Salford City Council
Property / Regeneration Briefing, Monday 12 January 2026 at 3.00pm

Better Bus Routes - Wave 2 Engagement

Approved Committee 3 papers

AI summarySalford City Council approves Wave 2 public engagement for the Better Bus Routes project between Salford Crescent and Media City UK, with delegated powers for the next business case.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedWave 2 engagement plus delegations for OBC and FBC stages
MoneyCRSTS development funding£803,435 original grant and £1,000,008 additional grant
What happens nextJanuary 2026Wave 2 engagement runs to end February 2026
Who it affectsFour Salford wardsOrdsall, Pendleton and Charlestown, Weaste and Seedley and Quays

What was decided

The council approved Wave 2 public engagement for the Better Bus Routes Salford Crescent to Media City UK project, so feedback can be considered and incorporated into the final scheme and Outline Business Case. Report P2

Authority was delegated to the Strategic Director for Place, in consultation with the S151 officer and Lead Member for Planning and Sustainable Development, to support Transport for Greater Manchester in submitting the Outline Business Case.

Further delegated authority was granted to negotiate, agree and finalise a Grant Funding Agreement in the form of a Development Agreement for the Full Business Case stage between Salford City Council, Transport for Greater Manchester and the Greater Manchester Combined Authority, subject to the outcome of the OBC. Report P40

Why

The project and its funding require public and stakeholder engagement at various stages and ahead of business case submissions, to gather feedback on the proposals and any impacts they may have. Report P28

The scheme aims to improve bus punctuality, reliability, waiting environment and journey times between Salford Crescent and Media City, and to upgrade walking and cycling links along the corridor. Report P22, P9, P10

The work supports the wider Greater Manchester Bee Network and the aim for 50 per cent of all journeys to be made by walking, cycling or public transport by 2040. Report P7

What happens next

Wave 2 public engagement is programmed to start in January 2026, with an expected end date of end February 2026. Report P2, P28

After engagement closes, feedback will be analysed and used to finalise the Outline Business Case before Transport for Greater Manchester submits it for approval. Report P3, P28

The Shared Legal Service is authorised to prepare all necessary documentation and to advise on the drafting and completion of the Grant Funding Agreement. Report P41

The money

  • £803,435 Original DfT CRSTS development grant made to Salford City Council under the Development Costs Letter dated 19 September 2023 Report P38
  • £1,000,008 Additional DfT CRSTS funding agreed by the GM Bee Network Committee on 27 February 2025 for additional project management and site investigation costs Report P39

Options considered

  • Rejected: None. The decision record states that no options were considered and rejected

Implications

  • Financial: The original CRSTS budget may no longer be sufficient to deliver all planned interventions because construction sector inflation has risen substantially, and the scheme may need to be split into phases with some work kept in reserve. Report P33, P36, P37, P44
  • Risk: Risk is rated Medium. The government funding letter confirms any cost overruns must be met locally and no additional HMG funding will be provided, so the scope of work may be reduced and claw back risk must be managed. Report P35, P37
  • Equalities: The transport network can be a barrier to equal access, and the improvements are intended to deliver a better network for a wide range of users. Report P32
  • Legal: Legal advice has been obtained. The Shared Legal Service will prepare documentation and advise on drafting and completion of the Grant Funding Agreement. Report P38, P41
  • Climate: Active travel measures and public transport prioritisation are described as a critical and highly effective strategy for reducing greenhouse gas emissions and air pollution, while supporting public health and the economy. Report P47, P48
  • Staffing: HR implications are stated as not applicable. Report P46
  • Other: Consultation materials and engagement details must be agreed with Ward Councillors and the Lead Member for Planning and Sustainable Development before any materials are published. Report P28

Who and where

  • Residents and users in the wards of Ordsall, Pendleton and Charlestown, Weaste and Seedley, and Quays Report P51
  • Bus passengers using the route 50 service between Salford Crescent and Media City UK Report P8, P22
  • Metrolink passengers on the Eccles Line, who may also benefit from faster journeys Report P22
  • Commuters, students, and vulnerable or mobility restricted passengers who rely on public transport Report P22
  • Private vehicle drivers, who may face minor localised detours because of the proposed bus gate on South Langworthy Road Report P22
  • Pedestrians and cyclists using new and upgraded facilities along the corridor Report P22

Timeline

  • 2021: Transport for Greater Manchester bus user satisfaction survey identified reasons for poor bus customer satisfaction Report P8
  • 25th November 2022: GMCA Combined Authority report on the project Report P5
  • 19 September 2023: Original CRSTS Development Costs Letter providing £803,435 of DfT CRSTS funds to Salford City Council Report P38
  • December 2023: Wave 1 engagement concluded Report P1
  • 27 February 2025: GM Bee Network Committee agreed additional grant of £1,000,008 for the project Report P39
  • January 2026: Wave 2 public engagement programmed to commence Report P2, P28
  • end February 2026: Expected end of Wave 2 public engagement Report P28

Plain English for the jargon

  • Bee Network: Greater Manchester's planned integrated transport network bringing together bus, tram, active travel and rail with integrated ticketing
  • CRSTS: City Region Sustainable Transport Settlement, the government funding stream supporting the scheme
  • OBC: Outline Business Case, the next submission required for the project before it can proceed
  • FBC: Full Business Case, the subsequent stage of project development
  • GFA: Grant Funding Agreement, to be agreed for the Full Business Case stage between the council, TfGM and GMCA
  • CYCLOPS: A type of junction upgrade providing improved pedestrian and cycling facilities
  • Bus gate: A traffic restriction limiting general traffic on a road to prioritise buses and other permitted vehicles
  • S151 officer: The council's statutory chief finance officer, responsible for the proper administration of financial affairs
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item4b

Resolved

Salford City Council - Record of Decision I Councillor Jack Youd, Deputy City Mayor and Lead Member for Finance, Corporate Services and Regeneration in exercise of the powers contained within the City Council Constitution do hereby: Give approval to proceed with the next phase (Wave 2) of public engagement for the Better Bus Routes (Improving Journeys) – Salford Crescent to Media City UK project, to allow feedback from this process to be considered and incorporated into the finalisation of the scheme proposals and project Outline Business Case (OBC). Grant delegated authority to the Strategic Director for Place, in consultation and agreement with the S151 officer and Lead Member for Planning and Sustainable Development, for SCC and its officers to; provide its support, to TfGM in their submission of the required OBC for approval. Grant delegated authority to the Strategic Director for Place, in consultation and agreement with the S151 officer and Lead Member for Planning and Sustainable Development, to; negotiate, agree, and finalise the detailed terms of a Grant Funding Agreement (GFA) in the form of a Development Agreement/s for the Full Business Case (FBC) work stage/s of the project, between SCC, TfGM and the Greater Manchester Combined Authority (GMCA) subject to the outcome of the OBC submission. Authorise the Shared Legal Service to prepare all necessary documentation and to take all steps which are required to give effect to the above recommendations. The Reasons are : The project and its funding require the public and stakeholders to be engaged with, at various stages in the project’s life cycle and in advance of business case submissions. With this engagement to gain feedback on the proposals being put forward, to understand the impact the proposals might have etc, with the feedback then used to refine the business case prior to finalisation and before its submission for approval. The feedback will also help shape future project development phases. Options considered and rejected were: None Assessment of Risk : Medium: The process of setting budgets for the CRSTS funding settlement which took place over a number of years means that inflationary pressures in the construction sector have increased substantially since the funding allocations were bid for and agreed. The government funding letter to Greater Manchester confirms ‘Any cost overruns must be met locally and no additional HMG (Government) funding from this settlement will be provided to support your CRSTS programmes’. This means that the work funded by the programme may have to be reduced in scope as inflation pressures continue to erode what can be delivered with the funding allocated. It will be important to develop the interventions working in close collaboration with the Greater Manchester and Active Travel England governance and approval gateway processes, to ensure the risk of funding claw back is minimised as projects progress beyond development to the delivery phase of the project. The source of funding is : Grant funding from the City Region Sustainable Transport Settlement (CRSTS). Legal Advice obtained : Yes – see report presented at ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Property / Regeneration Briefing

