The Highway Drainage Investment Programme (DIP) 2022/23 and the Culvert Investment Programme (CIP) 2022/23.
ApprovedPlanning1 paper
Planning, Transport and Sustainable Development and Regeneration approved this item on Friday 18 March 2022. Below is the council's own wording, with the papers it was decided on.
Salford City Council - Record of Decision I, Councillor Mike McCusker, Lead Member for Planning & Sustainable Development , in exercise of the powers contained within the Council Constitution , do hereby: Approve the proposed programme of work for the Highway Drainage Investment Programme (DIP) 2022/23 and the Culvert Investment Programme (CIP) for 2022/23, as outlined in the report. The Reasons are: To facilitate continuous improvement of the highway drainage infrastructure as part of the defined Network Recovery Plan as part of the ongoing rolling programme of drainage repair works. Options considered and rejected were: No other options were considered for this report. Assessment of Risk: Medium – It is important that the existing highway drainage and culvert infrastructure improvements continue in order to ensure that surface flooding is minimised and that the capacity of existing systems is maximised, especially in view of the recent weather conditions that have been experienced within the City. The source of funding is: Prudential Code funding (Capital) Legal Advice obtained: Tony Hemingway Principal Solicitor & Azra Furheen - Solicitor-0161 219 6323 Financial Advice obtained: Alison Woods, Senior Accountant, Tel. 925 1135 Procurement Advice obtained: Heather Stanton, Category Manager 686 6296 Contact Officer: Steve Mangan Tel No 0161 603 4034 This matter is not subject to consideration by another Lead Member. The appropriate scrutiny panel to call-in the decision is the Growth & Prosperity Scrutiny Panel. Signed: Councillor McCusker Dated: 18 th March 2022 Lead Member for Planning & Sustainable Development FOR DEMOCRATIC SERVICES USE ONLY This decision was published on 22 nd March 2022. This decision will come in force at 4.00 p.m. on 29 th March 2022, unless it is called-in, in accordance with the decision-making process rules.
Word for word from the decision Salford published for this meeting.Source: sccdemocracy.salford.gov.uk
Report to Planning, Transport and Sustainable Development and Regeneration
Part 1: Open to the Public
REPORT OF STRATEGIC DIRECTOR PLACE
TO LEAD MEMBER FOR PLANNING AND SUSTAINABLE DEVELOPMENT
ON 18 TH MARCH 2022
TITLE: THE HIGHWAY DRAINAGE INVESTMENT PROGRAMME (DIP) 2022/23 AND THE CULVERT INVESTMENT PROGRAMME (CIP) 2022/23
RECOMMENDATIONS: That the Lead Member for Planning and Sustainable Development approves the proposed programme of work for the Highway Drainage Investment Programme (DIP) 2022/23 and the Culvert Investment Programme (CIP) for 2022/23 as outlined in the report.
EXECUTIVE SUMMARY: The financial provision for the Highway Drainage Investment Programme for 2022/23 and the Culvert Investment Programme for 2022/23 has been confirmed as £250,000 (£200,000 and £50,000 respectively). The budget apportionments given in the report and detailed within the background document outline the 2022/23 scheme proposals as part of the ongoing rolling programme of drainage repair works. The works identified for inclusion within the Culvert Investment Programme are also outlined in the report.
BACKGROUND DOCUMENTS:
KEY DECISION: No
1 DETAILS: 1. The Highway Drainage Investment Programme
1.1Initial surveys and investigations into the condition of the highway drainage infrastructure identified many defective gullies and connections. The cause of many of these defects is attributed to damaged pipe work, which over time has allowed water to erode the carriageway foundation and cause failures. The repairs required usually consist of a small excavation to expose and repair the damaged sections of pipe work followed by backfill and reinstatement. 1.2 To date 5,997 of these defects have been addressed as summarised below in Table 1
Blocked Number of gullies covers lifted cleared with and greased New New concentrated following Gully Gully Gully General jetting & concentrated Connection Pots Covers Drainage Neighbourhood cleansing effort. Repairs installed installed Repairs Totals
East Salford 143 128 57 188 159 28* 703 Little Hulton, Walkden North 112 & Walkden South 295 126 85 268 54 940 Worsley & Westwood Park, 61 Boothstown & Ellenbrook 228 91 48 270 45 743 Eccles, Barton & Winton 205 122 30 66 83 54 560 Unscheduled (all Neighbourhoods) 62 62 Total **5997
2 Table 1 – Summary of highway drainage repairs completed (and scheduled to be completed to March 2022) * figure does not include the additional Broughton Flood Zone- 44 90 litre pots installed at Broughton Lane in 2018/19 ** Due to the new contractual arrangements- works will carry over to 2022/23 from 2021/22
1.3The capital funding allocation for highway drainage structural maintenance during 2022/23 has been confirmed as £200,000.
Work Element (£) Total (£) Drainage Investment Programme General Drainage Repairs: Direct Works Cost £167,700 Depot Overheads (19.26%)* £32,300 £32,300
Total Construction Costs £200,000.00
Total Budget for programme £200,000.00 Table 2 – proposed apportionment of DIP allocation for 2021/22. *Depot overhead for 2022/23 to be confirmed.
1.4The rolling programme of repairs will continue during 2022/23 to reduce the identified backlog of repairs. Details are as shown in Table 3 below. The programme has been prioritised using a risk-based approach to ensure that the worst areas of flooding and structural defects are addressed first. The programme has been identified in response to the following criteria:
where flooding affects or is likely to affect property.
locations adjacent to well used footways.
where standing water is at critical turning or braking points; and
where flooding is frequent and has been persistent for some years.
3 1.5 The proposed programme of work is highlighted in Table 3 below:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning, Transport and Sustainable Development and Regeneration at Salford and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.