Resolved
That the audit work carried out in quarter 1 2020/21, including work slipped from quarter 4 2019/20, and the expected deliverables for quarter 2 2020/21, as set out in the Audit Manager’s Report No. AUD20/06, be noted.
Audit and Governance Committee noted this item on Tuesday 28 July 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
That the audit work carried out in quarter 1 2020/21, including work slipped from quarter 4 2019/20, and the expected deliverables for quarter 2 2020/21, as set out in the Audit Manager’s Report No. AUD20/06, be noted.
LICENSING, AUDIT AND GENERAL PURPOSES COMMITTEE
AUDIT MANAGER 28th JULY 2020 REPORT NO. AUD 20/06
INTERNAL AUDIT – AUDIT UPDATE
SUMMARY: This report describes the work carried out by Internal Audit for quarter 1.
RECOMMENDATION: Members are requested to: i. Note the audit work carried out in quarter 1, including the work slipped from quarter 4 2019/20. ii. Note the update to the expected deliverables for quarter 2.
1 Introduction
1.1This report is to provide Members with: • An overview of the work completed by Internal Audit for Q1 and to date for Q2 2020/21. • A schedule of work expected to be delivered Q2 and Q3 2019/20.
2 Audit work – Q1 20/21
2.1The following audit work has been carried out within quarter 1:
Work Status Audit findings – Appendix A of this report
Treasury Management This audit was carried out by the contract auditors. A substantial assurance opinion has been given to this area. Findings are detailed within Appendix A. Estates Management and This audit was carried out by the contract auditors. Commercial Lettings A limited assurance opinion has been given to this area. Findings are detailed within Appendix A. PCI DSS This audit was carried out by the contract auditors. A reasonable assurance opinion has been given to this area. Findings are detailed within Appendix A. Audit work in progress SANGS/S106 The draft report is currently being reviewed by management and will be reported at the Committee meeting in September. Capital Project (Ski Slope The draft report is currently being reviewed by Maintenance) management and will be reported at the Committee meeting in September. Capital Programme The draft report is currently being reviewed by Management management and will be reported at the Committee meeting in September. Petty Cash Testing has been completed and a report on the findings is currently being drafted. Housing faster payment This was an area not previously within the audit plan. Testing has been completed and a report on the findings is currently being drafted. Housing company/RDP Testing is currently being carried out. set up Alderwood Leisure Centre Testing is currently being carried out. Car Park Income Consultancy work is currently being carried out to Reconciliation - review the income reconciliation. Consultancy Building Control The draft report is currently being reviewed by the Partnership Director at Hart Council as the report deals with elements related to the partnership with Hart Council. This report will be reported at the Committee meeting in July.
2.2Other deliverables:
Audit have been providing assistance to the organisation with regards to assurance for elements relating to Covid-19 and contributing to one of the covid-19 recovery workstreams.
3 Expected deliverables for Q2 & Q3 2020/21 3.1 The following changes will be made to quarter 2 work previously planned within the audit update provided to the Committee in May 2020: • PCNs – Due to changes within the parking team the audit has been deferred until August to ensure that there is staff availability within the parking team to assist with the audit process. • Legal system set up – due to other higher priority reviews being carried out this will be deferred to 2021/22 audit plan.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit: Audit UpdateReport | 352 KB | DownloadRead as text |
Follow Audit and Governance Committee at Rushmoor and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Sep 2026 | Reserve Risk Assessment Update ReportRESOLVED : That the Reserve Risk Assessment Update Report be noted. | Noted | Open |
| 29 Sep 2026 | Internal Audit Progress ReportRESOLVED : That SIAP’s Report No. SIAP26/05 be noted. | Noted | Open |
| 29 Sep 2026 | Corporate Policy and Guidance and the use of the Regulation of Investigatory Powers Act 2000RESOLVED : That the Surveillance and RIPA & IPA Policy and Guidance be approved and the contents of Report No. LEG260... | Approved | Open |
| 29 Sep 2026 | Annual Ombudsman Complaint Review LetterRESOLVED : That: ( i ) the Annual Review Letter be noted; and (ii) the Council commend officers on the positive outco... | Noted | Open |
| 30 Jul 2026 | Freedom of Information - Annual Update Report 2026RESOLVED : That officers: (i) continued the work on reducing the number of overdue FOIs within the system in 2026 and... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.