COUNCIL OFFICES IMPROVEMENT PROGRAMME

Approved Executive 1 paper

Cabinet approved this item on Tuesday 24 July 2018. Below is the council's own wording, with the papers it was decided on.

Item17

Resolved

RESOLVED that (i) the improvement projects, as set out in Report No. IT1801, be approved; (ii) the release of £95,000 from the Council’s Capital Programme in respect of the projects, as set out in the Report, be approved, subject to the preferred option in respect of the Council’s business continuity provision being agreed by the Head of IT and Facilities, in consultation with the Customer Experience and Improvement Portfolio Holder; and (iii) variations to the Council’s Capital Programme of £10,000 in respect of the relocation of Citizens Advice Rushmoor and £27,000 in respect of repairs to the passenger lift, as set out in the Report, be approved. NOTE: Cllr Barbara Hurst declared a personal but non prejudicial interest in this item in respect of her involvement as a Board member and the Council’s representative with Citizens Advice Rushmoor and, in accordance with the Members’ Code of Conduct, remained in the meeting during the discussion and voting thereon.
Word for word from the decision Rushmoor published for this meeting. Source: democracy.rushmoor.gov.uk

Follow this further

Built from Rushmoor's papers

What the report saysPro

Report to Cabinet

CABINET COUNCILLOR PAUL TAYLOR CUSTOMER EXPERIENCE AND IMPROVEMENT PORTFOLIO HOLDER 24th July 2018 REPORT NO. IT1801

COUNCIL OFFICES IMPROVEMENT PROGRAMME

SUMMARY AND RECOMMENDATIONS:

This report provides a high-level outline of the 2018/19 Council Offices improvement programme and seeks approval for accessing the current capital programme budget to implement the associated projects.

The report also sets out plans and costs to relocate the Farnborough Citizens Advice to the Council Offices, which requires additional capital funding.

In addition, urgent works are required to repair the Councils passenger lift ahead of finalising an insurance claim for these works.

It is recommended that Members:

 Agree the improvement projects outlined in this report;  Approve the release of £95,000 capital funds for the projects; and  Approve variations to the Capital Programme of £10,000 (Citizens Advice relocation) and £27,000 (passenger lift repairs - will be largely recovered by insurance).

1. INTRODUCTION

1.1The Council Plan for 2018/19 states that the Council should ‘Listen, Learn and Deliver Better’ and become customer-focussed. For the Council to achieve financial sustainability and deliver key outcomes, it will be necessary to redesign the way it currently works to deliver modern public services.

1.2The Rushmoor 2020 programme contains a Customer and Digital workstream, to enable and support new ways of working using digital technology to deliver services that are more efficient at a lower cost.

1.3To achieve these outcomes it is necessary to invest capital funds to create a modern and flexible working environment that is fit for the future and enables the delivery of our improvement and modernisation programme. 1.4 This report explains the rationale for investment in an improvement programme for the Council offices. The key principles for this work are:

 Provide a modern, clean, safe workspace environment;  Enable co-location of partners, income generation opportunities & improved collaboration;  Provide new flexible ways of working ‘Anytime Anywhere’; and  Support the ‘well-being’, flexible & workstyle HR policies currently being developed.

1.5As the proposed improvement programme incurs significant capital spend affecting the Council’s estate, any decision on these matters should be considered a key decision.

2. BACKGROUND AND CONTEXT

2.1The Council offices, a major asset, were built in 1981. The Health and Safety Executive guidelines and Building Regulations require both regular and ongoing maintenance and investment in capital works. Infrastructure investment combined with regular maintenance also minimises the insurance risk and keeps premiums stable.

2.2While our revenue budget contains adequate funding for our annual maintenance contracts, this report outlines required capital infrastructure works. This is needed to improve the Council offices and deliver the key outcomes in the Council Plan as well as to comply with legislative developments.

2.3Whilst the Council is considering the longer term options for the Civic Quarter, which may include relocation of the Council Offices, this is likely to take a number of years before it is completed. This means that there remains a requirement to maintain and develop the existing office environment.

2.4Over the last year good progress has been made on improving the Council offices which has included the following:

 Re-carpeting and redecoration of the Civic suite;  Installation of additional car parking bays;  Initial building repairs to Council mains drainage;  Improved office ‘white desking’ to support workstyle changes;  Improved café environment with new flexible working space; and  Initial lower office roof repairs.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
COUNCIL OFFICES IMPROVEMENT PROGRAMMEReport 188 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 7 attended
DC
Councillor David CliffordChairman, present
KM
Councillor Ken MuschampVice-Chair, present
BH
Councillor Barbara HurstCommittee Member, present
GL
Councillor Gareth LyonCommittee Member, present
MS
Councillor Maurice SheehanCommittee Member, present
PT
Councillor Paul TaylorCommittee Member, present
MT
Councillor Martin TennantCommittee Member, present

More from Rushmoor Cabinet

All decisions
MeetingDecisionOutcome
20 Oct 2026 Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... Noted Open
20 Oct 2026 Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... Approved Open
20 Oct 2026 Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... Noted Open
15 Sep 2026 Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... Noted Open
15 Sep 2026 Young people’s planRESOLVED that (i) the approach to the production of the Young People’s Plan, including to support and engage with all... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies