ALDERSHOT RAILWAY STATION AND SURROUNDS - VARIATION TO CAPITAL PROGRAMME

Approved Executive 1 paper

Cabinet approved this item on Tuesday 31 May 2016. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

RESOLVED that approval be given to a net reduction of £540,000 to the 2016/17 Capital Programme in respect of the Aldershot Railway Station and surrounds project (No. 5404), as set out in the Directors’ Management Board’s Report No. DMB1602 .
Word for word from the decision Rushmoor published for this meeting. Source: democracy.rushmoor.gov.uk

Follow this further

Built from Rushmoor's papers

What the report saysPro

Report to Cabinet

Background

2.1The approved Capital Programme identifies a cost estimate of £1,240,000 for the financial year 2016/17 in relation to the delivery of the Aldershot station area improvements.

2.2Aldershot railway station is an important gateway into Aldershot Town Centre, and, in partnership with the rail operator, bus operator and the Highway Authority, Rushmoor Borough Council is committed to its improvement. The site is identified for regeneration within the emerging Rushmoor Local Plan and within the adopted Aldershot Town Centre Prospectus, where it is recognised as one of four key sites.

2.3The Aldershot Station and surrounds project involves:

 significant changes to the existing forecourt of the railway station, through public realm improvements, resulting in a pedestrian friendly environment;  a realigned public transport interchange incorporating buses, taxis, cycling and a ‘kiss and drop’ facility;  the provision of a new decked car park;  unlocking the existing bus station site to deliver housing and commercial units.

2.4In addition, Hampshire County Council (HCC) is implementing transport improvements to Windsor Way to reduce unnecessary traffic flow/congestion in the town centre and create a more direct connection for commuters travelling to/from the east of Aldershot. Reduced traffic flow along Station Road will facilitate improved pedestrian links between the station gateway and the town centre.

2.5Officers are aware of local concerns in relation to the proposed scheme, particularly from residents of Kingsley Court, which sits

1 adjacent to the railway station. Further work is still required in respect of the detailed design of the proposals and concerns that have been raised to date will be taken into account and addressed. Further to this, Officers will seek to engage with local residents on revised proposals prior to any work commencing on the scheme.

Financial implications

3.1Since the Capital Programme was agreed in February, further work has been undertaken by Officers in relation to the costing of the scheme in support of an Enterprise M3 LEP Local Growth Fund bid. It is estimated that the overall cost relating to the delivery of the Aldershot Station and surrounds project is approximately £2 million. Whilst this represents an increased cost to the project against that identified within the Capital Programme for 2016/17, it is expected that £1 million of grant funding will be secured towards the works via the Local Growth Fund. To this end, a Full Business Case has been submitted to the LEP and is currently being considered by the Local Transport Board.

3.2In addition, Officers have been able to secure a financial commitment from Hampshire County Council and South West Trains totalling a combined £300,000 towards the overall cost of the project.

3.3Subsequently, the expected cost to Rushmoor Borough Council in delivering the Aldershot Station and surrounds project is approximately £700,000 (inclusive of a contingency). This represents a net reduction to the Council’s Capital Programme of £540,000 and reduces the impact on the revenue budget by lessening the impact of loss of interest. It is recommended that this reduction in project cost be reflected within a revised Capital Programme for 2016/17.

Recommendation

4.1It is recommended that Cabinet approve a variation to the Capital Programme 2016/17 in respect of the Aldershot Railway Station and surrounds project (no. 5404).

DIRECTORS’ MANAGEMENT BOARD

Contacts: Nick Irvine 01252 398739 [email protected]

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ALDERSHOT RAILWAY STATION AND SURROUNDS: VARIATION TO CAPITAL PROGRAMMEReport 158 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 7 attended
DC
Councillor David CliffordChairman, present
KM
Councillor Ken MuschampVice-Chair, present
SC
Councillor Sue CarterCommittee Member, present
BH
Councillor Barbara HurstCommittee Member, present
GL
Councillor Gareth LyonCommittee Member, present
PT
Councillor Paul TaylorCommittee Member, present
MT
Councillor Martin TennantCommittee Member, present

On this subject at Rushmoor

Search all
  1. ALDERSHOT RAILWAY STATION AND SURROUNDS - VARIATION TO CAPITAL PROGRAMMEThis decision
  2. Aldershot railway stationAgreed

More from Rushmoor Cabinet

All decisions
MeetingDecisionOutcome
20 Oct 2026 Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... Noted Open
20 Oct 2026 Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... Approved Open
20 Oct 2026 Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... Noted Open
15 Sep 2026 Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... Noted Open
15 Sep 2026 Young people’s planRESOLVED that (i) the approach to the production of the Young People’s Plan, including to support and engage with all... Agreed Open