Executive summary

This report provides an update on the progress that has been made in developing the Improving Journeys - Salford Crescent to Media City UK (SCMC) project since the Wave 1 Engagement concluded in December 2023.

The report also seeks approval to progress the project and the proposed improvements to the next round of public engagement (Wave 2), which is programmed to go live in January 2026, whereby the proposals in their current form will be shared with the public and stakeholders in a format which is suitable for the work stage and feedback sought.

Once Wave 2 engagement has been completed and the feedback analysed, this will then act as a gateway, to enable TfGM (as scheme promoter), to formally submit an Outline Business Case (OBC) for SCMC for approval.

In addition, the report also seeks approval for a series of Delegation of Authorities to support the submission of the OBC and secure funding for the following phase of scheme development.

BACKGROUND DOCUMENTS: GMCA Combined Authority Report – 25th November 2022 Property and Regeneration – Decision – 28th August 2023 Property and Regeneration – Decision – 12th May 2025

KEY DECISION: Yes

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
04bii Better Bus Route Engagement: Nov and Dec 2025: Appendix AAppendix 399 KB Download
PDF
04biii SCMC P&R Report Appendix BAppendix 254 KB Download
PDF
Better Bus Routes: Wave 2 EngagementReport 157 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 13 attended
BB
Barbara BenthamCommittee Member, present
JC
Jim CammellCommittee Member, present
PC
Philip CusackInvitee, in attendance
PD
Paul DennettCommittee Member, apologies
TK
Tracy KellyCommittee Member, present
MM
Mike McCuskerCommittee Member, present
JM
John Merry CBECommittee Member, present
WN
Wilson NkurunzizaInvitee, in attendance
TP
Teresa PepperCommittee Member, present
MR
Mike RelphSecretary, expected
GR
Gina ReynoldsInvitee, in attendance
HR
Hannah Robinson-SmithCommittee Member, apologies

All 13 on the meeting page

On this subject at Salford

Search all
  1. Better Bus Routes - Wave 2 EngagementThis decision
  2. Approval to Award the Contract for Better Bus Routes/ Improving Journeys - Salford Crescent to MediaCityUK - Site Investigation (Matthew Mollart)Approved
  3. Better Bus Routes - Salford Crescent to MediaCityUK - Bus Stop Upgrades going out to tender/ competition (Matthew Mollart)Approved
  4. Better Bus Routes - Salford Crescent to MediaCityUK - the Bund going out to tender/ competition (Matthew Mollart)Approved
  5. Better Bus Routes (Improving Journeys) - Salford Crescent to MediaCityUK.Approved
  6. Better Bus Routes: Salford Crescent to Salford Quays - TfGM Grant FundingApproved

More from Salford Property / Regeneration Briefing

All decisions
MeetingDecisionOutcome
14 Sep 2026 Retail Unit1 1 New BaileySalford City Council - Record of Decision I, Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning... Approved Open
14 Sep 2026 Housing Development at Robert Hall Street, Ordsall - Appointment of ContractorsSalford City Council - Record of Decision Affordable Housing Development - A2 Robert Hall Street, Ordsall I Councillo... Approved Open
24 Aug 2026 One New Bailey, ProposalSalford City Council - Record of Decision I Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning,... Approved Open
24 Aug 2026 One New Bailey, 2023 Rent ReviewSalford City Council - Record of Decision I Councillor Mike McCusker, Deputy City Mayor and Lead Member for Planning,... Agreed Open