It was RESOLVED that: a) the feedback from the Communities Scrutiny Group, which includes the endorsement of a golfing need at Edwalton Golf Course be acknowledged; and b) the utilisation of £0.05m of 2020/21 projected in-year budget efficiencies be allocated to undertake a further detailed technical risk assessment of the site and thereafter a further £0.25m for further master planning work, assuming the risks identified are not prohibitive so that a realistic and deliverable masterplan can be achieved for the site.
Word for word from the decision Rushcliffe published for this meeting.Source: democracy.rushcliffe.gov.uk
1.1This report provides an update from the Communities Scrutiny Group on Edwalton Golf Course (EGC) and recommends a way forward for what is a significant asset for the Council.
1.2In January 2020, Cabinet resolved to review ongoing provision of golf at Edwalton. Despite considerable effort, Lex Leisure has struggled to ensure that the golf course retains any viability, given the challenging operational environment (previously reported in financial reporting to both the Corporate Overview Group and Cabinet). Cabinet requested that a report be commissioned to consider whether there is a golfing need for Edwalton Golf Course, and an alternative options appraisal, if a need is not established, for consideration by the Communities Scrutiny Group.
1.3In January 2021, at the Communities Scrutiny Group meeting Knight, Kavanagh and Page (KKP) (which provides specialist services in sport, leisure, culture, regeneration and green spaces) presented the report on the finding of a two- stage study in respect Edwalton Golf Course:
1.4This report covers the findings of the Communities Scrutiny Group and proposes next steps for determining the future of the asset to maximise its value to the community and Rushcliffe.
Recommendation
It is RECOMMENDED that Cabinet:
(a) acknowledges the feedback from the Communities Scrutiny Group which includes the endorsement of a golfing need at Edwalton Golf Course; and OFFICIAL
(b) allocates the utilisation of £0.05m of 2020/21 projected in-year budget efficiencies to undertake a further detailed technical risk assessment of the site and thereafter a further £0.25m for further master planning work, assuming the risks identified are not prohibitive so that a realistic and deliverable masterplan can be achieved for the site.
Reasons for recommendation
To ensure that the Council’s Edwalton Golf Course asset continues to deliver maximum value for money for taxpayers across the Borough, whilst providing appropriate community infrastructure and the right level of leisure provision. More work is needed on refining future options for the site which includes further technical assessments of the site.
Background
The Council has been pro-active in trying to ensure Edwalton Golf Course maintained financial viability with investment by both the Council and Lex Leisure as reported previously. Lex has been running at a significant loss (around £44k on average over the last three years). This is despite many initiatives including improvements to the clubhouse facilities, enhanced marketing and events, signage and investment in a golf simulator.
5. KKP Findings
5.1The KKP Stage 1 Golf Needs Assessment recommended (as reported to the Communities Scrutiny Group):
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.