It is RESOLVED that Cabinet approves the attached report both noting and agreeing to: a) the expected revenue budget efficiency for the year of £0.054m inclusive of committed reserves; b) the planned use of reserves totalling £4.140m (detailed in Appendix A of the report); c) the capital underspend of £5.1m; and d) the expected outturn position for Special Expenses of £15.7k deficit.
Word for word from the decision Rushcliffe published for this meeting.Source: democracy.rushcliffe.gov.uk
1.1This report presents the budget position for revenue and capital as at 31 December 2021. This report provides an update to the report to Cabinet on 14 December 2021 and includes the in-year variances along with variances resulting from Covid-19.
1.2Given the current financial climate, and the recovery from Covid lock down measures, it is imperative that the Council maintains due diligence with regards to its finances and ensures necessary action is taken to ensure a balanced budget is maintained.
1.3The current budget was set anticipating an adverse impact of Covid on the Council’s finances. However, a combination of service budget efficiencies, Business Rates and Government funding have helped mitigate against the financial impact of Covid income losses. The position, although currently remaining positive, is subject to risks. The reduction in the Business Rates as a result of the power station appeal, additional charity reliefs and subsequent reduction in the Business Rates Pool surplus demonstrates how volatile the the position is.
1.4A outturn surplus of £0.054m (net of reserve commitments) is anticipated as at December 2021, although this position could change if further efficiencies or pressures are identified during the final quarter of 2021-22. The reduction from Quarter 2 is mainly due to the changes in Business Rates as referred to above and commitments from the overall efficiency position (see pargagraph 4.2).
1.5Going forward there are significant budget risks such as potential changes to the Business Rates system and Fairer Funding (both likely to be from 2023/24), and government policy in relation to waste collection. In addition there is the potential impact of the power station closure (2024) and the Council’s commitment to the opportunities expected to arise from the Freeport and Development Corporation. Maintaining sufficient reserves to address significant risks remains a key objective of the Council’s Medium Term Financial Strategy (MTFS) and is good financial practice.
1.6The Capital Programme currently shows a planned underspend of £5.1m, largely due to the rephasing of payments expected for two major schemes (Bingham Hub and Crematorium) arising from revised cash flows; an extended deadline for the release of green energy grants from the LAD2 scheme; £0.228 unallocated contingency; and a saving of £100k in relation to the Skype/Teams Business Migration.
Recommendation
It is RECOMMENDED that the Cabinet approves the attached report both noting and agreeing to:
a) the expected revenue budget efficiency for the year of £0.054m inclusive of committed reserves;
b) the planned use of reserves totalling £4.140m (detailed in Appendix A);
c) the capital underspend of £5.1m; and
d) the expected outturn position for Special Expenses of £15.7k deficit.
Reasons for recommendation
To demonstrate good governance in terms of scrutinising the Council’s on-going financial position and compliance with Council Financial Regulations.
4. Supporting Evidence
Revenue Monitoring
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.