Cabinet, Tuesday 10 February 2026 at 7.00pm

LEISURE OPERATOR CONTRACT AWARD

Noted Executive 1 paper

AI summaryRushmoor Cabinet awards 15 year leisure operating contract to the highest scoring bidder, covering Aldershot facilities and a new Farnborough centre, with a £30,000 ski centre feasibility study also approved.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNoted15 year term plus 5 year extension option and interim phase
Money£30,000 feasibility study budgetFunded from 2025/26 ski centre revenue budget balance
What happens nextContract award on 24 February 2026After 8 working day standstill period
Who it affectsAldershot and Farnborough leisure usersExisting pools, lido, ski centre and new centre

What was decided

Cabinet noted the completed procurement process and awarded the leisure operating contract to the highest scoring bidder, on an agency agreement basis, for 15 years with an option to extend by five years, plus an interim phase. Report 2.3, 2.21

Cabinet approved a £30,000 feasibility study revenue budget for the Alpine Snowsports Centre, to be funded from the remaining balance of the 2025/26 ski centre revenue budget. Report 2.16, 3.6

Cabinet approved budget adjustments from 2026/27 to reflect the proposed contract requirements, and delegated authority to the Executive Head of Operations, in consultation with the Corporate Manager for Legal Services, to finalise and enter into the contract. Report 2.2, 3.7

Why

The Ministry of Housing, Communities and Local Government gave full approval in April 2025 for delivery of the revised Farnborough Leisure Centre scheme, using the remaining £18.5m Levelling Up grant.

Officers used the Competitive Flexible Procedure under the Procurement Act 2023, with a 60% quality and 40% price weighting, and an agency model was chosen for its more efficient VAT treatment. Report 2.1, 2.7, 2.8

An interim operator is needed to run Aldershot Pools and Lido from 1 April 2026, as the existing Places Leisure contract ends on 31 March 2027 and the temporary ski centre arrangement ends in May 2026. Report 2.3, 2.20, 2.22

What happens next

Notification of award and standstill summary issued on 11 February 2026, with a statutory 8 working day standstill period from 12 to 23 February 2026. Report 2.5

Contract award scheduled for 24 February 2026, with the interim phase of the contract commencing on 1 April 2026. Report 2.5, 2.20

The main phase of the contract is expected to begin when the new Farnborough Leisure Centre opens, currently targeted for late 2027 or early 2028, subject to approval. Report 2.5, 2.21

The money

  • £18.5m Remaining Levelling Up grant approved by MHCLG in April 2025 for the revised Farnborough Leisure Centre scheme
  • £30,000 Feasibility study revenue budget for the Alpine Snowsports Centre, funded from remaining 2025/26 ski centre revenue budget Report 2.16, 3.6
  • £288k pa Cap on maximum interim payment from the Council to the operator, covering Aldershot Pools and Lido, ski centre, and tennis courts Report 2.9, 3.9
  • £300k Maximum cap on year one fee payable by the Council to the operator in the main phase Report 3.9
  • £120k Minimum fee payable by the operator to the Council for years 2 to 5 of the main phase Report 3.9
  • £330,000 Base and approved budget for Aldershot Pools and Lido in 2025/26 Report 3.6
  • (51,070) Base budget figure for Alpine Ski Centre in 2025/26, as shown in the report Report 3.6
  • 48,930 Approved budget for Alpine Ski Centre in 2025/26 Report 3.6
  • 278,930 Total base leisure budget for 2025/26 Report 3.6
  • 378,930 Total approved leisure budget for 2025/26, including the £100,000 growth approved on 3 June 2025 Report 3.6

Options considered

  • Chosen: Award the leisure operating contract to the highest scoring bidder on an agency model. Provides a net beneficial financial position through more efficient VAT treatment, allows appointment now, and meets the need for clarity ahead of the 23 May 2026 lido season opening Report 2.8, 2.23
  • Rejected: Delay awarding a leisure operating contract until delivery of the new Farnborough Leisure Centre is confirmed. An operator is needed as soon as possible to prepare for the 23 May 2026 lido season opening, and operators expect an award this month after a lengthy process Report 2.23, 2.24

Implications

  • Financial: The agency model allows the Council to reclaim VAT under Section 33 of the VAT Act 1994, giving a net beneficial financial position compared with a principal model. Report 2.8
  • Financial: Following the first 12 months of operation, the Council may incur an additional financial obligation if utilities and facilities management costs rise beyond reasonable inflationary increases. Report 3.3
  • Legal: The procurement process has been confirmed as legally compliant and sound, and the contract will continue to be subject to internal and external scrutiny to finalisation. Report 3.5
  • Risk: The key risk is dependency on delivery of the wider build project, but the contract includes a clause requiring the operator to continue running Aldershot Pools and Lido until December 2029 if the new centre does not progress. Report 3.1
  • Risk: There is a risk that the agency model becomes unviable due to an HMRC decision or a defect in the agency position, though external advice considers the HMRC risk low and the preferred operator has a financial fallback position. Report 3.2
  • Equalities: An Equality Impact Assessment screening has been completed, and the appointment is expected to have a positive impact on groups with protected characteristics and disadvantaged groups. Report 3.16, 3.17
  • Staffing: Additional internal resource is anticipated to manage the new contract, to be set out in the Farnborough Leisure Centre build report, alongside a small finance team impact to be managed within current resources. Report 3.15

Who and where

  • Users of Aldershot Pools and Lido Report 1.3, 2.3, 2.20
  • Users of the Alpine Snowsports Centre during the interim phase Report 2.16, 2.20
  • Future users of the new Farnborough Leisure Centre Report 1.3, 1.4
  • Tennis court users at Manor Park, Rectory Road and Cove Green Report 2.16
  • Existing leisure staff and contractor Places Leisure, whose current contract ends on 31 March 2027 Report 2.22

Timeline

  • February 2025: Cabinet approved the revised approach for delivery of the new Farnborough Leisure Centre and the operator procurement approach Report 1.1
  • 11 February 2025: Cabinet agreed the overall operator procurement and appointment approach and commencement of the process Report 2.2
  • April 2025: Ministry of Housing, Communities and Local Government gave full approval for the revised scheme using the remaining £18.5m Levelling Up grant
  • 24 June 2025: Tender notice and key procurement documents issued via the Proactis portal Report 2.5, 2.6
  • 28 August 2025: First stage tender return deadline Report 2.5, 2.13
  • 19 December 2025, 12pm: Second stage best and final tender return deadline Report 2.5, 2.17
  • 10 February 2026: Cabinet meeting to approve the contract award Report 2.5
  • 11 February 2026: Notification of award decision and issue of assessment summaries; Contract Award Notice issued on FTS Report 2.5
  • 12 to 23 February 2026: Statutory 8 working day standstill period Report 2.5
  • 24 February 2026: Contract award Report 2.5
  • 1 April 2026: Commencement of the contract interim phase, with operator running Aldershot Pools and Lido and the ski centre Report 2.3, 2.5, 2.20
  • May 2026: Existing temporary arrangement for Places Leisure to operate the Aldershot Ski Centre ends Report 2.22
  • 23 May 2026: Lido season opening Report 2.23
  • 31 March 2027: Existing contract with Places Leisure for the operation of Aldershot Pools and Lido ends Report 2.22
  • Late 2027 or Early 2028: Target opening of the new Farnborough Leisure Centre and commencement of the contract main phase Report 2.5, 2.21

Plain English for the jargon

  • Agency model: A delivery arrangement where the leisure operator acts as an agent on behalf of the Council, which is the principal, allowing the Council to account for gross income and expenditure and reclaim VAT under Section 33 of the VAT Act 1994.
  • Competitive Flexible Procedure: A procurement process introduced by the Procurement Act 2023 that allows contracting authorities to design project specific processes aligned with project objectives and market norms.
  • Interim Phase: The first part of the operating contract, running from 1 April 2026 until the new Farnborough Leisure Centre opens, during which the operator runs the existing Aldershot facilities.
  • Main Phase: The 15 year part of the operating contract that begins when the new Farnborough Leisure Centre opens, with an option to extend by a further 5 years.
  • Levelling Up grant: Central government funding administered by the Ministry of Housing, Communities and Local Government, of which £18.5m remains for the revised Farnborough Leisure Centre scheme.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item67

Resolved

RESOLVED that (i) the successful completion of the procurement process to secure a leisure operator for the Council’s existing leisure facilities and the proposed new centre in Farnborough, be noted; (ii) the implications of the risks highlighted in sections 3.1 – 3.4 of the Report, be noted; (iii) the award of the leisure operating contract be made to the highest scoring bidder, as outlined in Exempt Appendix 1, subject to the completion of the standstill period. The contract was on the basis of an agency agreement and covered a 15 year term, (with an option to extend by five years), plus an additional interim phase whilst the new centre was under development, be agreed; (iv) the adjustment to budgets from 2026/27 to reflect the proposed contract requirements as detailed in Exempt Appendix 2, be approved; (v) a feasibility study revenue budget for the Alpine Snowsports Centre of £30,000 to be funded from the remaining balance of the 2025/26 ski centre revenue budget, as referenced in section 3.6, be approved, and; (vi) authority be delegated to the Executive Head of Operations, in consultation with the Corporate Manager – Legal Services, to finalise and enter into the leisure operating contract with the successful bidder, be approved.
Word for word from the decision Rushmoor published for this meeting. Source: democracy.rushmoor.gov.uk

Follow this further

Built from Rushmoor's papers

What the report saysPro

Report to Cabinet

Background

1.1In February 2025, Cabinet approved a revised approach for the delivery of a Leisure Centre in Farnborough town centre along with the procurement approach to appoint an operator to run the existing Aldershot Pools & Lido facilities within the borough and the proposed new centre (Report REG2501). 1.2. The Ministry of Housing, Communities & Local Government (MHCLG) gave full approval in April 2025 for the Council to deliver the revised scheme utilising the remaining £18.5m Levelling Up grant. At that time the Cabinet noted that the scheme would also require some borrowing that would be funded by operator income payments.

1.3The proposed facility includes two swimming pools, (a 25m 6-lane main pool and a 10m x 8m learner pool), 100+ station fitness suite including provision of specialist equipment for people who are less mobile or active, studio space including a dedicated spin studio, a café and active play for children. A new surface car park and play park will also be delivered as part of the scheme.

1.4The new Farnborough Leisure Centre will play a significant role in reducing health inequalities - both physical and mental - and increasing levels of physical activity. These are key priorities identified in the Council Delivery Plan 2026-27. The Council is therefore keen to appoint an operating partner who shares this vision and is committed to operating the facility to optimise participative opportunities and benefits for the local community.

2. OPERATOR PROCUREMENT PROCESS

2.1The Procurement Act 2023 commenced on 24 February 2025 and had significant implications for public sector procurement. This revised public procurement system introduced the new 'Competitive Flexible Procedure' which enables contracting authorities to design project specific procurement processes to align with project objectives and market norms. The Council’s leisure operator procurement process made use of this competitive flexible procedure.

2.2On 11 February 2025, Cabinet agreed the overall operator procurement and appointment approach, and commencement of the process. Decisions to amend the procurement documentation as required throughout the process was delegated to the Executive Head of Operations in consultation with the Portfolio Holder for Healthy Communities & Active Lives, and financial implications in consultation with the Executive Head of Finance (S151).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LEISURE OPERATOR CONTRACT AWARDReport 336 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 6 attended
GA
Councillor Gaynor AustinCommittee Member, present
KD
Councillor Keith DibbleCommittee Member, present
CG
Councillor Christine GuinnessCommittee Member, present
JH
Councillor Julie HallCommittee Member, present
SP
Councillor Sophie PorterVice-Chair, present
GW
Councillor Gareth WilliamsChair, present

On this subject at Rushmoor

Search all
  1. LEISURE OPERATOR CONTRACT AWARDThis decision
  2. Additional item - leisure operators' requests for financial assistanceAgreed

More from Rushmoor Cabinet

All decisions
MeetingDecisionOutcome
20 Oct 2026 Budget management - month 4RESOLVED that (i) the revenue budget forecast, as set out in Section 3 of Report No. FIN2617, be noted; (ii) the writ... Noted Open
20 Oct 2026 Temporary accommodation placement policyRESOLVED that (i) the Temporary Accommodation Placement Policy, as set out in Appendix 1 of Report No. PG2617, be app... Approved Open
20 Oct 2026 Farnborough civic quarter regeneration - strategic delivery reviewRESOLVED that (i) the outcome of the Strategic Delivery Review exercise, as set out in Report No. REG2604, be noted ;... Noted Open
15 Sep 2026 Crisis and resilience fundRESOLVED that the information within Report No. ED2615, including work underway to support residents’ financial resil... Noted Open