Resolved
Agreed :- That the BDR Manager’s report be received and its contents noted.
Barnsley, Doncaster and Rotherham Joint Waste Board agreed this item on Monday 26 February 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
Agreed :- That the BDR Manager’s report be received and its contents noted.
Item 4 BDR MANAGER UPDATE REPORT
BDR WASTE PFI BDR MANAGER UPDATE REPORT
NOVEMBER 2017 – JANUARY 2018
1.0Governance
1.1Liaison Committee
1.1.1 Following on from a request at the annual Liaison Committee meeting, a 6-month review has been set up for April 2018.
2.0Contract Performance
2.1Recycling and Diversion
2.1.1 Table 1 contains the information about the number of tonnes processed and the contract performance for 2016/17 from 1 April 2017 to the 31 January 2018. The Contractor currently performing at 15.17% recycling this is above the 12.5% termination trigger but below the 19% target. A recycling deduction is applied at the end of the year for every tonne of waste not recycled below the 19% target.
Table 1 – Year to date tonnes Processed 1 April 2017 to 31 January 2018
Tonnes Percentage Target Tonnes Percentage 01 April 2017 Type 01 April 2017 to (contract 2016/17 2016/17 to 31 Jan 2018 estimate) 31 Jan 2018 95.60% of 94%of 250,000 pro rata Total Waste to MBT 239,004.88 250,000 196,301.53 100% capacity capacity Total Waste Third Party Waste 14,417.80 6.03% 11,179.94 5.70% delivered Contract waste only 224,587.08 93.97% 185,121.59 94.30% Household Waste 201,946.77 84.49% 166,838.78 84.99% Landfill Total 8,407.22 3.50% 8,930.81 4.82% 5% Recovery Total 213,310.78 63.62% 178,440.06 96% n/a Ferrous 2,163.30 1.06% 1,997.58 1.20% Non-ferrous 261.3 0.13% 297.12 0.18% Recycling Fines 9,101.75 4.34% 9,438.33 5.66% Glass and Stone 3,223.59 1.56% 3,897.49 2.34% Plastic 6,395.26 3.19% 5,826.70 3.49% Recycling 1,809.08 Metals in bottom ash 2,162.30 1.33% 1.08% other
1 284.08 AWM recycling 2,623.56 0.91% 0.17% 1,767.38 Fines CLO Uplift 1.05% Total 25,931.06 12.84% 25,317.76 15.17% 19.00%
Moisture Moisture Loss 62,375.88 30.76% 54,826.76 28.86% Loss
2.1.2 N.B. above figures are unaudited and subject to change.. Landfill diversion is calculated by total waste diverted from landfill divided by the total waste delivered.
2.1.3 The landfill diversion target for the contract is 95% and to date 4.82% has been landfilled which equates to 95.18% diversion. It should be noted that the average monthly figure for material to landfill from November 2017 to January 2018 is 3.18% or 96.82% diversion from landfill.
2.2Complaints
2.2.1 Flies
2.2.1.1 No fly complaints were received during November 2017 and January 2018.
2.2.2 Noise
2.2.2.1 There were 4 noise complaints received during December 2017 and January 2018, from a local resident. A review of site operations on the respective dates indicated there were no exceptional activities identified and investigations are ongoing.
2.3Health and Safety
Table 2 - Compliance from April 2017 to January 2018
2017/18 Close Accident Accident Non RIDDOR RIDDOR Major Environmental Call less than more RIDDOR dangerous more than RIDDOR 3 days than 3 dangerous occurrence 7 day days occurrence injury April 33 0 0 2 0 0 0 0 May 44 1 0 2 0 0 0 1 June 63 0 0 3 0 0 0 1 July 29 2 0 2 0 0 0 0 Aug 34 0 0 4 0 0 0 0 Sep 20 4 0 6 0 0 0 0 Oct 44 3 0 6 0 0 0 1
2 Nov 24 2 0 2 0 0 0 0 Dec 20 1 0 1 0 0 0 0 Jan 41 2 0 0 0 0 0 0 YTD 352 15 0 28 0 0 0 3 Total
2.3.1 Please note: close calls are not incidents; they are where staff have made an observation of something that has the potential to cause an accident. Reporting close calls allows action to be taken before an accident occurs and is a positive indicator of the efforts being made to improve health and safety.
2.3.2 Fire Protection Improvements
2.3.2.1 In December it was confirmed that 3SE were responsible for the costs of the Fire Improvement Works.
2.3.2.2. Work on the selection of the appropriate Fire Improvement works is ongoing. There have been several clarifications required regarding the scope and phasing of the work. . Once the phasing of the project is fully defined, the Councils will be briefed on the contingency plan for diversion of waste.
og 3.0 Grange Lane
3.1Dilapidation work at Barnsley Transfer station highlighted further work necessary to replace the roof. A separate work package is to be considered for this.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
BDR Joint Waste Project: Manager's ReportReport | 123 KB | DownloadRead as text |
Follow Barnsley, Doncaster and Rotherham Joint Waste Board at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Nov 2026 | Minutes of the previous meeting held on (copy attached)That the minutes of the meeting of 3 February 2026 be approved. | Approved | Open |
| 16 Nov 2026 | BDR Managers ReportThat the budget for 2026/27 be agreed. 2. That the report be noted. | Agreed | Open |
| 16 Nov 2026 | BiffaThat the update be noted. | Noted | Open |
| 16 Nov 2026 | Risk RegisterThat the report be noted. | Noted | Open |
| 3 Feb 2026 | Minutes of the previous meeting held on 7 October 2025 (copy attached) and any matters arising- That the minutes of the meeting held on 7 October 2025, be approved as a true and correct record of the proceedings. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.