Resolved
RESOLVED that the latest Capital Programme position, as set out in Tables 1 and 2 of Report No. FIN2202, including the proposed slippage of £26.893 million, be noted.
Cabinet noted this item on Tuesday 18 January 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the latest Capital Programme position, as set out in Tables 1 and 2 of Report No. FIN2202, including the proposed slippage of £26.893 million, be noted.
This report informs Members of the latest forecast of the Council’s Capital Programme for 2021/22 based on the monitoring exercise carried out during October and November 2021.
i) Note the latest Capital Programme position, as set out in Tables 1 and 2 including the proposed slippage of £26.893m
1 INTRODUCTION
1.1This report informs Members of the latest forecast regarding the Council’s Capital Programme for 2021/22.
1.2There are some projects of material financial significance included in the Council’s approved Capital Programme for 2021/22. These projects are: (a) Regeneration – Aldershot (b) Regeneration - Civic Quarter (c) Replacement cremators, and, (d) Housing PRS
2.1Financial Services, in consultation with relevant budget officers, carry out regular monitoring of the Capital Programme.
2.2A summary of the overall position is shown in Appendix A. 3 CURRENT POSITION
3.1The Council approved the Capital Programme of £38.510m on 20 February 2021. Based on the budget monitoring process Table 1 shows the reconciliation of budget changes together with the projected actual capital expenditure for the year 2021/22.
Table 1: Analysis of capital expenditure and approved budget 2021/22
(£’000)
Total approved budget for the year 2021/22* 38,510
Plus: Additional budget approvals made for the year 2021/22 ** 611
Slippage form 2020/21 2,176
Total approved budget for 2020/21 41,297
Actual plus commitments at P2 *** 3,936
Forecast capital expenditure for the year 14,580
Net favourable variance (against approved budget) 26,716
Projected Slippage/(Pre-spend) to 2022/23 **** 26,893 Table contains roundings
* As reported to Cabinet in the Revenue Budget, Capital Programme and Council Tax report FIN2106 (20/02/2021) ** Cabinet Reports RP21035 (08/06/2021) *** Expenditure and commitments as at 30 September. An additional £3.6m of expenditure is recorded between October and December 2021 **** Projected slippage based on the forecast at Period 2.
3.2Table 2 shows the outturn forecast for each scheme with a Portfolio summary of all approved projects.
3.3The Capital Programme is a significant undertaking for the Council in terms of magnitude and complexity. The scale of the projected slippage into 2021/22 and variation in programme highlights the need for close monitoring and clear project management across the whole Council.
3.4Up to the reporting period actual expenditure including commitments is £3.9m. £15m is due to be spent by the year-end, predominantly as part of programmed regeneration. This does not include expenditure under contract for the Union Yard scheme
3.5Members have been kept updated on the progress of the major regeneration schemes during the year with specific reports on Union Yard Aldershot and the Civic Quarter Farnborough schemes. 3.6 Council approved the Union Yard regeneration scheme at their meeting on 29 July 2021 which committed the Council to around £42m of further expenditure over a 3-year period. The profile of expenditure for the current year has been agreed following the formal contract agreement and will be included in the revised capital programme in February 2022.
3.7Appendix A provides commentary on the material variations on the capital programme Table 2: Capital Programme Outturn Forecast
2021/22 2021/22 2021/22 Original Latest Outturn 2021/22 Budget Budget Forecast Variation Portfolio and Scheme (£'000) (£'000) (£'000) (£'000) Corporate Services Flexible Use of Capital Receipts 0 74 74 0 Subtotal 0 74 74 0
Customer Experience & Improvement Computer Systems 115 115 110 (5) Council Offices 33 33 33 0 Subtotal 148 148 143 (5)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CAPITAL PROGRAMME MONITORING AND FORECASTING REPORT P2 2021/22Report | 188 KB | DownloadRead as text |
Follow Cabinet at Rushmoor and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Oct 2026 | Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... | Noted | Open |
| 20 Oct 2026 | Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... | Approved | Open |
| 20 Oct 2026 | Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... | Noted | Open |
| 15 Sep 2026 | Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... | Noted | Open |
| 15 Sep 2026 | Young people’s planRESOLVED that (i) the approach to the production of the Young People’s Plan, including to support and engage with all... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.