CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Rushmoor Borough Council
Audit and Governance Committee, Wednesday 31 January 2024 at 7.00pm

Internal Audit - Audit Update

Noted Finance 1 paper

Audit and Governance Committee noted this item on Wednesday 31 January 2024. Below is the council's own wording, with the papers it was decided on.

Item36

Resolved

RESOLVED : That the Audit Manager’s Report No. AUD2401 be noted.
Word for word from the decision Rushmoor published for this meeting. Source: democracy.rushmoor.gov.uk

Follow this further

Built from Rushmoor's papers

What the report saysPro

Report to Audit and Governance Committee

CORPORATE GOVERNANCE AUDIT MANAGER AUDIT AND STANDARDS COMMITTEE REPORT NO. AUD 24/01

31st JANUARY 2024

INTERNAL AUDIT – AUDIT UPDATE

SUMMARY: This report describes: • A progress update on the 2023/24 Audit Plan.

RECOMMENDATION: Members are requested to: i. Note the audit work completed. ii. Note the update to the deliverables for Quarters 4.

1 Introduction 1.1 This report is to provide Members with: • An overview of the work completed towards the 2023/24 audit plan; • A progress update on the 2023/24 Audit Plan; and • A schedule of work to be delivered in Q4.

2 Audit Work Completed 2.1 As previously reported to this committee in September 2023, there has been difficulty with recruiting to the Audit and Investigation officer posts. Contractors have been sourced to assist with delivering the remaining audits from the 2023/24 audit plan.

2.2Due to the difficulty with recruitment, Senior Management have agreed that the internal audit and investigations service for future years will be provided through a structured partnership with contractors with oversight by the Service Manager – Audit. This will ensure stability and resilience for the effective delivery of the internal audit plan.

2.3An external assessment on the internal audit service has been carried out by the Chief Audit Executive at Basingstoke BC. The assessment concluded,

‘I have completed an external review of your internal assessment against the Public Sector Internal Audit Standards (PSIAS) and based on the information provided, I can confirm that Rushmoor Borough Council conforms with the PSAIS requirements.’

A few minor improvement points have been recommended to further enhance the service.

Page 1 of 6 2.4 The table below provides an overview of the assurance opinion, given to the completed audit since the last update:

Audit Title Assurance Recommendations by Priority Opinion High Medium Low 2023/24 Internal Audit Plan Cyber Security in Limited 2 5 3 the Supply Chain Procurement Limited 4 5 0 Cards Insurance Follow Limited 3 6 0 up Purchase Ledger Reasonable 2 6 1 Estates Management Substantial 0 2 0 follow up

2.5Below is a summary of the key findings from the audits/ follow up’s.

Cyber Security in the supply chain The Council’s arrangements for procurement/contract management are transitional, with changes at a senior and operational level. The Council’s current focus is primarily on enhancing its ‘core’ procurement/contract management approach to better align with good practice. This process is supported by a Service Level Agreement (SLA) with Portsmouth City Council (PCC).

The current SLA with PCC does not include specific cyber risk in the supply chain support, although this could potentially be provided in future.

The Council does not currently have any defined arrangements to assess procurements for the risk they pose and put arrangements in place to manage the risk, appropriate to the scale of individual procurements, nor has any action been taken to review the existing contract portfolio for related risk and implement any enhancements necessary.

The IT Team has developed a set of questions (based on National Cyber Security (NCSC) guidance and supported by PCC), which are being used to ensure appropriate arrangements are in place for ‘new’ procurements. A ‘live’ procurement was reviewed by Internal Audit, confirming that this process is being followed appropriately.

The next and more substantial phase of work will be to review the existing portfolio of IT contracts and put any enhancements necessary in place. This phase has not yet started.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit: Audit UpdateReport 259 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 13 attended
PC
Councillor Peter CullumChairman, present
ST
Councillor Stuart TrusslerVice-Chair, present
CC
Councillor Craig CardCommittee Member, present
DC
Councillor David CliffordCommittee Member, apologies, sent representative
AG
Councillor Akmal GaniCommittee Member, present
CG
Councillor Christine GuinnessCommittee Member, present
NM
Councillor Nadia MartinCommittee Member, present
SS
Councillor Sarah SpallCommittee Member, present
NT
Councillor Nem ThapaCommittee Member, present
JV
Councillor Jacqui VosperCommittee Member, present
GW
Councillor Gareth WilliamsCommittee Member, present
TD
Mr. Tom DaviesNon-elected, non-voting, present

All 13 on the meeting page

On this subject at Rushmoor

Search all
  1. Internal Audit - Audit UpdateThis decision
  2. Internal Audit Progress ReportNoted
  3. Internal Audit - Audit Charter and Audit Plan 2026/27Approved
  4. Internal Audit - Progress ReportNoted
  5. Internal Audit - Audit Progress Report UpdateNoted
  6. Internal Audit - External Quality Assessment - Final ReportNoted

More from Rushmoor Audit and Governance Committee

All decisions
MeetingDecisionOutcome
29 Sep 2026 Reserve Risk Assessment Update ReportRESOLVED : That the Reserve Risk Assessment Update Report be noted. Noted Open
29 Sep 2026 Internal Audit Progress ReportRESOLVED : That SIAP’s Report No. SIAP26/05 be noted. Noted Open
29 Sep 2026 Corporate Policy and Guidance and the use of the Regulation of Investigatory Powers Act 2000RESOLVED : That the Surveillance and RIPA & IPA Policy and Guidance be approved and the contents of Report No. LEG260... Approved Open
29 Sep 2026 Annual Ombudsman Complaint Review LetterRESOLVED : That: ( i ) the Annual Review Letter be noted; and (ii) the Council commend officers on the positive outco... Noted Open
30 Jul 2026 Freedom of Information - Annual Update Report 2026RESOLVED : That officers: (i) continued the work on reducing the number of overdue FOIs within the system in 2026 and... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies