Resolved
RESOLVED that (i) the draft Capital Programme outturn position for 2019/20, as set out in Report No. FIN2025, be noted; (ii) the slippages totalling £4.188 million from 2019/20 to 2020/21, as set out in the Report, be approved.
Cabinet noted this item on Tuesday 15 September 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that (i) the draft Capital Programme outturn position for 2019/20, as set out in Report No. FIN2025, be noted; (ii) the slippages totalling £4.188 million from 2019/20 to 2020/21, as set out in the Report, be approved.
This report sets out the provisional outturn position on the General Fund Capital Programme for the 2019/20 financial year (subject to audit).
Members are requested to:
i) Note the draft Capital Programme outturn position for 2019/20. ii) Approve the slippage £4.188m from 2019/20 to 2020/21
1 INTRODUCTION
1.1This report sets out the Capital Programme outturn position for the 2019/20 financial year and provide members with an overview of the performance and any material variations to budgets, highlighting key issues and actions taken if required.
1.2Due to the complexity of some of the issues highlighted within the report and volume of information, it would be helpful where members have questions on matters of detail if they could be referred to the report author or the appropriate Head of Service before the meeting.
2 CAPITAL PROGRAMME OUTTURN
2.1The Council approved the revised Capital Programme of £50.628m at its meeting on 20 February 2020.
2.2The Capital Outturn is summarised in Table 1 below Table 1: Capital Programme Summary
(£’000)
Total approved budget for the year 2019/20 50,628
Plus: Additional budget approvals made for the year 2019/20 96
Final approved budget for 2019/20 50,714
Actual capital expenditure for the year 46,156
Net variance (against approved budget) 4,458
Slippage/(Pre-spend) to 2020/21 4,188
2.3The 2019/20 Capital Programme included the following significant projects: • Commercial Properties • Aldershot Town Centre Regeneration • Enhancement of Operational Assets • Improvement Grants (e.g. Disabled Facilities Grants)
2.4A summary of the Capital Programme outturn is shown in Table 2. The main variation within the capital programme is largely due to timing differences on Commercial Properties (£1.918m), Union Street Aldershot (£0.415m), and Housing Matters (£0.713m). A number of variations were identified in the Q3 Capital Programme monitoring report to Cabinet (April 2020). This report only provides commentary on the significant year-end variations.
2.5In most cases, the underspend on these significant schemes is treated as slippage from 2019/20 to 2020/21. The major variations are summarised below. • Commercial Properties – Voyager House: £1.9m slippage from 2019/20 to 2020/21. As reported in the Q3 Capital Programme monitoring report, there was a delayed start to site works. The project is expected to be completed in Q2/Q3 2020. • Union Street, Aldershot: £0.415m slippage from 2019/20 to 2020/21 owing to additional time required to complete the final elements of site assembly. As reported to Cabinet in the Quarterly Performance report in August 2020, the Council continues to make good progress towards the completion of site assembly and has now secured all freehold interests following the acquisition of 51 High Street. It is anticipated that vacant possession of all remaining interests will be resolved in Q2 2020. Due diligence work has begun in relation how the Council will deliver the permitted scheme, considering viability, funding options and procurement routes and is aiming to have concluded this work in Q3 2020. • Housing Matters: £0.713m slippage from 2019/20 to 2020/21. As reported to members in the Q3 Capital Programme monitoring report, the Housing Company was not established until April 2020 following formal incorporation. For reference, Council approved the Housing Company’s Business Plan in February 2020.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CAPITAL PROGRAMME OUTTURN 2019/20Report | 179 KB | DownloadRead as text |
Follow Cabinet at Rushmoor and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Oct 2026 | Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... | Noted | Open |
| 20 Oct 2026 | Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... | Approved | Open |
| 20 Oct 2026 | Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... | Noted | Open |
| 15 Sep 2026 | Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... | Noted | Open |
| 15 Sep 2026 | Young people’s planRESOLVED that (i) the approach to the production of the Young People’s Plan, including to support and engage with all... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.