CAPITAL PROGRAMME MONITORING AND FORECASTING 2016/17 - POSITION AT MARCH, 2017

Noted Executive 1 paper

Cabinet noted this item on Tuesday 4 April 2017. Below is the council's own wording, with the papers it was decided on.

Item110

Resolved

RESOLVED that (i) the latest Capital Programme monitoring position, as set out in the Head of Financial Services’ Report No. FIN1714, be noted; and (ii) the 2016/17 capital budget virement of £52,000 from the Beaumont Wall railings scheme to the main wall renovations scheme, as set out in the Report, be approved.
Word for word from the decision Rushmoor published for this meeting. Source: democracy.rushmoor.gov.uk

Follow this further

Built from Rushmoor's papers

What the report saysPro

Report to Cabinet

Recommendations

Members are requested to:

(i) Note the latest Capital Programme monitoring position. (ii) Approve a 2016/17 capital budget virement of £52,000 from the Beaumont Wall railings scheme to the Main Wall renovations scheme.

1. INTRODUCTION 1.1 This report informs Members of the position regarding the Council’s Capital Programme for 2016/17, based on the monitoring exercise carried out during February and March.

2. BACKGROUND 2.1 Financial Services, in consultation with relevant budget officers, carry out regular monitoring of the Capital Programme.

2.2A summary of the overall Capital Programme position is shown in Appendix A.

3. CURRENT POSITION 3.1 The Council approved the Revised 2016/17 Capital Programme of £27,547,000 on 23rd February 2017. Subsequently approved schemes totalling £560,000 bring the total approved Capital Programme for 2016/17 to £28,107,000.

3.2Based on the February/March 2017 monitoring exercise, the forecast outturn for 2016/17 is expected to be £25,407,000; with a forecast shortfall of £2,700,000 (net of an element of scheme overspends) against the approved Total Capital Programme of £28,107,000.

3.3Slippage amounts to £2,854,000 in the current year. The major areas of slippage in relation to the approved Capital Programme (Appendix A) are as follows:

1 Scheme Explanation £000s Loans - Farnborough International Changes to the funding model and a delay (647) Loan finalising the legal agreement have resulted in loan monies being paid out to a revised timeline than the original payment schedule.

Corporate Properties - 36 – 62 Union Street, Difficulties with reaching an agreed sale on one (614) Aldershot property, resulting in the expectation that sale completion will not be achieved until 2017/18.

Activation Aldershot - Phase 2, Town Centre Architectural design services associated with the (277) Improvements shop fronts has been carried out but the actual works to the shop fronts will not take place in the current year.

Activation Aldershot - Project 2 Phase 6, Now agreed that South West Trains will be (196) Aldershot Station carrying out the works in the following year.

Car Parks - Pay & Display Machine Some machine installation achieved in March but (169) Replacement a substantial number will now be installed in April 2017. This results in some slippage on the overall scheme to the following year. An overall saving is also now anticipated (see underspends section).

Corporate Properties - 12 Arthur Street Future Delay with determining plans for this property and (168) Use planning permission yet to be obtained.

Municipal Gardens - Playground Refurbishment The old playground equipment has been removed (152) and installation of new equipment programmed for completion in April 2017.

Corporate Properties - Property Acquisition An approval for a property purchase was granted (150) in February 2017 but acquisition is unlikely to be completed in the current year.

ICT Strategy & Customer First Projects Upgrade of the Councils backup system and (63) - Various introduction of “replication” has been deferred whilst delivery of equipment hardware and related services is achieved.

Manor Park Cottage - Refurbishment Approval for the refurbishment works was granted (53) in March 2017 and is unlikely to be completed in 2016/17.

2 Cycleway Links - Cove Brook Completion of both projects in 2016/17 has been (34) - Hazel Avenue to Arrow delayed due to delay in reaching agreement with (16) Road the Environment Agency.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
CAPITAL PROGRAMME MONITORING AND FORECASTING 2016/17: POSITION AT MARCH, 2017Report 228 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 7 attended
DC
Councillor David CliffordChairman, present
KM
Councillor Ken MuschampVice-Chair, present
SC
Councillor Sue CarterCommittee Member, present
BH
Councillor Barbara HurstCommittee Member, present
GL
Councillor Gareth LyonCommittee Member, present
PT
Councillor Paul TaylorCommittee Member, present
MT
Councillor Martin TennantCommittee Member, present

On this subject at Rushmoor

Search all
  1. CAPITAL PROGRAMME MONITORING AND FORECASTING 2016/17 - POSITION AT MARCH, 2017This decision
  2. Q4 revenue budget and capital programme monitoring and final outturn report 2022/23Noted
  3. P3 revenue budget and capital programme monitoring draft outturn report 2021/22Noted
  4. Capital programme monitoring and forecasting report p2 2021/22Noted
  5. Capital programme monitoring and forecasting report p1 2021/22Noted
  6. Capital programme monitoring and forecasting report 2020/21Noted

More from Rushmoor Cabinet

All decisions
MeetingDecisionOutcome
20 Oct 2026 Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... Noted Open
20 Oct 2026 Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... Approved Open
20 Oct 2026 Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... Noted Open
15 Sep 2026 Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... Noted Open
15 Sep 2026 Young people’s planRESOLVED that (i) the approach to the production of the Young People’s Plan, including to support and engage with all... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies