Resolved
That: (i) the completed audit work be noted, and; (ii) the progress to date towards the 2024/25 Audit Plan be noted.
Audit and Governance Committee noted this item on Wednesday 29 January 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
That: (i) the completed audit work be noted, and; (ii) the progress to date towards the 2024/25 Audit Plan be noted.
CORPORATE GOVERNANCE AUDIT MANAGER AUDIT AND STANDARDS COMMITTEE REPORT NO. AUD 25/01
29th JANUARY 2025
INTERNAL AUDIT – AUDIT UPDATE
SUMMARY: This report describes: • An update on the audits finalised since the last update report to Committee in September 2024 and a summary of the progress towards the 2024/25 audit plan.
RECOMMENDATION: Members are requested to: i. Note the audit work completed. ii. Note the progress to date towards the 2024/25 audit plan.
1 Introduction 1.1 This report is to provide Members with: • An overview of the work finalised for the 2023/24 audit plan; • A progress update on the 2024/25 Audit Plan; and • A schedule of work to be delivered in Q4.
2 Audit Work Completed 2.1 The table below provides an overview of the assurance opinion, given to the completed audits since the last update in September 2024:
Audit Title Assurance Recommendations by Priority Opinion High Medium Low 2023/24 Internal Audit Plan Capital Programme Reasonable 1 0 0 – Meads 2024/25 Internal Audit Plan Building Control Reasonable 1 3 1 Princes Hall Reasonable 2 7 1 Procurement cards Substantial 0 1 0 follow up
2.2Below is a summary of the key findings from the audits.
Page 1 of 7 Capital Programme – Meads The Council undertook a purchase of the Meads and did substantial due diligence using external expert support and advice.
Rushmoor Borough Council (RBC) commissioned the services of Lambert Smith Hampton Investment Management (LSHIM) to provide professional advice and assurance. Part of the Asset Report published by the LSHIM set out options for the format of operational management, following which Eddison’s were engaged through a standard tendering process. A decision was approved by Cabinet to contract with the successful company in advance of the acquisition to facilitate mobilisation and provide further due diligence.
Town Centre strategy was published by David Lock Associates, to explore the sustainability of a regeneration project of the scale likely to result from a capital purchase such as the Meads & Kingsmead. The viability of future regeneration was also validated by the commitment of Sovereign Housing Association to its own plans to rejuvenate their recently purchased Princes Mead, all be it a predominantly housing led project.
In addition, to one high priority recommendation on retrospective reporting on the approach taken to financing, a number of best practice recommendations were identified which would strengthen any future approach including: • Improved modelling providing more extensive scenario testing which covers worse case and other options available. • Clear approval requests within reports so that it is clearly shown what is being requested for approval from Cabinet. • Exit strategy to demonstrate at what point the Council would no longer view the strategy viable and what action would be taken to exit.
Building Control Key Observations Areas assessed to be working well/controls are effective: • Risk Management processes to ensure that projects identified as non- standard and therefore subject to a bespoke inspection are in place and embedded into the IDOX system in order to meet the requirements of KPI 3. • One of the requirements within the legislation (KPI5), is to state whether there is a Quality Management System (QMS) in place, RBC have been awarded (British Standards Institution) BSI ISO:9001 in Quality Management. • A complaints process is in place with a procedure on how to handle the complaints to enable continual improvement in compliance with KPI6 of the OSR monitoring arrangements as well as full reportable data. • In order to meet the Code of Conduct for Registered Building Inspectors a Whistleblowing Policy needs to be in place and the council have this and is readily available via different methods.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Internal Audit: Audit UpdateReport | 275 KB | DownloadRead as text |
Follow Audit and Governance Committee at Rushmoor and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Sep 2026 | Reserve Risk Assessment Update ReportRESOLVED : That the Reserve Risk Assessment Update Report be noted. | Noted | Open |
| 29 Sep 2026 | Internal Audit Progress ReportRESOLVED : That SIAP’s Report No. SIAP26/05 be noted. | Noted | Open |
| 29 Sep 2026 | Corporate Policy and Guidance and the use of the Regulation of Investigatory Powers Act 2000RESOLVED : That the Surveillance and RIPA & IPA Policy and Guidance be approved and the contents of Report No. LEG260... | Approved | Open |
| 29 Sep 2026 | Annual Ombudsman Complaint Review LetterRESOLVED : That: ( i ) the Annual Review Letter be noted; and (ii) the Council commend officers on the positive outco... | Noted | Open |
| 30 Jul 2026 | Freedom of Information - Annual Update Report 2026RESOLVED : That officers: (i) continued the work on reducing the number of overdue FOIs within the system in 2026 and... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.