Procurement Board, Monday 26 January 2026 at 2.00pm

Little Hulton Children’s Centre – Internal alterations (Dora Lo/ Tracy Squirrell)

Approved Committee 1 paper

AI summarySalford City Council's Procurement Board awards a £378,072 construction contract to Schofield and Sons Ltd for internal refurbishment at Little Hulton Nursery, creating a specialist SEND hub.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedInternal refurbishment at Little Hulton Nursery
Money£378,072 construction, £437,000 totalIncludes £58,928 professional fees and associated works
What happens nextContract starts 03/02/2026Ends 24/04/2026, with up to 2 months extension
Who it affectsLittle Hulton wardChildren with SEND, including high-level ASC needs

What was decided

The Lead Member for Finance and Support Services accepted the Procurement Board's recommendation to award the contract for Little Hulton Nursery Internal Refurbishment Works to Schofield and Sons Ltd.

The award followed a mini competition under the Minor Building Works Framework, Lot 1, with five companies tendering and Schofield and Sons Ltd scoring highest at 84.85%. Report P17, P18, P24

The works will refurbish and reconfigure the children's centre to create a discrete specialist SEND hub alongside the existing nursery, delivered in phases 2 and 3. Report P10, P11, P14, P15

Why

Salford has seen a steady increase in requests for specialist SEND and alternative provision, with about 70% of EHCP requests requiring specialist provision. Report P9

The Little Hulton Children's Centre site was identified as suitable due to available space, enabling the creation of a self-contained specialist provision for children with complex needs such as high-level ASC. Report P10, P11

What happens next

Schofield and Sons Ltd will carry out the works between 03/02/2026 and 24/04/2026, with optional extensions of up to one month each, approved by the Executive Director if under £150,000. Report P1

Social value commitments will be monitored throughout the project, with the initial £16,378.33 value expected to be exceeded. Report P32

The money

  • £378,072.00 Construction costs awarded to Schofield and Sons Ltd Report P1, P24
  • £437,000.00 Total project value including surveys, professional fees and associated works Report P1
  • £58,928 Professional fees element of total project value Report P46
  • £16,378.33 Social value from Schofield and Sons Ltd tender, independently evaluated Report P26, P32

Options considered

  • Chosen: Award contract to Schofield and Sons Ltd (highest scoring at 84.85%). Most economically advantageous tender that also supports social value Report P24
  • Rejected: Award to Provider E (84.63%). Scored lower than Schofield and Sons Ltd Report P23, P24
  • Rejected: Award to Provider D (84.14%). Scored lower than Schofield and Sons Ltd Report P22, P24
  • Rejected: Award to Provider C (80.87%). Scored lower than Schofield and Sons Ltd Report P21, P24
  • Rejected: Award to Provider B (80.07%). Lowest scoring bidder Report P20, P24
  • Rejected: Do nothing or alternative approaches. The decision record states no alternative options were considered or rejected

Implications

  • Financial: Funded from the SEND grant allocation, recognised within the Children's Services Capital Programme. Report P40, P46
  • Legal: Procurement followed Public Contracts Regulations 2015 and the Council's Contractual Standing Orders via the Minor Building Works Framework, Lot 1. Legal advice from Tony Hatton, Solicitor, on 13.01.2026. Report P41, P42, P43
  • Risk: Assessed as High risk: failure to complete works within timescales could result in the city council failing to provide sufficient school places. Report P37, P38
  • Equalities: All works will be undertaken in accordance with relevant Equality and DDA legislation and guidance. Report P36
  • Climate: No significant climate change implications. Projects support the Council's objective of becoming carbon neutral by 2038. Waste will be sorted and recycled to minimise landfill. Report P51, P52, P53
  • Other: Service group should consider efficiencies and enhanced contract management KPIs as part of the contract, given council budget challenges. Report P49

Who and where

  • Children and young people with SEND requiring specialist provision, including those with high-level ASC Report P9, P10
  • Users of Little Hulton Nursery and Children's Centre in Little Hulton ward Report P11, P56
  • Local Salford-based supply chain and SMEs Report P30
  • Unemployed local people and those not in education, employment or training, supported via the Kings Trust partnership Report P28, P29
  • VCSEs and SMEs receiving expert support from the contractor Report P31

