RESOLVED that (i) the latest Capital Programme monitoring position, as set out in Tables 1 and 2 of Report No. FIN2029, be noted ; (ii) the virement of £15,000 budget from Telephony Call Centre Upgrade to Ice Programme – Modernising Corporate and Service Systems be approved; (iii) the virement of £40,000 budget from App development of Love Rushmoor to Ice Programme – Modernising Corporate and Service Systems be approved; and (iv) the additional capital funding requests , as set out in paragraph 3.9 of the Report, be approved.
Word for word from the decision Rushmoor published for this meeting.Source: democracy.rushmoor.gov.uk
This report informs Members of the latest forecast of the Council’s Capital Programme for 2020/21 based on the monitoring exercise carried out during September 2020.
Recommendation
Members are requested to:
i) Note the latest Capital Programme position, as set out in Tables 1 and 2. ii) Approve the virement of £15k budget from Telephony Call Centre Upgrade to ICE Programme – Modernising Corporate and Service Systems iii) Approve the virement of £40k budget from App development of Love Rushmoor to ICE Programme – Modernising Corporate and Service Systems iv) Approve the additional capital funding requests, as set out in paragraph 3.9
1 INTRODUCTION
1.1This report informs Members of the latest forecast regarding the Council’s Capital Programme for 2020/21, based on the monitoring exercise carried out during September.
1.2There are some projects of major financial significance included in the Council’s approved Capital Programme for 2020/21. These projects are: (a) Aldershot Town Centre Integration and Union Street (b) Civic Quarter development (c) replacement cremators (d) Voyager House conversion (e) Housing PRS, and, (f) further acquisition of investment properties.
Background
2.1Financial Services, in consultation with relevant budget officers, carry out regular monitoring of the Capital Programme.
2.2A summary of the overall position is shown in Appendix A. 3 CURRENT POSITION
3.1The Council approved the Capital Programme of £52.226m on 20 February 2020. Based on June 2020 monitoring exercise Table 1 shows the reconciliation of budget changes together with the projected actual capital expenditure for the year 2020/21.
Table 1: Analysis of capital expenditure and approved budget 2020/21
(£’000)
Total approved budget for the year 2020/21* 52,226
Plus: Additional budget approvals made for the year 2020/21 ** (115)
Slippage form 2019/20 4,188
Total approved budget for 2020/21 56,299
Actual plus commitments as at Quarter 2 3,516
Forecast capital expenditure for the year 33,311
Net favourable variance (against approved budget) (22,988)
Projected Slippage/(Pre-spend) to 2021/22 *** 23,111
* As reported to Cabinet in the Revenue Budget, Capital Programme and Council Tax report FIN2007 (04/02/2020) ** Cabinet Reports OS1915 (16/12/2019), RP1903 (05/02/2019), RP2001 (07/01/2020), FIN2023
*** Projected slippage based on the forecast at Q2. Regeneration scheme budgets will be reprofiled
3.2Table 2 shows the outturn forecast for each scheme with a Portfolio summary of all approved projects is shown at Appendix A to this report. This Appendix includes a list of all expenditure and grant/contribution variations that have been approved since Full Council approved the Estimate for 2020/21 on 20 February 2020.
3.3The Capital Programme is a significant undertaking for the Council in terms of magnitude and complexity. The scale of the projected slippage into 2020/21 and variation in programme highlights the need for close monitoring and clear project management across the whole Council.
3.4During the year-to-date actual expenditure including commitments is £3.5m. £33.3m is due to be spent by the year-end, predominantly as part of programmed regeneration and investment property purchases. It is worth noting that these schemes a spread over multiple financial years and a variation on the budget in a given financial year does not necessarily mean the project is unable to deliver the intended outcomes. 3.5 Since budget approval £95k of the 2020/21 Civic Quarter was brought forward into 2019/20 related to feasibility and design work for the leisure centre and demolition and other pre-development work associated with Elles Hall. A further £20k budget for Aldershot Park Angling Club improvement project has been removed as the project is no longer being undertaken.
3.6Appendix B sets out the details in relation to:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.