Salford City Council
Procurement Board, Monday 27 July 2026 at 2.00pm

Better Bus Routes - Salford Crescent to MediaCityUK - Bus Stop Upgrades going out to tender/ competition (Matthew Mollart)

Approved Committee 1 paper

AI summarySalford City Council approves tender for bus stop upgrades between Salford Crescent and MediaCityUK, with an estimated construction cost of £400,000 funded by CRSTS grant.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedfor Salford Crescent to MediaCityUK bus stop upgrades
Money£400,000 estimated construction costfunded by CRSTS grant via GMCA
What happens nextTender September/October 2026with site works from February to August 2027
Who it affectsFour Salford wardsOrdsall, Pendleton and Charlestown, Weaste and Seedley, and Quays

What was decided

The Lead Member for Corporate Services approved going out to tender for the bus stop upgrades on the route of the number 50 bus between Salford Crescent and MediaCityUK. Report P10

The procurement will be run via an existing highways framework, in line with the Council's Contract Procurement Rules. Report P8, P30

The scheme will return to Procurement Board for approval to award the contract after tender assessment. Report P11

Why

The upgrades are intended to cut bus journey times, improve reliability, and provide more accessible and safer waiting environments for passengers. Report P4, P5

The scheme supports the region's target of being carbon neutral by 2038 by improving integration of sustainable travel modes. Report P34, P35

Securing funding at this stage reduces the risk of insufficient funding or additional unfunded costs at later stages.

What happens next

Tender to be issued in September or October 2026, with appraisal and moderation in November 2026. Report P9

Procurement Board will consider approval to award in December 2026, followed by Transport for Greater Manchester business case approval in January 2027. Report P9

Site works are scheduled to run from February 2027 to August 2027. Report P9

The money

  • £400,000 Estimated construction costs for the bus stop upgrades Report P6

Options considered

  • Chosen: Procure via existing Salford City Council Highways Framework. Compliant with Council Contract Procurement Rules and CSO requirement to use a suitable framework Report P8, P22, P23, P30
  • Rejected: Consider alternative compliant frameworks if packaging of work phases makes them more suitable. Not preferred at this stage; may be revisited if packaging changes Report P8
  • Rejected: Options considered and rejected. None stated

Implications

  • Financial: All costs will be funded by CRSTS grant from the Department for Transport via GMCA within the 2026/2027 Infrastructure Capital Programme; Salford will recover expended fees via a Grant Claim process. Report P7, P27, P29
  • Risk: Risk assessed as Medium: construction inflation since the CRSTS settlement was set may erode what can be delivered, and any cost overruns must be met locally with no additional government funding. Report P15, P16, P17
  • Legal: Procurement must comply with procurement legislation and the Council's Contractual Standing Orders, Financial Regulations, and Best Value and Social Value duties; using a compliant framework minimises legal challenge risk. Report P22, P23
  • Equalities: The improvements are intended to reduce transport-related barriers to equal access for a wide range of users. Report P13
  • Climate: The scheme supports the region's carbon neutral by 2038 target by enabling more sustainable travel choices. Report P34, P35

Who and where

  • Bus passengers using the number 50 service between Salford Crescent and MediaCityUK Report P4, P5
  • Residents of Ordsall, Pendleton and Charlestown, Weaste and Seedley, and Quays wards Report P40
  • Walking and cycling users along the route Report P4
  • Users of connecting Metrolink stops and rail stations Report P4

Timeline

  • September/October 2026: Tender issued Report P9
  • November 2026: Tender appraisal and moderation Report P9
  • December 2026: Procurement Board to consider approval to award Report P9
  • January 2027: Transport for Greater Manchester business case approval Report P9
  • February 2027 to August 2027: Site works for bus stop upgrades Report P9

Plain English for the jargon

  • CRSTS: City Region Sustainable Transport Settlement, a government grant funding stream
  • BBR / SCMC: Better Bus Routes / Salford Crescent to MediaCityUK project
  • GMCA: Greater Manchester Combined Authority
  • TfGM: Transport for Greater Manchester
  • HMG: Her Majesty's Government
  • CSO: Contractual Standing Orders
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6d

Resolved

Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the Procurement Board), accept the recommendation of the Procurement Board and in exercise of the powers contained within the Council Constitution do hereby: · approve to go out to tender/ competition for the proposed Salford Crescent to MediaCityUK – Bus Stop Upgrades. · endorse the proposed procurement route for the scheme, via an existing framework in accordance with the Council’s Contract Procurement Rules. The Reasons are : The bus stop improvements proposed as part of this package of works, will improve access to and the integration of sustainable travel modes for the residents of Salford and beyond. And help support the regions target of being carbon neutral by 2038. Options considered and rejected were: None. Assessment of Risk: Medium. The process of setting budgets for the CRSTS funding settlement which took place several years ago, means that inflationary pressures in the construction sector have increased substantially since the funding allocations were bid for and agreed. The government funding letter to Greater Manchester confirms ‘Any cost overruns must be met locally and no additional HMG (Government) funding from this settlement will be provided to support your CRSTS programmes’. This means that the work funded by the programme may have to be reduced in scope as inflation pressures continue to erode what can be delivered with the funding allocated. It will be important to develop the interventions working in close collaboration with the Greater Manchester and Active Travel England governance and approval gateway processes, to ensure the risk of funding claw back is minimised as projects progress beyond development to the delivery phase of the project. Securing funding for the SI work at this stage, reduces the risk of insufficient funding/additional unfunded costs at future work stages. The source of funding is : Grant funding from the City Region Sustainable Transport Settlement (CRSTS). Legal Advice obtained : Yes – see report presented at Procurement board of 27 th July 2026. Financial Advice obtained: Yes – see report presented at Procurement board of 27 th July 2026. Procurement Advice obtained: Yes – see report presented at Procurement board of 27 th July 2026. HR Advice obtained: N/A. Climate Change Advice obtained: Yes – see report presented at Procurement board of 27 th July 2026. The following documents have been used to assist the decision process: · GMCA Combined Authority Report – 25th November 2022. · Property and Regeneration – Decision – 28th August 2023. · Property and Regeneration – Decision – 12th May 2025. · Property and Regeneration - Decision – 12th January 2026. Contact Officer: Matthew Mollart Telephone number: [phone removed] · The Lead Member is supportive of the decision. Signed: Cllr Cusack Dated: 27 July 2026. Lead Member For Democratic Services use only: · This decision was published on 28 July 2026. · This decision will come in force at 4.00 p.m. on 4 August 2026 unless it is called-in in accordance with the Decision Making Process Rules.
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

Executive summary

The purpose of this report is to request approval to go out competition for the delivery of the abovementioned project.

BACKGROUND DOCUMENTS: GMCA Combined Authority Report – 25th November 2022 Property and Regeneration – Decision – 28th August 2023 Property and Regeneration – Decision – 12th May 2025 Property and Regeneration - Decision – 12th January 2026

KEY DECISION: Not at this stage

Sample A – going out to tender DETAILS: 1. Project Overview 1.1. The Better Bus Routes (BBR)/ Improving Journeys – Salford Crescent to MediaCityUK (SCMC) project, proposes improvements along part of the route of the existing number 50 bus service, between Salford Crescent and on the Bund (The Quays loop road), serving MediaCity. 1.2. This part of the route follows the Crescent, Broad Street, Belvedere Road, Hankinson Way, Fitzwarren Street, Liverpool Street, Langworthy Road, South Langworthy Road, Broadway and The Quays. 1.3. The proposed interventions aim to: • Reduce the journey time and improve the reliability of bus services that connect Salford Crescent and Salford Quays • Improve the actual and perceived bus waiting environment, ensuring these are fully accessible and provide a comfortable, safe space for passengers, including the provision of information for bus users on onward journeys. • Improve the actual and perception of integration between bus stops and destinations, Metrolink stops and rail stations. • Improve actual and perception of walking and cycling networks through improved accessibility via new cycle and walking infrastructure including safer routes and public realm improvements. • Increase bus patronage and the number of cycling and walking trips between Salford Crescent and Salford Quays.

2. Bus Stop Upgrades 2.1. A key component of the SCMC project and delivering on the project’s objectives are the upgrade of the existing bus stops on the route of the 50 bus service. 2.2. In total there are twelve number of bus stops in the programme which are proposed to be upgraded in some way including, new shelters, additional shelters and raised platforms.

Sample A – going out to tender 3. Estimated Construction Costs 3.1. The estimated construction costs for the bus stop upgrades are £400,000.

4. Project Funding 4.1. Funding for the project delivery, will (if approved) come from CRSTS provisions, with approvals for the required funding being sought by TfGM through TfGM/ GMCA governance procedures such as the Bee Network Committee. 4.2. Salford City Council will recover all expended fees/ costs via a Grant Claim process.

5. Procurement Route 5.1. The proposed route to procurement is via the existing Salford City Council Highways Framework. 5.2. Alternative compliant frameworks in line with the City Council’s Contract Procurement rules will also be considered if packaging of the different work phases associated with the project makes alternative frameworks more suitable for scheme delivery.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Better Bus Routes: Salford Crescent to MediaCityUK: Bus Stop Upgrades going out to tender/ competition (Matthew Mollart)Report 99 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 10 attended
PC
Philip CusackChair, present
PD
Paul DennettCommittee Member, apologies due to council business
TK
Tracy KellyCommittee Member, present
MM
Mike McCuskerCommittee Member, present
MB
Michele BarnesCommittee Member, apologies
JC
Jim CammellCommittee Member, apologies
BB
Barbara BenthamCommittee Member, present
HR
Hannah Robinson-SmithCommittee Member, absent
AH
Anthony HiltonOfficer, apologies
CH
Chris HowlClerk, present

On this subject at Salford

Search all
  1. Better Bus Routes - Salford Crescent to MediaCityUK - Bus Stop Upgrades going out to tender/ competition (Matthew Mollart)This decision
  2. Approval to Award the Contract for Better Bus Routes/ Improving Journeys - Salford Crescent to MediaCityUK - Site Investigation (Matthew Mollart)Approved
  3. Better Bus Routes - Salford Crescent to MediaCityUK - the Bund going out to tender/ competition (Matthew Mollart)Approved
  4. Better Bus Routes (Improving Journeys) - Salford Crescent to MediaCityUK.Approved
  5. Better Bus Routes - Wave 2 EngagementApproved
  6. Better Bus Routes: Salford Crescent to Salford Quays - TfGM Grant FundingApproved

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies