Procurement Board, Monday 27 July 2026 at 2.00pm

Better Bus Routes - Salford Crescent to MediaCityUK - the Bund going out to tender/ competition (Matthew Mollart)

Approved Committee 1 paper

AI summarySalford City Council approved going out to tender for bus stop and road improvements on The Bund between Salford Crescent and MediaCityUK, with construction costs of £650,000 funded by a CRSTS grant.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedProcurement via Bolton Highways Framework endorsed
Money£650,000Estimated construction costs, CRSTS grant funded
What happens nextTender autumn 2026Site works planned April 2027 to November 2027
Who it affectsQuays ward bus passengersRoute from Salford Crescent to MediaCityUK

What was decided

Approval was given to issue a tender for the Salford Crescent to MediaCityUK The Bund package of works. Report P1, P2, P13

The procurement route via an existing framework, the Bolton Highways Framework, was endorsed as compliant with the Council's Contract Procurement Rules. Report P2, P10, P14, P25, P33

The scheme will return to Procurement Board for approval to award the contract following tender assessment. Report P14, 6.2

Why

The improvements are intended to reduce bus journey times and improve reliability between Salford Crescent and Salford Quays, and to improve the waiting environment and integration with Metrolink, rail and walking and cycling networks. Report P6, P7

The bus stop on The Bund is the only stop directly serving MediaCity, with over 20,000 passenger boardings recorded in February and March 2026. Report P7

The package supports council policies on tackling the climate emergency, promoting transport connectivity, and creating vibrant places. Report P15, P16

What happens next

Tender to be issued in October or November 2026, with appraisal and moderation in January 2027. Report P11

Procurement Board to consider approval to award in February 2027, subject to TfGM business case approval in March 2027. Report P11

Site works are scheduled to run from April 2027 to November 2027. Report P11

The money

  • £650,000 Estimated construction costs for The Bund works Report P8

Options considered

  • Chosen: Procure via the existing Bolton Highways Framework. Framework was let in accordance with the Public Contracts Regulations 2015 and CSOs require use of a suitable framework Report P10, P25, P33
  • Not rejected: Consider alternative compliant frameworks. May be more suitable depending on packaging of different work phases Report P10

Implications

  • Financial: CRSTS budgets were set several years ago and inflationary pressures in construction may reduce the scope of work deliverable within the funding allocation. Any cost overruns must be met locally with no additional government funding from the settlement. Report P18, P19, P20
  • Legal: Procurement must comply with the Public Contracts Regulations 2015, the Council's Contractual Standing Orders, Financial Regulations, and best value and social value duties, acting transparently and without discrimination. Report P24, P25
  • Equalities: The transport network can be a barrier to equal access; the project is expected to deliver improvements for a wide range of users. Report P16
  • Climate: The completed project will enable more sustainable travel choices along the route, supporting safe and accessible access to public transport. Report P36, P37, P38
  • Risk: Risk assessment rated Medium, with ongoing need to work with Greater Manchester and Active Travel England governance to minimise the risk of funding clawback as projects move into delivery. Report P17, P18, P20

Who and where

  • Bus passengers using the stop on The Bund, the only stop directly serving MediaCity Report P7
  • Residents and workers travelling between Salford Crescent and Salford Quays and MediaCityUK Report P6
  • Pedestrians and cyclists using routes between Salford Crescent and Salford Quays Report P6
  • Ward: Quays Report P43

Timeline

  • 27 July 2026: Decision signed by Cllr Cusack, Lead Member for Corporate Services
  • 28 July 2026: Decision published
  • 4 August 2026 (4.00 p.m.): Decision comes into force unless called in
  • October or November 2026: Tender to be issued Report P11
  • January 2027: Tender appraisal and moderation Report P11
  • February 2027: Procurement Board approval to award Report P11
  • March 2027: TfGM Business Case approval Report P11
  • April 2027 to November 2027: Site works Report P11

Plain English for the jargon

  • CRSTS: City Region Sustainable Transport Settlement, a government transport funding settlement administered via Greater Manchester
  • BBR: Better Bus Routes, the wider programme of which this scheme forms part
  • SCMC: Salford Crescent to MediaCityUK, the corridor this project covers
  • TfGM: Transport for Greater Manchester
  • GMCA: Greater Manchester Combined Authority
  • The Bund: The Quays loop road; the location of the upgraded bus stop outside the Alchemist restaurant
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6e

Resolved

Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the Procurement Board, accept the recommendation of the Procurement Board and in exercise of the powers contained within the Council Constitution do hereby: · approve to go out to tender/ competition for the proposed Salford Crescent to MediaCityUK – The Bund. · endorse the proposed procurement route for the scheme via an existing framework in accordance with the Council’s Contract Procurement Rules. The Reasons are : The improvements proposed as part of this package of works, will improve access to and the integration of sustainable travel modes for the residents of Salford and beyond. Options considered and rejected were: None. Assessment of Risk: Medium. The process of setting budgets for the CRSTS funding settlement which took place several years ago, means that inflationary pressures in the construction sector have increased substantially since the funding allocations were bid for and agreed. The government funding letter to Greater Manchester confirms ‘Any cost overruns must be met locally and no additional HMG (Government) funding from this settlement will be provided to support your CRSTS programmes’. This means that the work funded by the programme may have to be reduced in scope as inflation pressures continue to erode what can be delivered with the funding allocated. It will be important to develop the interventions working in close collaboration with the Greater Manchester and Active Travel England governance and approval gateway processes, to ensure the risk of funding claw back is minimised as projects progress beyond development to the delivery phase of the project. Securing funding for the SI work at this stage, reduces the risk of insufficient funding/additional unfunded costs at future work stages. The source of funding is : Grant funding from the City Region Sustainable Transport Settlement (CRSTS). Legal Advice obtained : Yes – see report presented at Procurement board of 27 th July 2026. Financial Advice obtained: Yes – see report presented at Procurement board of 27 th July 2026. Procurement Advice obtained: Yes – see report presented at Procurement board of 27 th July 2026. HR Advice obtained: N/A. Climate Change Advice obtained: Yes – see report presented at Procurement board of 27 th July 2026. The following documents have been used to assist the decision process: · GMCA Combined Authority Report – 25th November 2022. · Property and Regeneration – Decision – 28th August 2023. · Property and Regeneration – Decision – 12th May 2025. · Property and Regeneration - Decision – 12th January 2026. Contact Officer: Matthew Mollart Telephone number: [phone removed] · The Lead Member is supportive of the decision. Signed: Cllr Cusack Dated: 27 July 2026. Lead Member For Democratic Services use only; · This decision was published on 28 July 2026. · This decision will come in force at 4.00 p.m. on 4 August 2026 unless it is called-in in accordance with the Decision Making Process Rules.
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

Recommendation

That Procurement Board recommends (Councillor Cusack, Lead Member for Corporate Services and Chairman of the Procurement Board) OR (Paul Dennett, City Mayor) to grant authority for the, Salford Crescent to MediaCityUK – The Bund, as set out below

1. Approval to issue a tender for the proposed Salford Crescent to MediaCityUK – The Bund 2. Endorses the proposed procurement route for the scheme via an existing framework in accordance with the Council’s Contract Procurement Rules.

Executive summary

The purpose of this report is to request approval to go out competition for the delivery of the abovementioned project/scheme/service or purchase of goods.

BACKGROUND DOCUMENTS: GMCA Combined Authority Report – 25th November 2022 Property and Regeneration – Decision – 28th August 2023 Property and Regeneration – Decision – 12th May 2025 Property and Regeneration - Decision – 12th January 2026

Sample A – going out to tender KEY DECISION: Not at this stage

DETAILS: 1. Project Overview 1.1. The Better Bus Routes (BBR)/ Improving Journeys – Salford Crescent to MediaCityUK (SCMC) project, proposes improvements along part of the route of the existing number 50 bus service, between Salford Crescent and on the Bund (The Quays loop road), serving MediaCity. 1.2. This part of the route follows the Crescent, Broad Street, Belvedere Road, Hankinson Way, Fitzwarren Street, Liverpool Street, Langworthy Road, South Langworthy Road, Broadway and The Quays. 1.3. The proposed interventions aim to: • Reduce the journey time and improve the reliability of bus services that connect Salford Crescent and Salford Quays • Improve the actual and perceived bus waiting environment, ensuring these are fully accessible and provide a comfortable, safe space for passengers, including the provision of information for bus users on onward journeys. • Improve the actual and perception of integration between bus stops and destinations, Metrolink stops and rail stations. • Improve actual and perception of walking and cycling networks through improved accessibility via new cycle and walking infrastructure including safer routes and public realm improvements. • Increase bus patronage and the number of cycling and walking trips between Salford Crescent and Salford Quays.

2. The Bund 2.1. A key component of the SCMC project and delivering on the project’s objectives is the upgrade of the existing bus stop on the bund, outside the Alchemist restaurant. 2.2. The stop, is the only bus stop that directly serves MediaCity and is extensively used, with passenger boarding data showing that in excess of 20,000 passengers boarded a bus at this stop in February and March 2026 and with a month on month increase in boarding since December 2025. 2.3. The proposed improvements in summary sees; an upgrade to the existing bus stops through the introduction of a larger shelter at the boarding stop, raised boarding platforms, footway widths increased by reducing overall carriageway width and the introduction of a new controlled crossing.

Sample A – going out to tender 3. Estimated Construction Costs 3.1. The estimated construction costs for the bund are £650,000.

4. Project Funding 4.1. Funding for the project delivery, will (if approved) come from CRSTS provisions, with approvals for the required funding being sought by TfGM through TfGM/ GMCA governance procedures such as the Bee Network Committee. 4.2. Salford City Council will recover all expended fees/ costs via a Grant Claim process.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Better Bus Routes: Salford Crescent to MediaCityUK: the Bund going out to tender/ competition (Matthew Mollart)Report 98 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 10 attended
PC
Philip CusackChair, present
PD
Paul DennettCommittee Member, apologies due to council business
TK
Tracy KellyCommittee Member, present
MM
Mike McCuskerCommittee Member, present
MB
Michele BarnesCommittee Member, apologies
JC
Jim CammellCommittee Member, apologies
BB
Barbara BenthamCommittee Member, present
HR
Hannah Robinson-SmithCommittee Member, absent
AH
Anthony HiltonOfficer, apologies
CH
Chris HowlClerk, present

On this subject at Salford

Search all
  1. Better Bus Routes - Salford Crescent to MediaCityUK - the Bund going out to tender/ competition (Matthew Mollart)This decision
  2. Approval to Award the Contract for Better Bus Routes/ Improving Journeys - Salford Crescent to MediaCityUK - Site Investigation (Matthew Mollart)Approved
  3. Better Bus Routes - Salford Crescent to MediaCityUK - Bus Stop Upgrades going out to tender/ competition (Matthew Mollart)Approved
  4. Better Bus Routes (Improving Journeys) - Salford Crescent to MediaCityUK.Approved
  5. Better Bus Routes - Wave 2 EngagementApproved
  6. Better Bus Routes: Salford Crescent to Salford Quays - TfGM Grant FundingApproved

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open