Internal Audit - Audit Update

Noted Finance 1 paper

Audit and Governance Committee noted this item on Monday 28 March 2022. Below is the council's own wording, with the papers it was decided on.

Item45

Resolved

RESOLVED : That the Audit Manager’s Report No. AUD2205 be noted.
Word for word from the decision Rushmoor published for this meeting. Source: democracy.rushmoor.gov.uk

Follow this further

Built from Rushmoor's papers

What the report saysPro

Report to Audit and Governance Committee

CORPORATE GOVERNANCE AUDIT MANAGER AUDIT AND STANDARDS COMMITTEE REPORT NO. AUD 22/05

28 MARCH 2022

INTERNAL AUDIT – AUDIT UPDATE

SUMMARY: This report describes: • The work carried out by Internal Audit since the last report; • An update on the overall progress on the 2021/22 Audit Plan, and • An update on outstanding audit issues from reports issued in 2019/20 & 2020/21.

RECOMMENDATION: Members are requested to: i. Note the audit work carried out in Quarter 3 to date. ii. Note the update to the expected deliverables for Quarter 4. iii. Note the outstanding high-risk audit issues and engagement by the Services to address them.

1 Introduction 1.1 This report is to provide Members with: • An overview of the work carried out by Internal Audit in Q3 2021/22 to date; • An update on progress towards the Audit Plan for 2021/22; • A schedule of work expected to be delivered in Q4; and • An update on the outstanding audit issues from Internal Audit reports covering 2019/20 & 2020/21 focusing on the high-risk issues.

2 Overview of Work Carried Out in Q3 to date 2.1 Since the last report, Internal Audit continued to work with Heads of Service and Service Managers to action and update the outstanding audit issues from 2019/20 and 2020/21 Audit reports. 2.2 Internal Audit issued the audit report for Corporate Risk Management. 2.3 Internal Audit continues to audit the Voyager House Capital Project. However, fieldwork progress is slow, as the key staff involved have left the Council. 2.4 Internal Audit is also involved in the Union Yard Capital Project in a consultative capacity. 2.5 Wokingham Borough Council (WBC), under a s113 Agreement to conduct audits on behalf of Internal Audit, is finalising audits in Finance on Insurance and National Non-Domestic Rates (NNDR). 2.6 WBC has also commenced an audit in Finance on the Sales Ledger. The Audit Brief has been issued and fieldwork is underway. 2.7 The Interim Audit Manager has recently received the management responses from Finance for the Purchase Ledger (2020/21) and FMS & Bank

Page 1 of 17 CORPORATE GOVERNANCE AUDIT MANAGER AUDIT AND STANDARDS COMMITTEE REPORT NO. AUD 22/05

28 MARCH 2022

Reconciliations (2021/22) audits. These will be reported on in the next Committee meeting.

3 Progress towards the 2021/22 Audit Plan 3.1 Since the last update to the Committee, there have been no further changes to the 2021/22 Audit Plan.

3.2The table below provides a summary of progress relevant to the 2021/22 Audit Plan:

Audit Status Number of reviews % Finalised 4 22.2 Draft report with Auditee for 3 16.7 management responses In progress 3 16.7 Not yet started 1 5.5 Postponed to 2022-23 5 27.8 Cancelled 2 11.1 Total 18 100%

3.3The table shows that 9 of the 11 audits (82%) to be delivered in 2021/22 are completed, being finalised or in progress. However, the remaining audit, on the CIPFA Financial Management Code, is unlikely to commence in Q4.

4. Audit Work Completed

4.1The table below provides an overview of the assurance opinions, given to completed audits since the last update, based on Internal Audit’s assessment of the control environment:

Audit Title Assurance Recommendations by Priority Opinion High Medium Low 2021/22 Internal Audit Plan Corporate Risk Reasonable 2 4 0 Management

4.2The table above highlights one audit for the Assistant Chief Executive (ACE). The two high risk-rated issues relate to the risk management process and key person risk.

The issue with the risk management process is that its current structure and efficiency may not allow key risks to RBC to be identified and managed, as the risk identification process has not been consistent. Risks have been identified Page 2 of 17 CORPORATE GOVERNANCE AUDIT MANAGER AUDIT AND STANDARDS COMMITTEE REPORT NO. AUD 22/05

28 MARCH 2022

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit: Audit UpdateReport 339 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 14 attended
JA
Councillor Jessica AutonCommittee Member, apologies
JB
Councillor Jib BelbaseCommittee Member, present
JC
Councillor Jonathan CantyReserve, present as substitute
SC
Councillor Sue CarterChairman, present
SC
Councillor Sophia ChoudharyCommittee Member, apologies, sent representative
AC
Councillor Abul ChowdhuryCommittee Member, present
PC
Councillor Peter CullumVice-Chair, present
TD
Mr. Tom DaviesCo-Optee, present
KD
Councillor Keith DibbleReserve, present as substitute
CG
Councillor Christine GuinnessCommittee Member, present
AH
Councillor Ashley HalsteadCommittee Member, present
PK
Councillor Prabesh KCCommittee Member, present

All 14 on the meeting page

On this subject at Rushmoor

Search all
  1. Internal Audit - Audit UpdateThis decision
  2. Internal Audit Progress ReportNoted
  3. Internal Audit - Audit Charter and Audit Plan 2026/27Approved
  4. Internal Audit - Progress ReportNoted
  5. Internal Audit - Audit Progress Report UpdateNoted
  6. Internal Audit - External Quality Assessment - Final ReportNoted

More from Rushmoor Audit and Governance Committee

All decisions
MeetingDecisionOutcome
29 Sep 2026 Reserve Risk Assessment Update ReportRESOLVED : That the Reserve Risk Assessment Update Report be noted. Noted Open
29 Sep 2026 Internal Audit Progress ReportRESOLVED : That SIAP’s Report No. SIAP26/05 be noted. Noted Open
29 Sep 2026 Corporate Policy and Guidance and the use of the Regulation of Investigatory Powers Act 2000RESOLVED : That the Surveillance and RIPA & IPA Policy and Guidance be approved and the contents of Report No. LEG260... Approved Open
29 Sep 2026 Annual Ombudsman Complaint Review LetterRESOLVED : That: ( i ) the Annual Review Letter be noted; and (ii) the Council commend officers on the positive outco... Noted Open
30 Jul 2026 Freedom of Information - Annual Update Report 2026RESOLVED : That officers: (i) continued the work on reducing the number of overdue FOIs within the system in 2026 and... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies