny 1 paper

Overview and Scrutiny Management Board noted this item on Wednesday 27 September 2017. Below is the council's own wording, with the papers it was decided on.

Item48

Resolved

Resolved :- That the report be noted.
Word for word from the decision Rotherham published for this meeting. Source: moderngov.rotherham.gov.uk

Follow this further

Built from Rotherham's papers

What the report saysPro

Report to Overview and Scrutiny Management Board, 6 pages

Summary

This report provides an update on the RCP Framework which was awarded on 23rd May 2017.

Recommendations

That the contents of this progress report are noted.

List of Appendices Included

Appendix A – Projects Procured Through Frameworks.

Background papers

None. Consideration by any other Council Committee, Scrutiny or Advisory Panel

N/A.

Council Approval Required

No.

Exempt from the Press and Public

Partially; Appendix A is exempt. Title

RCP (Rotherham Construction Partnership) Framework – Progress Report

1.1That the contents of this progress report are noted.

Background

2.1The majority of the Council’s building construction is procured through the YORbuild framework.

2.2There are instances where it is not wholly appropriate to use the YORbuild framework for example with roofing or demolition projects. Where these projects are procured through YORbuild, the main contractor tends to sub-contract the work to a specialist contractor, and then applies a management fee. This management fee can be in the region of 10% of the tender price and clearly this does not present best value to the authority. This type of project will now be procured through the RCP Framework.

2.3YORhub is the combined management organisation for the three regional frameworks (YORbuild, YORcivils and YORconsult).

2.4In 2016 the Council procured just over £4m through the YORbuild framework. The projected volume of work to be procured through the YORbuild framework in 2017 is £7.5m (see Appendix A). YORbuild2 was awarded in March 2016 so a few months of procurement activity were lost hence the drop off in volume of work that was procured through the framework in 2016.

2.5The Council’s own approved lists (for building works up to £150k and mechanical and electrical works up to £500k) expired in May 2016. As such there was no alternative in place as a fall-back to using the YORbuild framework without issuing open tenders.

2.6The decision to procure the RCP framework was approved at the Cabinet and Commissioners’ Decision Making meeting on 14th November 2016.

2.7The lots within the RCP framework are as follows: * Flat Roofing (individual contracts not exceeding £250k) * Pitched Roofing (not exceeding £250k) * Demolition (not exceeding £250k) * Asbestos Removal (not exceeding £250k) * Building Works 1 (up to £150k) * Building Works 2 (between £150k-£500k) * Structural Repairs (not exceeding £50k) * Mechanical Works (not exceeding £200k) and * Electrical Works (not exceeding £200k). 2.8 Expressions of interest were invited on 3rd February 2017 from contractors suitable for the categories of work. The advert was an OJEU notice and was advertised on the YORtender procurement portal. Applicants were required to complete a selection questionnaire (SQ) and provide three references relevant to the opportunity. Applications were received from 59 contractors by the closing date (8th March 2017) and they were comprehensively evaluated by technical and procurement officers.

2.9A scoring mechanism was devised to assess contractors approach to health and safety, environmental management, quality management and technical ability. In addition to this the applicants were also required to demonstrate how their organisation meets or exceeds the Council’s own minimum standards in terms of employment and skills, social values, safeguarding, local employment and buying Rotherham first.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Rotherham Construction Partnership FrameworkReport 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Rotherham

Search all
  1. Rotherham Construction Partnership FrameworkThis decision
  2. Rotherham Construction Partnership FrameworkApproved
  3. Erection of 6 No 132m high wind turbines and associated 80m high anemometer mast, access roads, crane pads, control building, sub-station and temporary construction compound at land at Penny Hill Lane, Ulley, Rotherham for Penny Hill Wind Farm Ltd. (RB2009/0824)Approved
  4. Outline application for residential development and associated parking including the details of the means of access at Job Lot Trading Company Ltd., Canklow Road, Canklow, Rotherham for Field Construction Ltd. (RB2006/0632FUL)Agreed
  5. Construction of flood alleviation scheme (application under Regulation 3 & 9A of the Town and Country Planning Regulations 1992) at land adjacent to the River Don from Bessemer Way to Main Street, Rotherham Town Centre, Rotherham for Rotherham Metropolitan Borough Council (RB2005/0026(FUL))Approved
  6. Rotherham Construction ProjectNoted

More from Rotherham Overview and Scrutiny Management Board

All decisions
MeetingDecisionOutcome
10 Nov 2026 Minutes of meeting Wednesday 7 October 2026 of Overview and Scrutiny Management BoardThat the Minutes of the meeting of the Overview and Scrutiny Management Board held on 7 October 2026 be approved as a... Approved Open
10 Nov 2026 Work ProgrammeThat the Overview and Scrutiny Management Board: 1. Approved the current work programme. 2. Agreed that the Governanc... Approved Open
10 Nov 2026 Forward Plan of Key DecisionsThat the Overview and Scrutiny Management Board: 1. Agreed that the following items would be added to the December ag... Agreed Open
10 Nov 2026 South Yorkshire Mayoral Combined Authority Overview and Scrutiny CommitteeResolved That: The Overview and Scrutiny Management Board received an update on the activities of the South Yorkshire... Decided Open
7 Oct 2026 Minutes of meeting Tuesday 8 September 2026 of Overview and Scrutiny Management BoardThat the Minutes of the meeting of the Overview and Scrutiny Management Board held on 8 September 2026 be approved as... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies