RESOLVED that (i) the appointment of Hill Investment Partnership Limited as the Council’s preferred Investment Partner, as set out in Report No. CEX1802, be approved; (ii) the commencement of a period of due diligence with the preferred partner be approved, with a further recommendation to be presented to the Cabinet and the Council in due course, with the Chief Executive authorised in the meantime to undertake necessary preliminary actions and to incur expenditure as required, within the budget agreed at (iv) below, to enable the effective establishment of an Investment Partnership; (iii) the establishment of a Shadow Partnership Board and Shadow Investment Team to oversee the development of the proposals be approved, the make-up of which in terms of Council representation being delegated to the Chief Executive, in consultation with the Council’s Monitoring Officer; and (iv) a supplementary estimate of up to £50,000 for the next phase of the process, as set out in Report No. CEX1802, be approved.
Word for word from the decision Rushmoor published for this meeting.Source: democracy.rushmoor.gov.uk
1) Approve Hill Investment Partnership Limited as the Council’s preferred investment partner.
2) Confirm that due diligence should proceed with the preferred partner with a further recommendation to be presented to Cabinet and Council in due course.
3) Confirm the establishment of a Shadow Partnership Board and Shadow Investment Team to oversee the development of proposals, the make-up of which in terms of Council representation to be delegated to the Chief Executive in consultation with the Monitoring Officer.
4) Approve a supplementary estimate of up to £50,000 for the next phase of the process as outlined within the report.
1. INTRODUCTION
1.1In May 2018 Cabinet approved the establishment of the Regenerating Rushmoor programme to drive the regeneration of both Aldershot and Farnborough. That report explained that the Council was also in the process of selecting an Investment Partner (IP) to work alongside the Council to bring forward projects within the programme. That process has now concluded. 2. BACKGROUND
2.1During the development of the regeneration programme, the Council identified the opportunity to secure a revenue income as opposed to a capital receipt from some or all of its development opportunities. In order to do this it needed to be prepared to take more of a share of development risk to secure a greater share of financial reward. The Council identified the need to enter into a form of joint venture partnership with an experienced partner in order to bring forward a number of major sites.
2.2By adopting this approach, the Council would be able to bring forward the redevelopment of some of the more challenging sites more quickly, and for the purposes of the initial agreement, the following sites were identified and included in the specification:
Union Street East, Aldershot Civic Quarter, Farnborough Parsons Barracks, Aldershot, Union Street West car park, Farnborough
2.3As the Council was not procuring works and services, the establishment of an IP was not deemed to require procurement, but, for the purposes of transparency, a selection process was proposed to ensure best value being obtained.
3. THE PROCESS
3.1The selection process was carried out through the Homes England Delivery Partner Panel 3 (DPP3) framework agreement. Homes England procured the framework through fully compliant Official Journal of the European Union (OJEU) processes and it consists of, for the South and South West Region, 37 leading national and regional housing developers and contractors.
3.2There were a number of stages to the selection process, and these, together with the number of companies who were actively involved in the process at each stage, are outlined below:
4.1Following the conclusion of the selection process, Hill Investment Partnership Limited have been identified as the Council’s preferred partner. The details of the process and the conclusions are attached as an exempt appendix.
5. NEXT STEPS
5.1The next steps for the project are to develop the business plan, legal agreements and carry out further due diligence and financial modelling to fully understand the legal and financial implications of establishing the partnership.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.