Resolved
RESOLVED that (i) The latest Capital Programme monitoring position, as set out in Report No. FIN1925, be noted ; and (ii) the additional capital requests for 2019/20, as set out in the Report, be approved.
Cabinet noted this item on Tuesday 20 August 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that (i) The latest Capital Programme monitoring position, as set out in Report No. FIN1925, be noted ; and (ii) the additional capital requests for 2019/20, as set out in the Report, be approved.
This report informs Members of the latest forecast of the Council’s Capital Programme for 2019/20 based on the monitoring exercise carried out during June 2019.
Members are requested to:
i) Members are requested to note the latest Capital Programme position. ii) Approve the additional capital requests during 2019/20
1 INTRODUCTION
1.1This report informs Members of the latest forecast regarding the Council’s Capital Programme for the first quarter of 2019/20, based on the monitoring exercise carried out during June.
2.1Financial Services, in consultation with relevant budget officers, carry out regular monitoring of the Capital Programme.
2.2A summary of the overall position is shown in Appendix A.
2 CURRENT POSITION
3.1The Council approved the Capital Programme of £70.231m on 21 February 2019.
3.2Based on the June 2019 monitoring exercise Table 1 shows the current approved budget together with the projected actual capital expenditure for the year 2019/20. Table 1: Analysis of capital expenditure and approved budget 2019/20 £000’s
Total approved budget for the year 2019/20 70,231
Additional budget approvals made for the year 2019/20 (31,862)
Slippage form 2018/19 34,012
Total approved budget for 2019/20 72,381
Actual plus commitments as at Quarter 1 29,688
Forecast capital expenditure for the year 72,244
Net favourable variance (against approved budget) (137)
Slippage/(Pre-spend) to 2020/21 (414)
3.2There are some projects of major financial significance included in the Council’s approved Capital Programme for 2019/20. These projects are: (a) Aldershot Town Centre Integration and Union Street (b) Civic Quarter development (c) finalisation of a loan to Farnborough International, and, (d) further acquisition of investment properties.
3.3A Portfolio summary of all approved projects is shown at Appendix A to this report. This Appendix includes a list of all expenditure and grant/contribution variations that have been approved since Full Council approved the Estimate for 2019/20 on 21 February 2019 for the financial year 2019/20.
3.4The Capital Programme is a significant undertaking for the Council in terms of magnitude and complexity. The scale of slippage into 2019/20 and variation in programme highlights the need for close monitoring and clear project management across the whole Council.
3.5During the year to date actual expenditure including commitments is £29.7m. £42.3m is due to be spent by the year-end, predominantly as part of programmed regeneration and investment property purchases.
3.6Additional approvals of -£31.9m since budget approval relates to funds being drawn forward into 2018/19 to facilitate regeneration and investment property purchases. The timing of any property purchase can be fluid and any movement in the capital programme is reported for approval.
3.7As part of the budget setting process for the 2019/20 capital programme, several items were subject to business cases. The following table sets out the IT and Rushmoor 2020 projects that require approval to proceed: Table 2: Capital business cases
3.8The following are additional approvals requested to facilitate capital projects within 2019/20:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CAPITAL PROGRAMME MONITORING AND FORECASTING 2019/20: POSITION AT JULY, 2019Report | 280 KB | DownloadRead as text |
Follow Cabinet at Rushmoor and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Oct 2026 | Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... | Noted | Open |
| 20 Oct 2026 | Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... | Approved | Open |
| 20 Oct 2026 | Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... | Noted | Open |
| 15 Sep 2026 | Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... | Noted | Open |
| 15 Sep 2026 | Young people’s planRESOLVED that (i) the approach to the production of the Young People’s Plan, including to support and engage with all... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.