RESOLVED that (i) the position to date and the Medium Term Financial Strategy assumptions, as set out in Report No. FIN2416, be noted; and (ii) the acceptance of the Prospect Estate Big Local contribution of £55,000, to be spent on the Water Lane playground project, along with an equivalent uplift in the expenditure budget, be approved.
Word for word from the decision Rushmoor published for this meeting.Source: democracy.rushmoor.gov.uk
CABINET COUNCILLOR GARETH WILLIAMS FINANCE PORTFOLIO HOLDER 26 NOVEMBER 2024 REPORT NO. FIN2416
KEY DECISION? NO
BUDGET MANAGEMENT AND MTFS STRATEGIC REVIEW
SUMMARY AND RECOMMENDATIONS:
The Council’s Medium Term Financial Strategy (MTFS) approved on 22nd February 2024 presented a cumulative £16.651 million budget deficit over 4 years to 2027-28 before mitigation through a savings programme. The budget estimates included several significant assumptions and risks and a set of savings targets to mitigate the deficit to bring the council back to financially sustainability by 2027-28. Cabinet committed to update Council on these assumptions and progress against the savings targets. Unlike the July update, there is a significant variation on the potential outcomes on the matters brough to attention in this report and these need to be fully worked through and it is appropriate to bring a detailed numerical MTFS update forward for February Council.
Recommendation(s) requiring decision.
1. Cabinet notes the position to date and MTFS assumptions. 2. Approve the acceptance of the PEBL contribution of £55k to be spend on the water Lane playground project and an equivalent uplift in the expenditure budget.
1. INTRODUCTION
1.1The Budget is a major decision for the Council and setting and maintaining a balanced budget is a statutory requirement. This report provides a summary of the latest forecast performance against the 2024-25 approved revenue and capital budget and an update on the 2025-28 Medium Term Financial Strategy (MTFS) assumptions adopted by Full Council on 22nd February 2024.
2. BACKGROUND AND EXECUTIVE SUMMARY
2.1The Council has a statutory obligation to set and maintain a balanced budget. In February the Council identified a significant challenge to its future financial sustainability (as set out at the February 2024 Budget Council) and without mitigation the council would not be able to set a balanced budget in 2026-27.
2.2The forecast outturn is on track with the full £740k savings requirement achieved for 2024-25. The detail behind the headline shows a more challenging position for the MTFS. Key income streams are forecast below budget and will require adjustment in the MTFS, mitigated by several one off in year favourable variances.
2.3The level of external borrowing has reduced through careful cashflow management delaying the need to borrow externally. Whilst the council has utilised more of its cashflow to avoid external borrowing, the overall level of borrowing can only be reduced through the achievement of the capital receipts factored into the MTFS, this is proving difficult to achieve and is a concern due to interest rates increasing from October. There are several other significant budget implications identified that are currently being worked through to inform the MTFS revision.
3. CURRENT YEAR FINANCIAL PERFORMANCE
Revenue Account
3.1Full Council on 22nd February 2024 approved the 2024-25 revenue and capital budget and the 2025-28 Medium Term Financial Strategy (MTFS). The 2024- 25 revenue budget projected an unsustainable £5.379m drawdown on reserves before mitigation and a cumulative £16.651m deficit over 4 years. Full Council adopted a set of budget savings targets to bring the revenue account sustainably back into balance without the need to draw on reserves. The projected deficits and savings targets are shown in the table below.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.