It was RESOLVED that: a) the projected revenue position for the year, with a minor 0.6% variation (£63,000) in the revenue position (due to the expected business rates position), be noted. b) the capital underspend of £10,237,000 as a result of capital scheme re-phasing and projected savings, be noted.
Word for word from the decision Rushcliffe published for this meeting.Source: democracy.rushcliffe.gov.uk
1.1This report presents the budget position for revenue and capital as at 31 July 2018 along with the appropriate recommendations. The report was considered by the Corporate Governance Group (20 September 2018) with no significant issues raised. Given the current financial climate, it is imperative that the Council maintains due diligence with regards to its finances and ensures necessary action is taken to maintain a robust financial position.
1.2Overall, the financial position is relatively stable with revenue efficiencies and additional grant income of £98k offset by a slightly worse than anticipated business rates position of £161k. The net position of £63k represents a 0.6% variation against the net expenditure budget, in essence a broadly balanced budget position. Positively, £1.19m is expected to be transferred to reserves, so the Council can meet the significant financial challenges and risks going forward.
1.3The capital programme shows a planned underspend of £10.237m due to reasons such as a ‘slow down’ in asset investment (with there being much property market risk) and awaiting the position on the Depot project being finalised.
Recommendation
It is RECOMMENDED that Cabinet note:
a) the projected revenue position for the year with a minor 0.6% variation (£63k) in the revenue position (due to the expected business rates position); and
b) the capital underspend of £10.237m as a result of capital scheme re- phasing and projected savings.
Reasons for recommendation
3.1To demonstrate good governance in terms of scrutinising the Council’s on- going financial position and compliance with Council Financial Regulations. 4. Supporting Information
Revenue Monitoring
4.1The revenue monitoring statement by service area is attached at Appendix A with detailed variance analysis as at 31 July 2018 attached at Appendix B. This shows projected net efficiency savings for the year to date of £83k and additional funding of £15k in Individual Elector Registration (IER) grant, more than offset by the reduction in the collection fund surplus against the budgeted position (£161k) due to business rates variation. The overall £63k variation represents 0.6% against the net expenditure budget and we currently anticipate £1.19m to be transferred to reserves to meet in particular business rates risk going forward (see paragraph 5.3). This position is likely to change throughout the remainder of the year as managers continue to drive cost savings, and raise income, against existing budgets.
4.2Appendix A includes a Minimum Revenue Provision (MRP) of £1m. This is a provision that the Council is required to make each year to cover the internal borrowing costs for the Arena which will be funded by the New Homes Bonus.
4.3As documented at Appendix B, the financial position to date reflects a number of positive variances totalling £378k including additional income from planning applications, the Garden Waste Scheme, salary savings and the additional recovery of Housing Benefit Overpayments. There are several adverse variances totalling £363k including Planning public inquiries, the rising costs of diesel, and an increase in the Streetwise Contract (mainly due to flytipping), and the slowing of asset investments as the Council continues to review its position in light of a volatile property market.
Capital Monitoring
4.4The updated Capital Programme monitoring statement as at 31 July 2018 is attached at Appendix C. This provides further details about the progress of the schemes, any necessary re-phasing and highlights savings of £10.237m A summary of the projected outturn and funding position is shown in the table below:
CAPITAL PROGRAMME MONITORING - JULY 2018
EXPENDITURE SUMMARY Current Projected Projected Budget Actual Variance £000 £000 £000
Transformation 9,387 6,552 (2,835)
Neighbourhoods 2,936 2,950 14
Communities 764 749 (15)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.