AGENDA ITEM 4
LICENSING & GENERAL PUPOSES COMMITTEE AUDIT MANAGER 27TH MARCH 2017 REPORT NO. AUD1702
INTERNAL AUDIT – AUDIT PLAN
Overview: This report is to set out the annual plan for 2017/18 and detail the work carried out in order to develop the plan in a different way to previous years.
Action required: Members are required to: Agree to the new methodology for selecting audit areas and the rolling programme to commence in 2017/18. Agree to the new monitoring arrangements for the audit plan.
1 Introduction
1.1The audit plan is produced annually in order to set out the work that will be covered within the financial year by the internal audit team. The plan needs to ensure that overall assurance of the internal control environment for the Council is covered.
1.2The plan has been developed in the same way for the last 7 years and is no longer fit for purpose. Therefore, with the Systems Thinking team, we have looked to develop a more efficient process, which is more appropriate for meeting the needs of the current environment and utilise resources more effectively.
2 Purpose of Internal Audit
2.1Internal Auditing, as defined by the Public Sector Internal Audit Standards 2013:
‘An independent, objective assurance and consultancy activity designed to add value and improve an organisations operations. It helps an organisation accomplish its objectives by bringing a systematic, disciplined approach to evaluate and improve the effectiveness of risk management, control and governance processes.’
2.2Internal Audit help the Directors Management Board demonstrate that they are managing the organisation effectively on behalf of the stakeholders.
Page 1 of 11 Furthermore, ensuring that the Council conforms to the Accounts and Audit (England) Regulations 2015:
‘5.—(1) A relevant authority must undertake an effective internal audit to evaluate the effectiveness of its risk management, control and governance processes, taking into account public sector internal auditing standards or guidance.’
2.3Internal audit carry out their activities in order to conform to the Standards and Regulation detailed above. Furthermore, work is carried out with the consideration of the external auditors to ensure that they can appropriately comment on the Council’s overall control environment.
2.4As above the purpose of internal audit is to satisfy the organisation that risks are being adequately controlled and managers are being provided with the necessary information and support to enable them to control these risks.
3 Current method for developing and communicating the audit plan
Risk Universe and Criteria
3.1The ‘risk universe’ comprises of all potential areas that could be audited within the Council. The potential auditable areas were last updated in 2014.
3.2The risk universe serves as a basis for developing the risk based audit plan. Each auditable area is rated against risk criteria, to give an overall risk score.
3.3The risk criteria were developed in March 2006 and have not been updated since. They cover the following areas:
Financial Materiality Business Risk Previous audit experience Fraud and corruption
Developing the Audit Plan
3.4The annual plan is set in March, for the year, detailing when the audits will commence. However, this is prone to changes throughout the year due to a number of factors, including: Unplanned work/ investigations Ad hoc audits taking longer than estimated (This is more prone in new areas not audited before). Concerns being raised by Members or officers
Page 2 of 11 3.5 Much of the focus when setting the audit plan is on resources available rather than for the needs of the organisation or the purpose of the Internal Audit activity.
Communication and monitoring of the plan
3.6Changes made to the plan throughout the year are not specifically reported to DMB. There is no annual reflection of the work carried out in the year against the work originally planned and why changes were necessary.
4 Why do it differently
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit: Audit PlanReport | 454 KB | DownloadRead as text |
Follow Audit and Governance Committee at Rushmoor and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Sep 2026 | Reserve Risk Assessment Update ReportRESOLVED : That the Reserve Risk Assessment Update Report be noted. | Noted | Open |
| 29 Sep 2026 | Internal Audit Progress ReportRESOLVED : That SIAP’s Report No. SIAP26/05 be noted. | Noted | Open |
| 29 Sep 2026 | Corporate Policy and Guidance and the use of the Regulation of Investigatory Powers Act 2000RESOLVED : That the Surveillance and RIPA & IPA Policy and Guidance be approved and the contents of Report No. LEG260... | Approved | Open |
| 29 Sep 2026 | Annual Ombudsman Complaint Review LetterRESOLVED : That: ( i ) the Annual Review Letter be noted; and (ii) the Council commend officers on the positive outco... | Noted | Open |
| 30 Jul 2026 | Freedom of Information - Annual Update Report 2026RESOLVED : That officers: (i) continued the work on reducing the number of overdue FOIs within the system in 2026 and... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.