Resolved
RESOLVED that approval be given to a variation to the 2016/17 Capital Programme of £54,000 to enable the procurement of the repair and upgrade of the existing lift , as set out in the Solicitor to the Council’s Report No. LEG1607 .
Cabinet approved this item on Tuesday 28 June 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that approval be given to a variation to the 2016/17 Capital Programme of £54,000 to enable the procurement of the repair and upgrade of the existing lift , as set out in the Solicitor to the Council’s Report No. LEG1607 .
2.1The existing lift in the main entrance foyer at Farnborough Leisure Centre is around 30 years old and has become increasingly unreliable and with spare parts difficult to obtain resulting in extended periods when the lift is out of service.
2.2The lift is currently out of service and has been so for a number of weeks. The lift maintenance company employed by the leisure centre operator has now stated that repair of the lift is uneconomic and has informed the centre operator that even if repaired, the reliability and safety of the lift cannot be guaranteed. The lift maintenance company has reportedly now refused to carry out any work on the lift to bring it back into service.
2.3The lift provides access to the upper levels of the building for disabled swimmers, users of the gym and parents with pushchairs. There is a second lift in the building but it is some distance from the main entrance, and the unserviceable lift is the sole means of access to the gymnasium for wheelchair users and those with impaired mobility.
2.4The contractual arrangement with the operator of the leisure centre is that the operator is responsible for providing a “comprehensive ...... lift maintenance service …. including all replacement parts”. The operator is also responsible for repairing plant and equipment but where the cost exceeds £1000 the operator is only liable for the first £1000 provided the repair is not due to any failure by the operator to carry out its responsibilities. The specification assumes that the Contractor will pay and the Council will reimburse the costs in excess of £1000 (arguably index linked). The Council is responsible for repair and maintenance of structural elements (as defined, but this only includes the lift shaft and pit). Lift replacement is not covered by the contract but in view of the approach to repairs and given the operator only occupies as
1 a licensee it would be difficult to argue the operator is liable for the cost of replacement, other than for a minimal contribution.
2.5The operator may argue the Council is effectively closing the gym to a class of individuals. Were such an argument to be made then under the contract the Council is liable to reimburse loss of income if the Council requires closure of all or part of the leisure centre. For longer periods, the extent of this loss is subject to negotiation but as a guide, the contract states that for closures of less than a week the loss is the average weekly income less expenditure saved for that area. In addition to the management fee paid to the operator there is a profit share mechanism. Irrespective of whether the operator makes a claim for loss of income there may be an impact on the profit share.
3 LIFT CONSULTANT’S REPORT
3.1The independent lift consultant has reported as follows :-
i) Option 1) Repair and upgrade of existing lift. Notwithstanding the comment by the lift maintenance company, that the repair of the existing lift is uneconomic, the consultant considers that repair and up-grade of the existing lift is viable. The life of the existing lift could be extended by an estimated 5 - 10 years. The existing lift has a travel speed of 0.4 m/s.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
FARNBOROUGH LEISURE CENTRE: CONSIDERATION OF OPTIONS FOR MAIN LIFT IN FOYERReport | 211 KB | DownloadRead as text |
Follow Cabinet at Rushmoor and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Oct 2026 | Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... | Noted | Open |
| 20 Oct 2026 | Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... | Approved | Open |
| 20 Oct 2026 | Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... | Noted | Open |
| 15 Sep 2026 | Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... | Noted | Open |
| 15 Sep 2026 | Young people’s planRESOLVED that (i) the approach to the production of the Young People’s Plan, including to support and engage with all... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.