Resolved
RESOLVED : That the Audit Manager’s Report No. AUD2209 be noted.
Audit and Governance Committee noted this item on Thursday 26 May 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED : That the Audit Manager’s Report No. AUD2209 be noted.
CORPORATE GOVERNANCE AUDIT MANAGER AUDIT AND STANDARDS COMMITTEE REPORT NO. AUD 22/09
26 MAY 2022
INTERNAL AUDIT – AUDIT UPDATE
SUMMARY: This report describes: • The work carried out by Internal Audit since the last report; • An update on the overall progress on completing the 2021/22 Audit Plan; and • An update on outstanding audit issues from reports issued in 2019/20 & 2020/21.
RECOMMENDATION: Members are requested to: i. Note the audit work carried out in Quarters 3 & 4 to date. ii. Note the update to the expected deliverables for Quarter 1 2022/23. iii. Note the outstanding high-risk audit issues and engagement by the Services to address them.
1 Introduction 1.1 This report is to provide Members with: • An overview of the work carried out by Internal Audit in Q3 & Q4 2021/22 to date; • An update on progress towards completing the Audit Plan for 2021/22; • A schedule of work expected to be delivered in Q1 2022/23; and • An update on the outstanding audit issues from Internal Audit reports covering 2019/20 & 2020/21 focusing on the high-risk issues.
2 Overview of Work Carried Out in Q3 & Q4 to date 2.1 Since the last report, Internal Audit continued to work with Heads of Service and Service Managers to action and update the outstanding audit issues from 2019/20 and 2020/21 Audit reports. 2.2 Internal Audit issued the audit reports for the Purchase Ledger (2020/21), FMS & Bank Reconciliations, National Non-Domestic Rates (NNDR) Billing, Collection & Recovery and Insurance (Assets). 2.3 Internal Audit is finalising the audit the Voyager House Capital Project. However, fieldwork progress has been slow, as the key staff involved have left the Council. 2.4 Internal Audit is also involved in the ongoing Union Yard Capital Project in a consultative capacity.
Page 1 of 17 2.5 Wokingham Borough Council (WBC), under a s113 Agreement to conduct audits on behalf of Internal Audit, is progressing an audit in Finance on the Sales Ledger, which should be finalised soon. 2.6 In Q4 Internal Audit was developing the Audit Plan for 2022/23, as well as the other reports that were presented at the last Committee meeting.
3 Progress towards completing the 2021/22 Audit Plan 3.1 Since the last update to the Committee, there have been no further changes to the 2021/22 Audit Plan.
3.2The table below provides a summary of progress relevant to the 2021/22 Audit Plan:
Audit Status Number of reviews % Finalised 7 38.9 Draft report with Auditee for 0 0 management responses In progress 3 16.7 Not yet started 1 5.5 Postponed to 2022/23 5 27.8 Cancelled 2 11.1 Total 18 100%
3.3The table shows that 10 of the 11 audits (91%) to be delivered in 2021/22 are completed, being finalised or in progress. However, the remaining audit, on the CIPFA Financial Management Code, should commence in Q1 2022/23.
4. Audit Work Completed
4.1The table below provides an overview of the assurance opinions, given to completed audits since the last update, based on Internal Audit’s assessment of the control environment:
Audit Title Assurance Recommendations by Priority Opinion High Medium Low 2020/21 Internal Audit Plan Purchase Limited 3 3 2 Ledger 2021/22 Internal Audit Plan FMS & Bank Substantial 0 2 2 Reconciliations NNDR – Billing, Reasonable 1 7 3 Collection & Recovery Insurance Limited 4 7 0 (Assets) Page 2 of 17 4.2 The table above highlights three audits for Finance, including one from 2020/21, and a joint Finance and Property audit. There was a total of eight high-risk issues in three of the reports.
For the Purchase Ledger audit (2020/21), the three high-risk issues were all repeat findings from the previous audit in 2017/18: • A lack of segregation of duties and limited controls in the Purchase Ledger system; • A lack of clarification over exemption from complying with the Finance Procedure Rules; and • A lack of validity checks on new suppliers. The Executive Head of Finance has agreed a target date of 30 September 2022, which will be 4 years from the date these issues were first raised.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit UpdateReport | 338 KB | DownloadRead as text |
Follow Audit and Governance Committee at Rushmoor and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Sep 2026 | Reserve Risk Assessment Update ReportRESOLVED : That the Reserve Risk Assessment Update Report be noted. | Noted | Open |
| 29 Sep 2026 | Internal Audit Progress ReportRESOLVED : That SIAP’s Report No. SIAP26/05 be noted. | Noted | Open |
| 29 Sep 2026 | Corporate Policy and Guidance and the use of the Regulation of Investigatory Powers Act 2000RESOLVED : That the Surveillance and RIPA & IPA Policy and Guidance be approved and the contents of Report No. LEG260... | Approved | Open |
| 29 Sep 2026 | Annual Ombudsman Complaint Review LetterRESOLVED : That: ( i ) the Annual Review Letter be noted; and (ii) the Council commend officers on the positive outco... | Noted | Open |
| 30 Jul 2026 | Freedom of Information - Annual Update Report 2026RESOLVED : That officers: (i) continued the work on reducing the number of overdue FOIs within the system in 2026 and... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.