RESOLVED that (i) the Corporate Manager – Legal Services, in consultation with the Executive Head of Finance and Major Projects and Property Portfolio Holder, be authorised to enter into the grant funding agreement with the Enterprise M3 LEP for the Aldershot Railway Station and Surrounds project, as set out in Report No. RP1923 ; (ii) the Executive Head of Regeneration and Property be authorised to apply for planning permission associated with the relocation of the field gun currently located at the entrance to the railway station and to secure other associated permissions; (iii) Council officers be authorised to work with the Aldershot Civic Society to develop a process for commissioning new public art on the railway station forecourt; (iv) the likely underspend on the Council’s contribution to the Aldershot Railway Station and Surrounds project be noted; and (v) the re-purpose of up to £75,000 of the agreed capital budget to fund new public art on the railway station forecourt, be approved.
Word for word from the decision Rushmoor published for this meeting.Source: democracy.rushmoor.gov.uk
CABINET COUNCILLOR MARTIN TENNANT MAJOR PROJECTS AND PROPERTY PORTFOLIO HOLDER 12 NOVEMBER 2019 REPORT NO. RP1923
KEY DECISION? NO
ALDERSHOT RAILWAY STATION
SUMMARY AND RECOMMENDATIONS:
This report seeks authority to enter into the grant funding agreement with the Enterprise M3 LEP for the purposes of delivering the Aldershot Railway Station and Surrounds project. The report also seeks subsequent approvals associated with relocating existing public art to facilitate the project and introducing new public art on the railway station forecourt.
It is recommended that Cabinet:
1) Delegates authority to the Corporate Legal Manager in consultation with the Executive Head of Finance and Major Projects and Property Portfolio Holder to enter into the grant funding agreement with the Enterprise M3 LEP for the Aldershot Railway Station and Surrounds project
2) Authorises the Executive Head of Regeneration and Property to apply for planning permission associated with the relocation of the field gun currently located at the entrance to the railway station, and to secure other associated permissions;
2) Authorises officers to work with Aldershot Civic Society to develop a process for commissioning new public art on the railway station forecourt;
4) Notes the underspend likely on the RBC contribution to the Aldershot Railway Station and Surrounds project and approves the repurpose of up to £75,000 of the agreed capital budget to fund new public art on the railway station forecourt.
1. INTRODUCTION
1.1The purpose of this report is to firstly seek authority enter into the grant funding agreement with the Enterprise M3 LEP for the Aldershot Railway Station and Surrounds project and to subsequently seek authority relating to two proposals for the public realm arising from project works. 2. BACKGROUND
2.1Aldershot station is an important gateway to the town. The forecourt and station approach currently experiences issues with traffic congestion and traffic movement conflicts. It does not, at present, provide a welcoming environment for residents or visitors.
2.2To address this, Hampshire County Council (HCC) and Rushmoor Borough Council (RBC), in partnership have prepared a scheme for improving the quality of routes to and from the station for pedestrians, cyclists and cars and improvements to the station environment that facilitate a new public transport interchange for bus and taxi movements and will free up the existing bus station for redevelopment. The scope of this works is referred to as the Aldershot Railway Station and Surrounds project and was the subject of a successful Business Case proposal to the Enterprise M3 LEP for grant funding. At the time of the Business Case being agreed in 2016, the funding contribution from the LEP was £900,000 and was match funded by RBC (£620,000), HCC (£180,000) and South West Trains (£100,000).
2.3The delivery of the project has experienced delays, primarily associated with the anticipated costs to provide decked car parking on site escalating beyond the project budget. Delivery timescales were also impacted by a franchise change that saw South West Trains replaced by South Western Railway.
2.4In the interim period, Officers have engaged on revisions to the scope of the project and have been able to agree a revised scope that achieves the intended outcomes of the original Business Case proposal but removes the need for the provision of the decked car park.
2.5This links to the Rushmoor Council Business Plan theme of “Place” and contributes to its work in improving Aldershot town centre.
3. DETAILS OF THE PROPOSAL
Grant Funding Agreement
3.1Having agreed the revised scope of the project works, the Council is required to formally enter into the grant funding agreement with the Enterprise M3 LEP. The revised project costs have been estimated at approximately £600,000 with the breakdown of contribution as follows:
• Rushmoor Borough Council: £100,000 • Hampshire County Council: £300,000 • Enterprise M3 LEP grant funding: £200,000
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.