Procurement Board, Monday 19 May 2025 at 2.00pm

Approval to Award the Contract for Key Route Network (KRN) Maintenance Scheme, A580 East Lancashire Road/ Broad Street (Nathan Williams)

Approved Committee 2 papers

Procurement Board approved this item on Monday 19 May 2025. Below is the council's own wording, with the papers it was decided on.

Item5e

Resolved

Salford City Council – Record of Decision I Paul Dennett, City Mayor, in exercise of the powers contained within the Council Constitution do hereby: 1. approve the appointment of J Hopkins Ltd, at a cost of £766,949.90, to undertake the main works on A580 East Lancashire Road/Broad Street. 2. approve the creation of a purchase order to J Hopkins Ltd, to the value of £766,949.90, to enable payments to be made to the contractor. 3. approve a risk allocation totalling £154,425.97, and the approval to create any required Purchase Orders that may call on the risk allocation. 4. approve the ‘Supervision and Management Fees’ totalling £119,757.33. 5. approve the ‘Other Costs’ associated with the project delivery totalling £5,179.95 and approve the creation of any required Purchase Orders. , as detailed in the table below: Detail required Answers Title/Description of Contracted Service/Supply/Project KRN Maintenance Scheme - A580 East Lancashire Road/Broad Street Name of Successful Contractor J Hopkins (Contractors) Ltd Supplier Registration Number (to be supplied by Corporate Procurement) 1112562 Type of organisation (to be supplied by Corporate Procurement) Private Limited Company Status of Organisation (to be supplied by Corporate Procurement) SME Contract Value (£) £766,949.90 Full Project Risk Allowance £154,425.97 Supervision and Management Fees £119,757.33 Other Costs £5,179.95 Contract Duration 4 Weeks Contract Start Date 30/06/2025 Contract End Date 25/07/2025 Optional Extension Period 1 Not applicable Optional Extension Period 2 Not applicable Who will approve each Extension Period? Procurement Board (extension > £150k) Contact Officer (Name & number) Nathan RL Williams 0161 779 4916 Lead Service Group Place How the contract was procured? (to be supplied by procurement) Further Competition Framework Details (where applicable) (procurement body, framework reference & title, start/ end date Rochdale Borough Council Framework Agreement for Highways Related Services - Lot 2. Funding Source External Funding Source (please identify below) Ethical Contractor (EC): Mayor’s Employment Charter EC: Committed to sign Charter EC: Accredited Living Wage Employer The Reasons are : - A580 East Lancashire Road/Broad Street scheme forms part of the part of Key Route Network (KRN) DfT Highways grant. The grant is to only be used for selected carriageway schemes. The total settlement Salford received for KRN is £4.5m over five years (starting 2023). - The proposed works on A580 East Lancashire Road/Broad Street is a carriageway resurfacing scheme and will improve the current condition of the existing carriageway. - Invitations to tender under the Lot 3 Rochdale Borough Council Framework Agreement were conducted by issuing a further competition to the three contractors. All three submitted a tender and based on the scoring criteria Tarmac Trading limited received the highest score and was the most economically advantageous tender based on the quality and pricing assessment. - If approved, the scheme is proposed to commence Monday 30 th June 2025. Options considered and rejected were: Not to award the contract. Assessment of Risk : Low. The source of funding is : City Region Sustainable Transport Settlement (CRSTS) Core Maintenance. Legal Advice obtained : Tony Hatton, ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

Salford City Council Constitution.

Published in Accordance with The Local Authorities (Executive Arrangements) (Meetings and Access to Information) (England) Regulations 2012 (“the Regulations”)

Part 4 Section B Access to Information Procedure Rules

General Exception

Notice is given to the public the reasons why compliance with the requirements for publicity in connection with key decisions are impracticable.

In relation to the making of decision under General Exception; Salford City Council’s Constitution states:-

17.1Subject to Rule 18 (special urgency), where the publication of the intention to make a key decision under Rule 16 is impracticable, the decision may still be made, but only if:

a) the Monitoring Officer has informed each Member of the Overview and Scrutiny Board (if the decision is one within the remit of the Overview and Scrutiny Board) or otherwise each member of the relevant Scrutiny Panel, , by notice in writing of the matter about which the decision is to be made;

b) the Monitoring Officer has made a copy of that notice available to the public at the offices of the Council at Salford Civic Centre, Chorley Road, Swinton, Salford, M27 5DA and published it on the council’s website; and

c) at least 5 clear days have elapsed since the Monitoring Officer complied with (a) and (b).

17.2As soon as reasonably practicable after the Monitoring Officer has complied with Rule 17.1(a) and (b), they must make available at the Council’s offices at Salford Civic Centre, Chorley Road, Swinton, Salford, M27 5DA a notice setting out the reasons why compliance with Rule 16 is impracticable and publish that notice on the Council’s website.

Title: Approval to Award the Contract for Key Route Network (KRN) Maintenance Scheme, A580 East Lancashire Road/ Broad Street.

Purpose: The scheme proposal is to remove/re-surface the existing carriageway along with associated drainage works. The proposed work will improve the overall condition of the carriageway and provide a safer road surface for users

1 Decision-Maker: City Mayor / Lead Member for Finance, Support Services & Regeneration (Procurement Board)

Contact: Nathan Williams, Engineer [email protected]

Notice 9 May 2025 Published: Decision Date: 19 May 2025

Reasons why As part of the tender process, the start date for the scheme impracticable to has been brought forwards by five weeks, with works now give 28 days’ scheduled to commence on Monday 30th June 2025, instead clear public of the originally planned date of Monday 4th August 2025. notice: The next available Procurement Board meeting following Monday 19th May 2025 is Monday 9th June 2025.

With that being said, the reason why we are unable to give 28 days clear public notice is that, if required this timeline significantly shortens the mobilisation period for the appointed contractor, raising concerns about their ability to adequately prepare for the earlier start. This may have implications for both the quality and efficiency of early-stage delivery, and we are currently reviewing options to mitigate this risk.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approval to Award the Contract for Key Route Network (KRN) Maintenance Scheme, A580 East Lancashire Road/ Broad Street (Nathan Williams)Report 76 KB DownloadRead as text
PDF
Procurement Board: KRN: Contract Award: A580 East Lancashire Road_Broad Street: V2Report 171 KB Download

At this meeting

Whole meeting

Who was there

4 of 7 attended
BB
Barbara BenthamInvitee, in attendance
PD
Paul DennettCommittee Member, apologies due to council business
CH
Chris HowlClerk, present
TK
Tracy KellyCommittee Member, apologies due to council business
JM
John Merry CBECommittee Member, present
TP
Teresa PepperCommittee Member, present
JY
Jack YoudChair, present

On this subject at Salford

Search all
  1. Approval to Award the Contract for Key Route Network (KRN) Maintenance Scheme, A580 East Lancashire Road/ Broad Street (Nathan Williams)This decision
  2. Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Approved
  3. Approval to Award the Contract for the continued use of the Line of Business System for Planning, Building Control and Local Land and Property Gazetteer (Anthony Stephenson)Approved
  4. Approval to Award the Contract for Statutory Homeless Supported Temporary Accommodation (Jane Barlow)Approved
  5. Approval to Award the Contract for the construction of affordable homes at Robert Hall St Ordsall (A2) Dylan VinceApproved
  6. Approval to Award the Contract for Better Bus Routes/ Improving Journeys - Salford Crescent to MediaCityUK - Site Investigation (Matthew Mollart)Approved

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies