BDR MANAGER UPDATE REPORT Item 6
BDR WASTE PFI BDR MANAGER UPDATE REPORT
APRIL 2019 – JULY 2019
1.0Governance
1.1Resources
1.1.1 The BDR team is now fully resourced and work has commenced on the Team plan taking into account the Waste and Resource Strategy for England and the key projects that are underway on the BDR Waste Treatment Facility.
1.1.2 The BDR CELO is currently on secondment to Rotherham council to work with the engagement team to help with the new recycling services and bin changes.
2.0Contract Delivery
2.1Bolton Road
1.1.1 Table 1 contains the information about the number of tonnes processed from April to July 2019. The overall tonnage forecast in table 1, will be reviewed quarterly to better reflect the anticipated outturn.
2.1.2 In the July 2019 invoice the forecast tonnage for all three Councils has been reduced in line with the actuals. As the Rotherham service change has resulted in a decrease in the residual waste, the apportionment has been recalculated to reflect this change.
1 Table 1 – Year to date tonnes processed from 1 April 2019 to 31 July 2019
Inputs 2018/19 April May June July YTD 2019/20 Contract Waste (Limbs) A (Household) 52717.51 4241.24 4844.06 3993.08 4518.12 17596.50 B (Commercial) 5203.84 423.66 466.86 421.60 480.80 1792.92 Barnsley C (HWRC) 5469.45 499.04 465.62 428.62 438.56 1831.84 D (Public Highways etc) 1091.27 99.98 86.74 94.48 100.08 381.28 E (Grounds Maintenance) 0.00 0.00 0.00 0.00 0.00 0.00 A (Household) 69143.14 5600.28 6667.82 5725.36 5940.94 23934.40 B (Commercial) 5360.16 157.54 165.76 158.80 177.56 659.66 Doncaster C (HWRC) 7562.06 667.40 644.64 536.46 594.22 2442.72 D (Public Highways etc) 0.00 0.00 0.00 0.00 0.00 0.00 E (Grounds Maintenance) 0.00 0.00 0.00 0.00 0.00 0.00 A (Household) 56246.07 3969.14 4175.74 3678.52 4291.64 16115.04 B (Commercial) 3496.32 273.54 294.24 271.28 322.48 1161.54 Rotherham C (HWRC) 6393.60 559.04 548.68 478.22 524.82 2110.76 D (Public Highways etc) 0.00 0.00 0.00 0.00 0.00 0.00 E (Grounds Maintenance) 0.00 0.00 0.00 0.00 0.00 0.00 Limbs A&B Sub-Total 192167.04 14665.40 16614.48 14248.04 15731.54 61259.46 A (Household) 178106.72 13810.66 15687.62 13396.96 14750.70 57645.94 B (Commercial) 14060.32 854.74 926.86 851.68 980.84 3614.12 BDR C (HWRC) 19425.11 1725.48 1658.94 1443.30 1557.60 6385.32 D (Public Highways etc) 1091.27 99.98 86.74 94.48 100.08 381.28 E (Grounds Maintenance) 0.00 0.00 0.00 0.00 0.00 0.00 Total 212,683 16,491 18,360 15,786 17,389 68026.66
1.1.2 The above table breaks down the input tonnages by authority and waste streams.
Table 2 - Third Party Waste Year to date 1 April 2019 to 31 July 2019
Inputs - 3rd Party 2018/19 April May June July YTD 2019/20 Renewi Derby 15407.70 2347.82 2467.00 3239.38 2131.76 10185.96
1.1.3 Table 2 above shows the third party waste tonnage, this is municipal waste from the sub-contractors other contract.
Table 3 – Performance Year to Date from 1 April 2019 to 31 July 2019
Performance 2018/19 April May June July YTD 2019/20 Recycling (%) 11.41% 12.85% 13.23% 13.59% 10.47% 12.51% Diversion (%) 97.09% 102.02% 90.26% 91.94% 98.78% 95.71% Moisture Loss (%) 27.29% 27.50% 27.63% 32.56%
1.1.4 Contract recycling was 10.47% in July with the year to date recycling figure running at 12.51%. At the request of the Environment Agency,
2 organic contamination of the glass and stone fraction was reduced. This adversely impacted the total volume of glass and stone generated.
Table 4 - Contract Outputs
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
BDR Manager Report April to July 2019Report | 13 pages | DownloadRead as text |
PDF |
Item 6: Appendix 1: Notes from CLG meeting June 2019Appendix | 3 pages | Download |
Follow Barnsley, Doncaster and Rotherham Joint Waste Board at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Nov 2026 | Minutes of the previous meeting held on (copy attached)That the minutes of the meeting of 3 February 2026 be approved. | Approved | Open |
| 16 Nov 2026 | BDR Managers ReportThat the budget for 2026/27 be agreed. 2. That the report be noted. | Agreed | Open |
| 16 Nov 2026 | BiffaThat the update be noted. | Noted | Open |
| 16 Nov 2026 | Risk RegisterThat the report be noted. | Noted | Open |
| 3 Feb 2026 | Minutes of the previous meeting held on 7 October 2025 (copy attached) and any matters arising- That the minutes of the meeting held on 7 October 2025, be approved as a true and correct record of the proceedings. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.