Resolved
RESOLVED : That the Quality and Assurance Improvement Plan, as set out in the Audit Manager’s Report No. AUD1701, be endorsed.
Audit and Governance Committee decided this item on Thursday 25 May 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED : That the Quality and Assurance Improvement Plan, as set out in the Audit Manager’s Report No. AUD1701, be endorsed.
AGENDA ITEM NO. 2
LICENSING AND GENERAL PUPOSES COMMITTEE AUDIT ANAGER’S 25TH MAY 2017 REPORT NO. AUD1703
INTERNAL AUDIT – AUDIT OPINION
Summary: This report explains the legislative requirements and best practice guidance for reporting on the adequacy and effectiveness of the Council’s framework of governance, risk management and control environment and presents the Audit Manager’s opinion on the level of assurance.
Recommendations: Members are recommended to note the contents of the report, including the audit opinion, note the self-assessment exercise against the Public Sector Internal Audit Standards and endorse the Quality and Assurance Improvement Plan.
1 Introduction
1.1The Accounts and Audit Regulations (2015) require that:
“2(3) A relevant authority must ensure that it has a sound system of internal control which – a) Facilities the effective exercise of its functions and the achievement of its aims and objectives. b) Ensure that the financial and operational management of the authority is effective, and c) Includes effective arrangements for the management of risk.
2(5) A relevant authority must undertake an effective internal audit to evaluate the effectiveness of its risk management, control and governance processes, taking into account public sector internal auditing standards or guidance.”
1.2Furthermore, with effect from 1st April 2013 the Public Sector Internal Audit Standards (PSIAS) with the Local Government Application Note together supersede the 2006 CIPFA Code of Practice for Internal Audit in Local Government in the UK.
1.3In accordance with the above requirements, the Audit Manager is required to report, on an annual basis, on the overall adequacy and effectiveness of
Page 1 of 7 Rushmoor Borough Council’s framework of governance, Risk Management and control.
1.4In order to fulfil this requirement, this report will cover: The internal audit coverage, findings and performance for 2016/17 An overall assurance opinion on the adequacy and effectiveness of the Council’s framework of governance, risk management and control The result of the Public Sector Internal Audit Standards (PSIAS) self- assessment The Quality Assurance and Improvement Plan (QAIP) for the internal audit service for 2017/18.
2 Audit work for 16/17
2.1The audit work for 16/17 was agreed at the Standards and Audit Committee on the 14/3/16. As of April 2016 the Standards and Audit Committee was discontinued. As a result, internal audit now report to the Licensing and General Purpose Committee. The audit plan was communicated to this committee at the meeting on the 27/6/16.
2.211 audits were originally planned to be completed within 16/17 in order to contribute to the audit assurance opinion.
2.3Due to the following additional higher priority work being identified within 16/17 External tenants Public Sector Internal Audit Standards Heating Payments
the following audits were dropped from the plan in order to free up audit days: Heating Contract Prospect Community Centre Building Control Petty cash/ Procurement cards
2.4Therefore, only nine audits will be used to provide the audit opinion for 16/17. Although, at the time of completing this report, 1 audit was still to be completed and will be carried over into quarter 1 of 17/18.
2.58 follow-ups on recommendations made within previous audits were also carried out in 16/17 to ensure that recommendations are implemented in a timely manner.
Page 2 of 7 Audited area Completed Underway Outstanding Parking Management System 5 2 - IT audit - Express System 3 2 - Financial Grants 11 1 - HMRC compliance 4 1 2 Member/Mayoral allowances 4 1 - Planning Enforcement 6 2 - Network Security 3 2 3 Maintenance team Unable to review recommendations until Confirm Connect is in place. A further follow-up to be scheduled.
3 Audit Opinion
3.1An assurance opinion on the adequacy of the system of internal control has been given to each audit assignment completed in 16/17. See appendix A
3.2There are 5 categories of assurance that can be given:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
INTERNAL AUDIT: PUBLIC SECTOR INTERNAL AUDITING STANDARDSReport | 380 KB | DownloadRead as text |
Follow Audit and Governance Committee at Rushmoor and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Sep 2026 | Reserve Risk Assessment Update ReportRESOLVED : That the Reserve Risk Assessment Update Report be noted. | Noted | Open |
| 29 Sep 2026 | Internal Audit Progress ReportRESOLVED : That SIAP’s Report No. SIAP26/05 be noted. | Noted | Open |
| 29 Sep 2026 | Corporate Policy and Guidance and the use of the Regulation of Investigatory Powers Act 2000RESOLVED : That the Surveillance and RIPA & IPA Policy and Guidance be approved and the contents of Report No. LEG260... | Approved | Open |
| 29 Sep 2026 | Annual Ombudsman Complaint Review LetterRESOLVED : That: ( i ) the Annual Review Letter be noted; and (ii) the Council commend officers on the positive outco... | Noted | Open |
| 30 Jul 2026 | Freedom of Information - Annual Update Report 2026RESOLVED : That officers: (i) continued the work on reducing the number of overdue FOIs within the system in 2026 and... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.