CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Rushmoor Borough Council
Cabinet, Tuesday 28 June 2016 at 7.00pm

STREET HOMELESS SOLUTION - PROVISION OF A HOSTEL

Approved Executive 1 paper

Cabinet approved this item on Tuesday 28 June 2016. Below is the council's own wording, with the papers it was decided on.

Item16

Resolved

RESOLVED that (i) approval be given to seek planning permission for a change of use for the building; (ii) a variation to the Capital Programme of £20,000 in 2016/17 be approved; and (iii) a Supplementary Estimate of £34,700 in 2016/17, to reflect costs as set out in the Head of Environmental Health and Housing’s Report No. EHH1607, for which the Council had already secured grant funding, be approved .
Word for word from the decision Rushmoor published for this meeting. Source: democracy.rushmoor.gov.uk

Follow this further

Built from Rushmoor's papers

What the report saysPro

Report to Cabinet

CABINET AGENDA ITEM NO. 2 28TH JUNE 2016 Report No. EHH1607

STREET HOMELESS SOLUTION – PROVISION OF A HOSTEL

Use of former Army Barrack at Ordnance Road Aldershot for a homeless hostel and request for Capital Funding

1 Introduction

1.1Members will be aware of the current levels of street homelessness within the borough. Currently the Council is supporting eight street homeless people. This group require time-consuming support. Ideally, they require specialist housing and intervention to be able to access mainstream accommodation.

1.2Grainger Trust has offered the Council the use of an empty, former barrack building on the Wellesley site to provide accommodation for rough sleepers. The project will provide nine bed spaces for a three-year period with specialist support being provided by the Society of St. James Housing Association. Clients will be provided with care and support to address their drug, alcohol and mental health problems, with the objective of them being able to move into mainstream accommodation. The purpose of this report is to seek Cabinet approval to proceed with the project.

2 Building Proposal and Capital Costs

2.1The building identified is located on Ordnance Road Aldershot opposite Mike Jackson House, it is well screened and far enough from residential properties not to impact upon them. A lease agreement between the Council, Grainger Trust and the MOD will be in place for a three-year term. The lease will contain a conditional break clause with a 6 month notice to mitigate reputational risk to all parties by allowing the project to close should there be serious behaviour problems from the client group that impact on the local community. The building in its current form is sub-standard and a Capital budget of £20,000 is needed to meet the cost of building materials and associated planning fees. Our proposal is for nine bedrooms with communal kitchen, bathing and living space. The Council will project manage the build through Skilled Up and in partnership with the Army Training Centre. This provides free labour for the project and appropriate training opportunities for Skilled Up and Army trainees. Materials will be purchased in accordance with the Councils procurement procedures. A breakdown of the budget is attached as Appendix A.

2.2A change of use planning application from Army Barracks to Supported Residential Accommodation is required. The project will also be subject to pre-application discussion before an application is prepared or submitted. Implementation of the development will not be permitted until Planning

1 Permission is granted and any associated conditions have been discharged. Associated external alterations, should they be necessary, may also require planning permission. Cabinet is asked to approve the submission of a planning application.

3 Environmental Survey

3.1The site was used in the 1950s for tipping so an Environmental Survey has been carried out to ascertain levels of contamination and provide assurance that the site is suitable for residential use. The survey report and risk assessment is attached as Appendix B, and concludes that there is no significant contamination, which would pose a risk to human health.

3.2An asbestos survey was carried out in October 2015 and shows that there is no asbestos present within the building. A copy of the survey is attached as Appendix C.

4 Partnership support and financial commitment

4.1Interest and funding offers have been confirmed from a number of partners:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
STREET HOMELESS SOLUTION: PROVISION OF A HOSTELReport 2.3 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 7 attended
DC
Councillor David CliffordChairman, present
KM
Councillor Ken MuschampVice-Chair, present
SC
Councillor Sue CarterCommittee Member, apologies
BH
Councillor Barbara HurstCommittee Member, present
GL
Councillor Gareth LyonCommittee Member, present
PT
Councillor Paul TaylorCommittee Member, present
MT
Councillor Martin TennantCommittee Member, present

More from Rushmoor Cabinet

All decisions
MeetingDecisionOutcome
20 Oct 2026 Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... Noted Open
20 Oct 2026 Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... Approved Open
20 Oct 2026 Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... Noted Open
15 Sep 2026 Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... Noted Open
15 Sep 2026 Young people’s planRESOLVED that (i) the approach to the production of the Young People’s Plan, including to support and engage with all... Agreed Open