RESOLVED : That (i) the audit work carried out in Quarter 1 and the update to the expected deliverables in Quarters 2 and 3, as set out in the Audit Manager’s Report No. AUD1704, be noted; and (ii) the expected deliverables for Quarter 3 be endorsed.
Word for word from the decision Rushmoor published for this meeting.Source: democracy.rushmoor.gov.uk
LICENSING AND GENERAL PURPOSES COMMITTEE AUDIT MANAGER 26TH JUNE 2017 REPORT NO. AUD1704
INTERNAL AUDIT – AUDIT UPDATE
SUMMARY: This report describes the work carried out by Internal Audit for quarter 1 and the proposed work to be delivered for quarter 2 and 3.
RECOMMENDATION: Members are requested to: i. Note the audit work carried out in quarter 1 ii. Note the update to the expected deliverables for quarter 1 and 2 iii. Endorse the expected deliverables for quarter 3
1 Introduction
1.1This report is to provide Members with: An overview of the work completed by Internal Audit for quarter 1 An update of the progress made and any changes required for the expected deliverables for quarter 1 and 2, as approved by the Committee on the 27th March 2017 A schedule of work expected to be delivered in quarter 3.
2 Resources
2.1The resources within the internal audit team are still being finalised following the Audit Manager leaving under MARS. Contractors have been commissioned to carry out some audits within quarter 2, 3 and 4 to assist the internal audit team to ensure that appropriate audit coverage for 2017/18 is provided.
3 Audit work - Q1 17/18
3.1The following audit work has been carried out within quarter 1:
Work Status Parking Machine Income This audit was brought forward from the 16/17 audit plan and finalised in Q1. A reasonable assurance opinion has been given to this area. Findings are detailed within appendix A.
Page 1 of 12 External tenants follow up A follow up was carried out on the recommendations made for the external tenants audit carried out in 2016/17. The findings from the follow up has changed the assurance opinion within this area from limited assurance to reasonable assurance. 2 recommendations have not yet been implemented. Findings are detailed within appendix A. Capital programme – This audit was brought forward from the 16/17 Activation Aldershot audit plan and is on track to be finalised within quarter 1. Details of findings will be reported to the committee at the meeting in September. Heating payments This audit was brought forward from the 16/17 audit plan and is on track to be finalised within quarter 1. Details of findings will be reported to the committee at the meeting in September.
3.2Other deliverables within quarter 1 included: The audit opinion – reported to the Committee on the 25th May 2017 The Public Sector Internal Audit Standards – reported to the Committee on the 25th May 2017
4 Update to audit work for Q1 & Q2
4.1At the meeting on the 27th March 2017, it was agreed that if any changes were required to the agreed deliverables for the quarter, in order to meet changing needs of the organisations, then this would be communicated to the committee along with the reason for the change.
4.2As at the time of this report, no changes are required to the audits expected to be delivered by quarter 2. The table below details the current status against the audits previously agreed to be delivered.
Audits/follow ups Status External tenants follow up Completed Q1 Capital projects follow up To be carried out in Q2 Aldershot/Farnborough markets follow To be carried out in Q2 up Purchase and sale of property and To be carried out in Q2 land Capital programme and accounting – To be finalised within Q1 Activation Aldershot Contract letting and tendering To be carried out in Q2 by the contract auditor Transparency code To be carried out in Q2 by the contract auditor Cyber security To be carried out in Q2 by the contract auditor
Page 2 of 12 5 Expected deliverables for Q3
5.1The work expected to be delivered in quarter 3 is detailed within the table below. The audits have been selected from the high risk areas detailed in Appendix B. As with the previous quarters, these audits can be subject to change due to the changing needs of the organisation or resource availability. An update will be provided at the September meeting.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Annual Ombudsman Complaint Review LetterRESOLVED : That: ( i ) the Annual Review Letter be noted; and (ii) the Council commend officers on the positive outco...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.