RESOLVED that : (a) the total funding requirement of £4.726 million, as set out in Report No. OS2312 , be approved, broken down as follows: - refurbishment of Aldershot Crematorium - £3.537 million - supply and installation of a new fully functional cremator to accompany existing, with abatement and DeNOx capability - £0.9 million - refurbishment of the chapels at the Redan Road Cemetery to be used as a temporary facility during the main works - £0.289 million; (b) the impact on the 2024/25 budget, which would require additional costs of around £0.457 million to be incorporated into the Medium-Term Financial Strategy for consideration as part of the 2024/25 budget setting process, be noted, along with the fact that, from 2025/26 onwards, surplus funds of around £0.2 million would be available to contribute towards future revenue budgets ; and (ii) RECOMMENDED TO THE COUNCIL that approval be given to an additional capital allocation of £1.152 million for the crematorium refurbishment project, over and above the £3.574 million already agreed as part of the existing Capital Programme.
Word for word from the decision Rushmoor published for this meeting.Source: democracy.rushmoor.gov.uk
This report sets out the full business case for a major refurbishment of Aldershot Crematorium and requests the approval of capital funding to progress the scheme through to development.
The report also sets out the case for the refurbishment of the chapels at Redan Road Cemetery to be used as a temporary facility for services whilst the works at the main site take place.
Recommendations
Cabinet is recommended to:
• Approve a total funding requirement of £4.726m, broken down as follows: o Refurbishment of Aldershot Crematorium - £3.537m o Supply and installation of a new fully functional cremator to accompany existing, with abatement and DeNOx capability - £0.9m o Refurbishment of the chapels at Redan Road Cemetery to be used as a temporary facility during the main works - £0.289m
• Recommend to Council that an additional capital allocation of £1.152m is approved for the crematorium refurbishment project, over and above the £3.574m already agreed as part of the existing Capital Programme
• Note the impact on the 2024/25 budget which will require additional costs of c.£457k to be incorporated into the MTFS for consideration as part of the 2024/25 budget setting process. Also, that from 2025/26 onwards surplus funds of c.£200k will be available to contribute towards future revenue budgets. 1. BACKGROUND AND CONTEXT
1.1The Park Crematorium is located in the south-east corner of the borough, adjacent to Aldershot Park. It was opened in the Summer of 1960, and sits on 16 acres of land. The site contains a single large building, an 80-space car park, and grounds housing gardens of remembrance. The building contains a chapel that can accommodate up to 120 mourners, (80 seated), an area housing three cremators, a memorial room, waiting room, offices, toilets and a number of small ancillary rooms.
1.2The venue is open five days a week, (Monday to Friday), and currently holds around 1,500 cremations a year. The building was last fully refurbished in 1996/97. Since this time, whilst regular maintenance has taken place, there has been no major investment in refurbishment.
1.3The operation of the crematorium generates a surplus on operational activities and consequently a considerable contribution to the Council’s annual General Fund budget position. Income for the 2022/23 financial year totalled £1.642m, against expenditure of £1.106m, generating a surplus on activities of £536,000. A similar sum of c.£500,000 net income is anticipated as part of the current 2023/24 revenue budget.
2. RATIONALE
2.1Due to the age of the facility and the heavy operational demands placed on the Aldershot Crematorium, regular extensive maintenance is required. The Council’s most recent condition survey has indicated that significant repair and refurbishment works are also now required in addition to the regular maintenance regime. Given the scale of identified repairs and refurbishment requirements, it is appropriate that the Council considers the best approach to the continuous provision of crematorium services.
2.2There are a number of factors to take into account when considering the rationale for investing in the crematorium:
• ‘Improving facilities at Aldershot Crematorium’ is a priority identified in the Rushmoor Council Business Plan, 2023 to 2026.
• The Office of National Statistics predicts the UK’s death rate to increase significantly over the next 50 years, placing additional demand on crematoria nationally for the foreseeable future.
• Meanwhile, the population in Rushmoor is forecast to increase steeply over the next few years, with the percentage of over 65’s rising considerably quicker than the UK average.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.