Timeline

  • 13.01.2026: Legal advice obtained from Tony Hatton, Solicitor Report P41
  • 14.01.2026: Financial implications submitted by Adam Mozley, Accountant Report P44
  • 2026-01-26: Procurement Board meeting and decision
  • 03/02/2026: Contract start date for internal refurbishment works Report P1
  • 24/04/2026: Contract end date for the 12-week refurbishment programme Report P1

Plain English for the jargon

  • SEND: Special Educational Needs and Disabilities
  • EHCP: Education, Health and Care Plan, a formal assessment of a child's special educational needs
  • ASC: Autism Spectrum Condition
  • VCSE: Voluntary, Community and Social Enterprise organisations
  • SME: Small and Medium-sized Enterprises
  • ITT: Invitation to Tender, the procurement method used
  • DDA: Disability Discrimination Act, governing accessibility requirements
  • TOMs: Themes, Outcomes and Measures, the framework used to evaluate social value
  • CSO: Contractual Standing Orders, the Council's procurement rules
  • PCR: Public Contracts Regulations 2015, governing public procurement
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5c

Resolved

Salford City Council – Record of Decision I Councillor Youd, Lead Member for Finance and Support Services and chairman of the Procurement Board, accept the recommendation of the Procurement Board and in exercise of the powers contained within the Council Constitution do hereby approve: · to Award the Contract forLittle Hulton Nursery Internal Refurbishment Works, as detailed in the table below: Detail required Answers Title/ Description of Contracted Service/Supply/Project Little Hulton Nursery Internal Refurbishment Works Procurement Reference numbers (DN and CR number supplied by Procurement) S1144-113 Name of Successful Contractor Schofield and Sons Ltd Supplier Registration Number (to be supplied by Procurement 02459259 Proclass Classification No. (to be completed by procurement) 390000 – Works – Construction, Repair & Maintenance Type of organisation (to be supplied by Procurement) Private Limited Company Status of Organisation (to be supplied by Procurement) SME Contract Value (£) £378,072.00 construction costs Total contract value £ (including extensions) £437,000.00 total project value including surveys, professional fees and associated works Contract Duration 12 Weeks Contract Start Date 03/02/2026 Contract End Date 24/04/2026 Optional Extension Period 1 months Optional Extension Period 2 months Who will approve each Extension Period? Executive Director (extension < £150k) Contact Officer (Name & number) Adam Vanden Lead Service Group Children's Services How the contract was procured? (to be supplied by procurement) ITT Framework Details (where applicable) (procurement body, framework reference & title, start/ end date Minor Building Works Framework, Lot 1 Funding Source Capital Programme Ethical Contractor (EC): Mayor’s Employment Charter Yes EC: Committed to sign The Mayor’s Employment Charter N/A EC: Committed to the principles outlined in the Mayor’s Employment charter N/A EC: Accredited Living Wage Employer Yes EC: Committed to becoming Accredited Living wage Employer N/A The Reasons: are for the refurbishment and remodelling of the children’s centre to create a specialist SEND hub. Options considered and rejected were : None. All procedures are in accordance with normal contractual standing orders. Assessment of Risk : High Failure to complete the works within the timescales could result in the city council failing to provide sufficient school places. The source of funding is : SEND Capital. Legal Advice obtained - Tony Hatton, Solicitor, 13.01.2026 When commissioning contracts for the procurement of goods, services, or the execution of works, the Council must comply with the Public Contracts Regulations 2015 (PCR) (for contracts and frameworks let before 28th February 2025) and its own Contractual Standing Orders (CSO’s), failing which a contract may be subject to legal challenge from an aggrieved provider. CSO’s stipulate that where a suitable framework agreement exists, this must be used unless there is an auditable reason not to. The proposed award of contract follows a tender exercise by mini competition in accordance with the Minor Building Works Framework, Lot 1. The Council will need to have followed the procedure set out in the framework agreement for mini competition to ensure that the procurement process is compliant. Five companies from the framework suppliers submitted a tender, and the bid has been evaluated on the most economically advantageous ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

