Property / Regeneration Briefing, Monday 8 April 2024 at 3.00pm

Highway Drainage (DIP) and Culvert (CIP) Investment Programmes 2024/25

Approved Committee 1 paper

Property / Regeneration Briefing approved this item on Monday 8 April 2024. Below is the council's own wording, with the papers it was decided on.

Item3a

Resolved

Salford City Council - Record of Decision Title: The Highway Drainage Investment Programme 2024/25 and the Culvert Investment Programme 2024/25 I, Councillor Tracy Kelly, Deputy City Mayor, in exercise of the powers contained within the City Council’s constitution do hereby approve the proposed programmes of work for the continuation of the Highway Drainage Investment Programme (DIP) 2024/25 and the Culvert Investment Programme (CIP) for 2024/25. The Reasons: The financial provision for the Highway Drainage Investment Programme for 2024/25 and the Culvert Investment Programme for 2024/25 has been confirmed as £450,000 (£400,000 and £50,000 respectively).The budget apportionments given in the report and detailed within the background document outline the 2024/25 scheme proposals as part of the ongoing rolling programme of drainage repair works. The works identified for inclusion within the Culvert Investment Programme are also outlined in the report. Assessment of Risk : Medium - It is important that the existing highway drainage and culvert infrastructure improvements continue in order to ensure that surface flooding is minimised and that the capacity of existing systems is maximised, especially in view of the climate emergency. The source of funding: Capital Programme 2024/25 Legal Advice s upplied by Helen Chapman Principal Solicitor, Legal Services Financial advice s upplied By Adam Flaherty, Senior Accountant Procurement advice supplied by Adam Flaherty, Senior Accountant HR advice: N/A Climate Change advice/implications supplied by Matthew Ryan Flood Risk and Drainage Manager. The following documents have been used to assist the decision process: Report submitted to Property/Regen Briefing on 8 April 2024 Contact Officer: Steve Mangan, Group Engineer Highway Asset Management * This decision is not subject to consideration by another Lead Member/Director * The appropriate scrutiny panel to call-in the decision is the Growth and Prosperity Scrutiny Panel. Signed : Councillor Tracy Kelly Deputy City Mayor Date: 8 th April 2024 * This decision was published on Monday 8 th April 2024 . * This decision will come in force at 4.00 pm on Monday 15 th April 2024 unless it is called-in in accordance with the Decision Making Process Rules.
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Property / Regeneration Briefing

Recommendations

That the City Mayor notes the proposed programmes of work for the continuation of the Highway Drainage Investment Programme (DIP) 2024/25 and the Culvert Investment Programme (CIP) for 2024/25 and subject to any matters arising the report is further submitted for approval on 25th March 2024

EXECUTIVE SUMMARY: The financial provision for the Highway Drainage Investment Programme for 2024/25 and the Culvert Investment Programme for 2024/25 has been confirmed as £450,000 (£400,000 and £50,000 respectively).The budget apportionments given in the report and detailed within the background document outline the 2024/25 scheme proposals as part of the ongoing rolling programme of drainage repair works. The works identified for inclusion within the Culvert Investment Programme are also outlined in the report.

BACKGROUND DOCUMENTS:

KEY DECISION: Yes: All wards are affected.

1 DETAILS:

1. The Highway Drainage Investment Programme

1.1Initial surveys and investigations into the condition of the highway drainage infrastructure identified many defective gullies and connections. The cause of many of these defects is attributed to damaged pipe work, which over time has allowed water to erode the carriageway foundation and cause failures. The repairs required usually consist of a small excavation to expose and repair the damaged sections of pipe work followed by backfill and reinstatement. 1.2 To date 6,093 of these defects have been addressed as summarised below in Table 1

Blocked Number of gullies covers lifted cleared with and greased New New concentrated following Gully Gully Gully General jetting & concentrated Connection Pots Covers Drainage Neighbourhood cleansing effort. Repairs installed installed Repairs Totals

Cadishead & Lower Irlam, Higher Irlam & Peel Green 377 75 70 25 60 67 674 Claremont, Weaste & Seedley 190 165 30 87 135 43 650 Swinton & Pendlebury 226 179 60 375 57 92 989 The Quays,Ordsall, Pendleton & Charlestown 281 100 41 152 75 56 705

East Salford 143 128 57 188 159 50* 725 Little Hulton, Walkden North & Walkden South 295 126 85 268 54 135 963 Worsley & Westwood Park, Boothstown & Ellenbrook 228 91 48 270 45 80 762 Eccles, Barton & Winton 205 122 30 66 83 57 563 Unscheduled (all Neighbourhoods) 62 62 Total **6093

2 Table 1 – Summary of highway drainage repairs completed (and scheduled to be completed to March 2024) * figure does not include the additional Broughton Flood Zone- 44 90 litre pots installed at Broughton Lane in 2018/19

1.3The capital funding allocation for highway drainage structural maintenance during 2024/25 has been confirmed as £400,000.

Work Element (£) Total (£) Drainage Investment Programme General Drainage Repairs: Direct Works Cost £173,145 Depot Overheads (15.51%)* £26,855 £26,855

Total Construction Costs £200,000.00

Excavations to repair unforeseen highway drainage issues

Direct Works Cost £173,145 Depot Overheads (15.51%)* £26,855 £26,855

Total Construction Costs £200,000.00

Table 2 – proposed apportionment of DIP allocation for 2024/25. *Depot overhead for 2024/25 to be confirmed. 1.4 The rolling programme of repairs will continue during 2024/25 to reduce the identified backlog of repairs. Details are as shown in Table 3 below. The programme has been prioritised using a risk-based approach to ensure that the worst areas of flooding and structural defects are addressed first. The programme has been identified in response to the following criteria:

• where flooding affects or is likely to affect property.

• locations adjacent to well used footways.

• where standing water is at critical turning or braking points; and

• where flooding is frequent and has been persistent for some years.

3 1.5 The proposed programme of work is highlighted in Table 3 below:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highway Drainage (DIP) and Culvert (CIP) Investment Programmes 2024/25Report 155 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 13 attended
SA
Sharmina AugustCommittee Member, apologies
BB
Barbara BenthamCommittee Member, present
JC
Jim CammellCommittee Member, apologies
PC
Philip CusackGuest, present
PD
Paul DennettCommittee Member, apologies
BH
Bill HindsCommittee Member, present
TK
Tracy KellyCommittee Member, present
MM
Mike McCuskerCommittee Member, present
JM
John Merry CBECommittee Member, present
WN
Wilson NkurunzizaGuest, present
TP
Teresa PepperGuest, present
MR
Mike RelphSecretary, expected

All 13 on the meeting page

On this subject at Salford

Search all
  1. Highway Drainage (DIP) and Culvert (CIP) Investment Programmes 2024/25This decision
  2. Technical and Highways Minor Civils Framework Lot 3 – Drainage Investigation and Repair 2024/25 (Stuart Culshaw)Approved
  3. Highway Drainage Investment Programme and Culvert Investment Programme 2023-24.Approved
  4. Approval to Award the Contract for Highways Drainage Maintenance ProgrammeAgreed
  5. The Highway Drainage Investment Programme (DIP) 2022/23 and the Culvert Investment Programme (CIP) 2022/23.Approved
  6. Highway Drainage Investment Programme (DIP) 2021/22 and Culvert Investment Programme (CIP) 2021/22.Approved

More from Salford Property / Regeneration Briefing

All decisions
MeetingDecisionOutcome
14 Sep 2026 Retail Unit1 1 New BaileySalford City Council - Record of Decision I, Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning... Approved Open
14 Sep 2026 Housing Development at Robert Hall Street, Ordsall - Appointment of ContractorsSalford City Council - Record of Decision Affordable Housing Development - A2 Robert Hall Street, Ordsall I Councillo... Approved Open
24 Aug 2026 One New Bailey, ProposalSalford City Council - Record of Decision I Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning,... Approved Open
24 Aug 2026 One New Bailey, 2023 Rent ReviewSalford City Council - Record of Decision I Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning,... Agreed Open
24 Aug 2026 Two New BaileySalford City Council - Record of Decision I Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning,... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies