It was RESOLVED that: a) the detailed technical assessments that have been undertaken for the par 3 course be acknowledged, which conclude that the site could represent a good option for residential development subject to planning, although Cabinet direction is that it is retained at the present time as an important community facility; b) it was acknowledged that there is likely to be sufficient housing supply in Rushcliffe to 2038 without the need to allocate this site within the Greater Nottinghamshire Strategic Plan but that it be included in a pipeline of potential sites for future consideration as part of the Local Plan process, should the requirement for further sites arise, to be considered concurrently with the site as a community facility; c) further detailed design assessments for the driving range business case over the next period to establish if a standalone driving range could be delivered to provide a betterment to the golfing offer on-site be endorsed; and d) opportunities for ecological improvements and bio-diversity net gain on the main 9-hole course through improvement management and partnership working in line with the Council Climate Change Strategy objectives be explored.
Word for word from the decision Rushcliffe published for this meeting.Source: democracy.rushcliffe.gov.uk
1.1This report provides an update from the previous report to Cabinet in March 2021 on Edwalton Golf Course (EGC) and recommends a way forward for what is a significant asset for the Council.
1.2In March 2021, Cabinet resolved to acknowledge the feedback from the Communities Scrutiny Group, which included that the endorsement of a golfing need at EGC be accepted; and the utilisation of £0.05m of 2020/21 project in- year budget efficiencies be allocated to undertake further detailed technical risk assessments of the site, and thereafter a further £0.25m for further master planning work, assuming the risks identified are not prohibitive so that a realistic and deliverable masterplan can be achieved for the site.
Recommendation
It is RECOMMENDED that Cabinet:
a) acknowledges the detailed technical assessments that have been undertaken for the par 3 course which conclude that the site could represent a good option for residential development subject to planning, although Cabinet direction is that it is retained at the present time as an important community facility;
b) acknowledges that there is likely to be sufficient housing supply in Rushcliffe to 2038 without the need to allocate this site within the Greater Nottinghamshire Strategic Plan but that it be included in a pipeline of potential sites for future consideration as part of the Local Plan process should the requirement for further sites arise, to be considered concurrently with the site as a community facility;
c) endorses further detailed design assessments for the driving range business case over the next period to establish if a standalone driving range could be delivered to provide a betterment to the golfing offer on site; and d) explores opportunities for ecological improvements and bio-diversity net gain on the main 9-hole course through improvement management and partnership working in line with the Council Climate Change Strategy objectives.
Reasons for recommendation
To ensure that the Council’s EGC asset continues to deliver maximum value for money for taxpayers across the Borough, whilst providing appropriate community infrastructure and the right level of leisure provision.
4. Supporting Information
Technical Assessments
4.1Following Cabinet approval to undertaken detailed technical assessments of the EGC site in line with the Knight Kavanagh and Page (KKP) recommendations, officers procured several technical assessments of the current par 3 course to better understand the opportunities and constraints of the site for potential redevelopment.
4.2The technical assessments provided input on the landscape, flooding and drainage, highways and transport, ecology, and topography of the par 3 course to provide a high-level indicative masterplan.
4.3The masterplan identified that given its location and proximity to services, the site was featured in the Nottinghamshire Strategic Plan Growth Options Document as a “Potential Development Site” under reference R11.1 and was confirmed to be both “Suitable” for development and a “potential area for strategic growth” by the accompanying Growth Options Study conducted by AECOM. As a result, Rushcliffe Borough Council submitted representations to the Growth Options Consultation promoting the site for residential use in March 2021.
4.4The technical assessments exercise identified a number of potential constraints within the par 3 site which include the presence of a number of trees and vegetation, overhead electricity cables and Gamston Brook, which cuts through the centre of the site. These reports have confirmed that the site is within Flood Risk Zone 1 and will not affect statutorily designated sites from an ecological perspective – options to underground the electricity cables is also a possibility.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.