Cabinet, Tuesday 21 August 2018 at 7.00pm

ALDERSHOT CREMATORIUM - REPAIRS TO CREMATORS

Approved Executive 1 paper

Cabinet approved this item on Tuesday 21 August 2018. Below is the council's own wording, with the papers it was decided on.

Item29

Resolved

RESOLVED that (i) a supplementary estimate of £63,000 in 2018/19 to enable the urgent relining of a cremator and the replacement of the venturis and nozzles at the Aldershot Crematorium, as set out in Report No. COMM1807, be approved; and (ii) the establishment of a project to explore the feasibility, design and procurement of replacement cremators, with the final proposals being presented to the Cabinet in due course, be approved.
Word for word from the decision Rushmoor published for this meeting. Source: democracy.rushmoor.gov.uk

Follow this further

Built from Rushmoor's papers

What the report saysPro

Report to Cabinet

Summary

Following the six monthly inspection, urgent works have been identified to reline a cremator and replace venturi`s and nozzles which extract gases from the cremators at the crematorium, to ensure they remain operational.

The Council will at the end of this financial year have £600k available in reserves to replace the cremators with ones that are mercury compliant. Given the additional, spend anticipated in 2019/20 it is proposed that the Council seek specialist advice and costings on the feasibility, design and procurement of new cremators with the final project being presented to Cabinet in due course with a view to bringing forward the investment required.

Recommendation

Cabinet is recommended to approve:

 a supplementary estimate of £63k for 2018/19 to enable the urgent relining of a cremator and to replace the venturi`s and nozzles at the crematorium.

 the feasibility, design and procurement of new cremators with the final project detail being presented to Cabinet in due course with a view to bringing forward the investment required

1. Introduction

1.1This paper seeks approval for a supplementary estimate to enable urgent works to the cremators at the crematorium.

Background

2.1The Aldershot Crematorium has three cremators and through a pre-planned maintenance programme receives detailed inspections every six months. The brickwork to the cremators were relined in 2012 with the venturi`s and nozzles having been replaced in 2010.

2.2It was anticipated that all three cremators would have required either, relining or replacing and the venturi`s and nozzles replacing in 2019/20.

2.3A recent inspection identified more advanced brickwork decay and work required to the hearth in cremator one. Due to the deterioration of the venturi`s and nozzles, the suction from the cremators to the chimney has also deteriorated. 2.4 The Council currently receives a levy from each cremation through the Mercury Abatement Scheme. The Council will have accrued just over £600,000 by the end of 2018/19 towards the replacement of the existing cremators, with ones, which are mercury compliant.

3. Details of the Proposal

General

3.1Due to their poor condition the venturi`s and nozzles to all three cremators need to be replaced as soon as possible. To ensure no disruption the above works will be completed over a weekend.

3.2The walls of cremator one are very worn and the brickwork needs replacing. The hearth also requires urgent attention. These works will take around a week to complete and any disruption will be kept to a minimum.

Alternative options

3.3The following alternative option has been considered and rejected. Rather than reline cremator one the Council could try to operate with the remaining two cremators. However, this would place additional strain on the cremators and require additional staff to cover longer working hours in order to complete the current level of cremations. If a further cremator failed, the Council would have to divert cremations to other crematoriums. This would significantly reduce both income and customer service.

3.4If the venturi`s and nozzles are not replaced it is likely the cremators would cease operating due to safety concerns before the end of this year.

4. Implications / Risks

4.1The crematorium must operate in a safe manner. If the above works are not completed in a timely fashion, it is likely that one or more cremators will be taken out of commission.

Financial and resource implications

4.2The Council receives a net income of around £700k pa and carries out around 1,700 cremations a year.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ALDERSHOT CREMATORIUM: REPAIRS TO CREMATORSReport 153 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 7 attended
DC
Councillor David CliffordChairman, present
KM
Councillor Ken MuschampVice-Chair, present
BH
Councillor Barbara HurstCommittee Member, present
GL
Councillor Gareth LyonCommittee Member, present
MS
Councillor Maurice SheehanCommittee Member, apologies
PT
Councillor Paul TaylorCommittee Member, present
MT
Councillor Martin TennantCommittee Member, present

On this subject at Rushmoor

Search all
  1. ALDERSHOT CREMATORIUM - REPAIRS TO CREMATORSThis decision
  2. Aldershot crematorium - proposal to undertake full refurbishment of existing facilityApproved
  3. Aldershot crematorium - proposal to undertake feasibility study to inform future investment optionsApproved

More from Rushmoor Cabinet

All decisions
MeetingDecisionOutcome
20 Oct 2026 Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... Noted Open
20 Oct 2026 Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... Approved Open
20 Oct 2026 Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... Noted Open
15 Sep 2026 Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... Noted Open
15 Sep 2026 Young people’s planRESOLVED that (i) the approach to the production of the Young People’s Plan, including to support and engage with all... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies