Barnsley, Doncaster and Rotherham Joint Waste Board noted this item on Tuesday 24 June 2025. Below is the council's own wording, with the papers it was decided on.
- 1) That a letter of thanks be issued to the out-going Chair of the Board. 2) That the minutes of the Community Liaison Group meeting held on 3 December 2024, be noted. 3) That any members wishing to visit the Mavers site contact the BDR Waste Partnership Manager, to arrange a visit.
Word for word from the decision Rotherham published for this meeting.Source: moderngov.rotherham.gov.uk
Report to Barnsley, Doncaster and Rotherham Joint Waste Board
Notes from the meeting of the Community Liaison Group on Tuesday, 3 December 2024, at 6pm at the Manvers site.
Attendance
Non-members
Apologies
There were no apologies.
Written updates from Biffa, BDR, and the CELO had been circulated previously. Brief summaries and further updates were given verbally at the meeting and CLG members had the opportunity to ask questions.
1. Welcome and introductions. The acting chair welcomed everyone to the meeting and thanked everyone for their attendance following the postponed meeting scheduled for 19 November - cancelled due to adverse weather. The acting chair said he was happy to chair the meeting pending CLG agreeing a new chair from the group.
2. Notes from the last meeting on 21 May 2024. These were agreed as a true record.
3. Issues arising. There were no issues arising.
4. Biffa BDR update
The Biffa BDR Contract Director summarised and updated the written report and highlighted recent staff changes. In the first half of 24/25 there had been an increase in contract tonnage from the previous year (23/24) over the same period (April – Sept) of approximately 1,300t. It was projected that contract tonnage would likely be higher by the end of the year:
22/23 = 207,700t
23/24 = 209,300t
25/25 = estimated to finish circa 210,000t.
The site had accepted around 3,000t of third-party waste between April and September this year.
Recycling performance had risen to 15% YTD (April – Sept) compared to FY 23/24 of 13.8%. The continued performance of organic fines recovery had given this improvement. This had resulted in slightly better green energy production from the CHP. Glass and stone recovery remained low due to the need to maintain high quality levels.
Following the fire at the Barnsley transfer station a CAPEX had been applied for, and approved, to complete the work to rebuild the transfer station. The work had started and was expected to be completed by December. While the work was being completed the transfer station remained fully operational due to the minimisation of the rebuild area and night works.
Ferrybridge FM1 had dealt with several issues resulting in long queuing times. Biffa had continued to liaise with Ferrybridge to see if the situation could be improved. Tipping slots had been introduced but queueing had resulted in the slots being missed. The tipping bays had been fully repaired and are in operation. The transition into Biffa was underway and the integration process was progressing well. Fundamentally not much would change due to the contract in place. The next 6-12 months would see the legacy Renewi facilities fully integrated with Biffa. Items such as signage and PPE were planned to be changed in the coming months. The partnership was now known as ‘Biffa BDR.’
Biffa Contract Director
The Councils’ (BDR) Waste Team
The BDR Manager summarised and updated his written report and informed CLG he was now the full-time manager of the BDR contract. His role would be focussed on performance management of the contract and ensuring high plant maintenance standards. The BDR councils had continued to successfully deliver waste services and collect all waste streams as scheduled. The councils had seen a slight increase in the amounts of household waste tonnages collected at kerbside and HWRCs, but within acceptable parameters.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Barnsley, Doncaster and Rotherham Joint Waste Board at Rotherham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.