It was RESOLVED that: a) the CIL draft charging schedule and supporting documentation, including the draft regulation 123 list for a six week public consultation, be approved. b) the Executive Manager – Communities be delegated authority to make minor modifications to the draft charging schedule prior to public consultation, and to consult on the draft charging schedule in line with the statutory regulations. c) the Executive Manager – Communities, in consultation with the Portfolio Holder for Housing, Planning and Waste Management, be delegated authority, to make the final decision as to whether to proceed with the submission of a draft charging schedule, representations made and evidence base, together with any proposed modifications, forward to public examination.
Word for word from the decision Rushcliffe published for this meeting.Source: democracy.rushcliffe.gov.uk
1.1The purpose of this report is to provide an update on the latest position in developing the Community Infrastructure Levy (CIL) in Rushcliffe Borough following consultation on the preliminary draft charging schedule in February – March 2017.
1.2It also seeks Cabinet endorsement to consult the public for six weeks on the CIL draft charging schedule (Appendix A) and supporting documentation including the draft regulation 123 list before it is submitted for examination. The draft charging schedule has had regard the comments received to the preliminary draft charging schedule.
1.3The CIL should only be adopted if it will support the provision of infrastructure required to deliver the Local Plan and if it can be set at an economically viable rate. The rate set should have regard to evidence relating to viability, its relationship with Section 106 obligations and any Government reforms to the system of development contributions. These factors should be considered before deciding whether to proceed to examination and, ultimately, adoption.
Recommendation
It is RECOMMENDED that Cabinet
a) approve the CIL draft charging schedule (Appendix A) and supporting documentation, including the draft regulation 123 list for a six week public consultation.
b) authorise the Executive Manager (Communities) to make minor modifications to the draft charging schedule prior to public consultation, and to consult on the draft charging schedule in line with the statutory regulations.
c) delegate to the Executive Manager (Communities), in consultation with the Portfolio Holder for Housing, Planning and Waste Management, the final decision as to whether to proceed with the submission of a draft charging schedule, representations made and evidence base, together with any proposed modifications, forward to public examination. 3. Reasons for Recommendation
3.1To ensure that the impacts of development are mitigated as far as possible through improvements to infrastructure across the Borough.
4. Supporting Evidence
4.1In 2010 the Government introduced legislation to enable local authorities to introduce a Community Infrastructure Levy (CIL) as part of funding new infrastructure required to support growth. CIL would be applied as a standard pre-set charge to almost all new developments that involves new buildings or extensions of 100 square metres or more of gross internal floor space or that involves the creation of an additional dwelling even when that is below the 100 square metre threshold.
4.2CIL is intended to sit alongside Section 106 and other legal agreements in order to fund new infrastructure to support development. The two would operate together, on the basis that, generally, Section 106 agreements would be used to secure new infrastructure that is required to support individual development schemes (particularly on-site facilities) and CIL would be used to fund new infrastructure that is required to support a number of developments. There are now restrictions in force that limit the ability of councils to ‘pool’ those financial contributions secured through Section 106 agreements, which means, therefore, that use of CIL is the only option if there is a need or desire to combine infrastructure funding from multiple developments. It should be noted that Section 106 agreements would still be used to secure affordable housing where appropriate.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.