Recommendation

That Procurement Board approve the award of the Contract for Little Hulton Nursery Internal Refurbishment Works as detailed in the table below: Detail required Answers Title/Description of Contracted Little Hulton Nursery Internal Refurbishment Service/Supply/Project Works Procurement Reference numbers (DN and S1144-113 CR number supplied by Procurement) Name of Successful Contractor Schofield and Sons Ltd Supplier Registration Number 02459259 (to be supplied by Procurement Proclass Classification No. 390000 – Works – Construction, Repair (to be completed by) & Maintenance Type of organisation Private Limited Company (to be supplied by Procurement) Status of Organisation SME (to be supplied by Procurement) Contract Value (£) £378,072.00 construction costs Total contract value £ (including £437,000.00 total project value including extensions) surveys, professional fees and associated works Contract Duration 12 Weeks Contract Start Date 03/02/2026 Contract End Date 24/04/2026 Optional Extension Period 1 months Optional Extension Period 2 months Who will approve each Extension Period? Executive Director (extension < £150k) Contact Officer (Name & number) Adam Vanden Lead Service Group Children's Services How the contract was procured? ITT (to be supplied by procurement) Framework Details (where applicable) (procurement body, framework reference Minor Building Works Framework, Lot 1 & title, start/ end date Funding Source Capital Programme Ethical Contractor (EC): Mayor’s Yes Employment Charter N/A EC: Committed to sign The Mayor’s Employment Charter

EC: Committed to the principles outlined N/A in the Mayor’s Employment charter Yes EC: Accredited Living Wage Employer

EC: Committed to becoming Accredited N/A Living wage Employer ☒

Executive summary

The purpose of this report is to seek approval for the award of the above mentioned contract.

BACKGROUND DOCUMENTS:

Exempt under Paragraph 3 of Schedule 12A of the Local Government Act 1972 ‘Tender Submissions and Evaluation Documents’

KEY DECISION: Yes

DETAILS:

Background

Salford City Council has experienced a steady increase in requests for specialist SEND and alternative provision for children and young people, with approximately 70% of EHCP request requiring specialist provision.

Children’s Services have undertaken a feasibility study to develop a SEND hub for children with more complex needs, such as high-level ASC (Autism Spectrum Condition). The site at Little Hulton Children’s Centre has been identified as suitable due to its available space, enabling the creation of a discrete specialist provision.

The scheme proposes to utilise the existing external playground and two large internal classroom spaces within the Nursery. This will require refurbishment and reconfiguration of the Children’s Centre layout and functionality to accommodate both the Nursery and the SEND hub within the same site.

As part of the scheme, we are separating the works into 3 phases.

Phase 1: New extension has been completed. This has created new space to facilitate the Nursery’s operation.

Phase 2: Remodelling of two existing classrooms, office and corridor space into three classrooms. This will ultimately provide 4 classrooms for the Nursery. Phase 3: The remaining classrooms, taken from the Nursery, will be refurbished and remodelled to create a self-contained outreach hub, including staff rooms, teacher working room, and new children’s WCs.

This report recommends the approval of Schofield and Sons Ltd to undertake the internal refurbishment works phase 2 and 3.

2. The Procurement Process

The works for the project were tendered under the Council’s e-tendering portal in accordance with the council's Contractual Standing Orders. Tenders were let by competition under the Minor Building Works Framework Lot 1 via The Chest.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Little Hulton Children’s Centre: Internal alterations (Dora Lo/ Tracy Squirrell)Report 118 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 9 attended
BB
Barbara BenthamInvitee, in attendance
PD
Paul DennettCommittee Member, apologies due to council business
AH
Anthony HiltonOfficer, apologies
CH
Chris HowlClerk, present
TK
Tracy KellyCommittee Member, apologies
MM
Mike McCuskerInvitee, in attendance
JM
John Merry CBECommittee Member, present
TP
Teresa PepperCommittee Member, apologies
JY
Jack YoudChair, present

On this subject at Salford

Search all
  1. Little Hulton Children’s Centre – Internal alterations (Dora Lo/ Tracy Squirrell)This decision
  2. Longshaw Drive, Little Hulton - Transfer of Market Rent Homes to DeriveApproved
  3. Land at Lester Road, Little HultonApproved
  4. Brackley Village Development, Little Hulton - Transfer of Properties (also see item 6b)Approved
  5. Peel Park Pavilion, Little HultonApproved
  6. Approval to Award the Contract for the Delivery of Solar Farm at Little HultonApproved

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies