Approval to Award the Contract for Monton Canal Bridge VRS Protection Scheme (Jack McClung)

Approved Committee 1 paper

AI summarySalford City Council has awarded Amalgamated Construction Limited a £220,352.15 contract for vehicle restraint system works on Monton Canal Bridge, running 14 weeks from March 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedMonton Canal Bridge VRS Protection Scheme, 14 weeks
Money£220,352.15 contract, £326,800.39 schemeFunded from 2025/26 Highways Capital Programme
What happens nextWorks from 02/03/2026 to 22/05/2026Subject to call-in by Growth and Prosperity Panel
Who it affectsNot stated

What was decided

Award the contract for the Monton Canal Bridge Vehicle Restraint System Protection Scheme to Amalgamated Construction Limited at a contract value of £220,352.15. Report P1, P2, P29

Run the contract for 14 weeks from 02/03/2026 to 22/05/2026 under Technical and Highway Works Framework Lot 4 (Structures & Bridges). Report P2, P21

Fund the works from the 2025/26 Highways Capital Programme, comprising CRSTS grant and unsupported borrowing. Report P17, P50, P60

Why

A routine structural inspection found the bridge's only edge protection was the edge beams themselves, so a vehicle impact could cause serious structural damage and loss of the structure. Report P11, P12

Amalgamated Construction Limited was the highest-scoring bidder at 89.6% in a mini-competition of five tenders (price 55%, quality 30%, social value 15%). Report P22, P23, P25, P29

Officers judge the risk as low; without the works, vehicle impact could close the bridge with no simple diversion route, and post-collision repair would cost substantially more. Report P46, P47, P48

What happens next

Contract starts 02/03/2026 and ends 22/05/2026, with traffic management via two-way lights off-peak and night closures with diversion for surfacing. Report P2, P14

The Growth and Prosperity Panel may call in the decision; the matter is not subject to consideration by another Lead Member.

All scheme spend should be closely monitored to ensure best value for money, against expenditure code D30049. Report P63, P64

The money

  • £220,352.15 Contract value to Amalgamated Construction Limited Report P2, P19
  • £326,800.39 Total scheme budget Report P2, P19, P60
  • £152,200.00 CRSTS grant from DfT via GMCA Report P17, P60
  • £174,600.39 Unsupported Borrowing allocation Report P17, P60
  • £50,000.00 Quantified Risk Assessment Report P19
  • £24,331.69 S&B Design Fee (9%) Report P19
  • £12,706.55 S&B Supervision Fee (4.7%) Report P19
  • £825.00 Principal Designer Report P19
  • £2,000.00 Highway Design Report P19
  • £6,600.00 Temporary Traffic Regulation Order Report P19
  • £9,985.00 Site investigation and trial holes Report P19
  • £41,250 Retained in 2025/26 for initial scheme costs Report P61
  • £61,452.66 Total social value committed for the project Report P34
  • £10,000 Minimum spend with local non-SME companies in Salford Report P37
  • £20,000 Forecast local SME spend through contract supply chain Report P38
  • £3,000 Minimum in-kind support to local community projects Report P39

Options considered

  • Chosen: Award the contract to Amalgamated Construction Limited. Highest-scoring bidder at 89.6% in compliant mini-competition under framework Lot 4. Report P25, P29, P69
  • Rejected: Not to award the contract. Would leave the bridge without proper vehicle restraint, risking structural damage and costly future repairs. Report P48

Implications

  • Financial: Adequate budget within £326,800.39; CRSTS grant plus unsupported borrowing; financial risk assessed as low with most costs already identified. Report P60, P62, P63
  • Legal: Procurement follows a call-off mini-competition under the Council's Technical and Highways Minor Civils Works Framework, compliant with PCR 2015 and the Council's Contractual Standing Orders. Report P54, P55, P56, P68
  • Equalities: No adverse equality implications; a well-maintained highway structure aids less able-bodied and visually impaired people and supports safe movement of the travelling public. Report P45
  • Risk: Risk judged low by the Engineering and Landscape Department; without the works, a vehicle impact could close the bridge with no easy diversion. Report P46, P47, P48
  • Other: Contractor not currently signed up to the Mayor's Employment Charter but has committed to sign; is an Accredited Living Wage Employer. Report P2, P3, P33

Who and where

  • Residents and road users in Eccles, Worsley & Westwood Park and Barton & Winton wards Report P74
  • Pedestrians, cyclists and vehicles using Parrin Lane over Monton Canal Bridge Report P13, P45
  • A minimum of 5 local people employed or retained, plus 3 subcontractor employees on site for at least 30 days Report P35
  • Salford schools receiving curriculum-linked road safety and environmental awareness engagement Report P36
  • Local non-SME companies and local SMEs in the supply chain (tarmac, aggregates, stone, sand, kerbs, gully posts) Report P37, P38
  • Local community projects receiving donations and staff volunteering Report P39, P40

Timeline

  • 5th November 2025: Tender documents issued via The Chest under Structures & Bridges Lot 4 Report P21
  • 5th December 2025: Original tender return date Report P21
  • 12th December 2025: Revised tender submission date after extension granted to contractors Report P21
  • 8th January 2026: Procurement advice received from Category Manager Report P67
  • 9th January 2026: Legal advice received from Principal Solicitor Report P53
  • 12th January 2026: Financial advice received from Senior Accountant Report P59
  • 26 January 2026: Decision published by Lead Member for Finance and Support Services
  • 02/03/2026: Contract start date Report P2
  • 22/05/2026: Contract end date Report P2

Plain English for the jargon

  • VRS: Vehicle Restraint System, safety barriers preventing vehicles leaving the road or hitting structures.
  • CRSTS: City Region Sustainable Transport Settlement, grant funding awarded to GMCA by the Department for Transport.
  • USB: Unsupported Borrowing, council borrowing not supported by central government revenue funding.
  • ITT: Invitation to Tender, a procurement method seeking competitive bids.
  • PCR 2015: Public Contracts Regulations 2015, the procurement rules the Council must follow.
  • CSO: Contractual Standing Orders, the Council's own procurement rules.
  • S&B: Structures & Bridges, the Council team managing this scheme.
  • TOMs: Themes, Outcomes and Measures, the social value framework used in evaluation.
  • trief kerbs: Kerbs designed to deflect errant vehicle wheels back into the carriageway, protecting bridge edges.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5a

Resolved

Salford City Council – Record of Decision I Councillor Youd, Lead Member for Finance and Support Services and chairman of the Procurement Board accept the recommendation of the Procurement Board and in exercise of the powers contained within the Council Constitution do hereby approve: · to Award the Contract forMonton Canal Bridge Vehicle Restraint System (VRS) Protection Scheme , as detailed in the table below: Detail required Answers Title/ Description of Contracted Service/Supply/Project Monton Canal Bridge VRS Protection Scheme Procurement Reference numbers (DN and CR number supplied by Procurement) DN794586 / S1232/122 Name of Successful Contractor Amalgamated Construction Limited Supplier Registration Number (to be supplied by Procurement 0995892 Proclass Classification No. (to be completed by procurement) 391200 Type of organisation (to be supplied by Procurement) Private Limited Company Status of Organisation (to be supplied by Procurement) Non-SME Contract Value (£) £ 220,352.15 Total Scheme value £ £ 326,800.39 Contract Duration 14 Weeks Contract Start Date 02/03/2026 Contract End Date 22/05/2026 Optional Extension Period 1 N/A Optional Extension Period 2 N/A Who will approve each Extension Period? Executive Director (extension < £150k) Contact Officer (Name & number) Jack McClung - [phone removed] Lead Service Group Place How the contract was procured? (to be supplied by procurement) ITT Framework Details (where applicable) (procurement body, framework reference & title, start/ end date Technical and Highway Works – Lot 4 – Structures & Bridges Funding Source Capital Programme Ethical Contractor (EC): Mayor’s Employment Charter No EC: Committed to sign The Mayor’s Employment Charter Yes EC: Committed to the principles outlined in the Mayor’s Employment charter N/A EC: Accredited Living Wage Employer Yes EC: Committed to becoming Accredited Living wage Employer N/A The Main works are Monton Canal Bridge Vehicle Restraint System Protection Scheme. Options considered and rejected were : Not to award the Contract. Assessment of Risk : Low – Salford City Council Engineering and Landscape Department are well versed in delivering works of this nature. The risk of not undertaking the works is that a vehicular collision could cause structural damage to the bridge resulting in a bridge closure and significant impact on the Highway Network, with no simple diversion route available to lessen the impact on the passage of vehicles. Furthermore, the cost for the repair works following vehicle collision are likely to be substantial in comparison to the cost of the vehicular restraint measures proposed. The source of funding is : the 2025/26 Highways Capital Programme. Legal Advice obtained : 9 th January 2026 – received from Tony Hatton, Principal Solicitor. Financial Advice obtained : 12 th January 2026 – Received from Ian Cowburn, Senior Accountant. Procurement Advice obtained: 8 th January 2026 – Received from Heather Stanton, Category Manager. Contact Officer: Jack McClung Telephone number: [phone removed] · This matter is not subject to consideration by another Lead Member. · The appropriate Scrutiny Committee to call-in the decision is the Growth and Prosperity Panel. Signed: Cllr J Youd Dated: 26 January 2026. Lead Member FOR DEMOCRATIC SERVICES USE ONLY * This decision was published on 26 January 2026 ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

Recommendation

That Procurement Board recommends Councillor Youd, Lead Member for Finance and Support Services and chairman of the Procurement Board approve the award of the Contract for Monton Canal Bridge Vehicle Restraint System (VRS) Protection Scheme, as detailed in the table below:

Monton Canal Bridge Vehicle Restraint System Protection Scheme – Procurement Board Report – Award of Contract Detail required Answers Title/Description of Contracted Monton Canal Bridge VRS Protection Service/Supply/Project Scheme Procurement Reference numbers (DN and DN794586 / S1232/122 CR number supplied by Procurement) Name of Successful Contractor Amalgamated Construction Limited Supplier Registration Number 0995892 (to be supplied by Procurement Proclass Classification No. 391200 (to be completed by procurement) Type of organisation Private Limited Company (to be supplied by Procurement) Status of Organisation Non-SME (to be supplied by Procurement) Contract Value (£) £ 220,352.15 Total Scheme value (£) £ 326,800.39 Contract Duration 14 Weeks Contract Start Date 02/03/2026 Contract End Date 22/05/2026 Optional Extension Period 1 N/A Optional Extension Period 2 N/A Who will approve each Extension Period? Executive Director (extension < £150k) Contact Officer (Name & number) Jack McClung - [phone removed] Lead Service Group Place How the contract was procured? ITT (to be supplied by procurement) Framework Details (where applicable) Technical and Highway Works – Lot 4 – (procurement body, framework reference Structures & Bridges & title, start/ end date Funding Source Capital Programme Ethical Contractor (EC): Mayor’s No Employment Charter Yes EC: Committed to sign The Mayor’s Employment Charter

EC: Committed to the principles outlined N/A in the Mayor’s Employment charter Yes EC: Accredited Living Wage Employer

Monton Canal Bridge Vehicle Restraint System Protection Scheme – Procurement Board Report – Award of Contract EC: Committed to becoming Accredited N/A Living wage Employer

Executive summary

The purpose of this report is to seek approval for the award of the above-mentioned contract.

BACKGROUND DOCUMENTS:

Bridge asset file held on Pontis (digital asset management system for bridges) and in the archive files within the Councils Bridges and Structures Department.

KEY DECISION:

No – if the value of the decision is between £150,000 and £349,999

DETAILS:

Background

Monton Canal Bridge carries Parrin Lane over the Bridgewater Canal in Monton.

During a routine structural inspection, it was identified that the only means of edge protection on the bridge, was in fact the edge beams of the structure. Whilst these would suitably stop vehicles from falling off the bridge into the watercourse below, should these edge beams suffer impact damage, there could be significant structural damage caused and in turn, loss of functionality of the structure resulting in the need for emergency repairs and in the worst case, replacement of the entire structure. This would cause serious disruption along Parrin Lane and the wider community of Monton.

It is intended that the scheme works will improve the safety of pedestrians (cyclists) and vehicles. The works involved in the scheme are as followed: • Installation of trief kerbs over the bridge • Widening of North Footway • Installation of bridge expansion joints • Resurfacing approximately 1900m2 of Parrin Lane and footways over structure (previously part of proposed SCC Highway Network Management Scheme, taken on by SCC Structures & Bridges team to minimise disruption to the Local Highway Network) • Reinstate Highway lining • General minor civils works

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approval to Award the Contract for Monton Canal Bridge VRS Protection Scheme (Jack McClung)Report 131 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 9 attended
BB
Barbara BenthamInvitee, in attendance
PD
Paul DennettCommittee Member, apologies due to council business
AH
Anthony HiltonOfficer, apologies
CH
Chris HowlClerk, present
TK
Tracy KellyCommittee Member, apologies
MM
Mike McCuskerInvitee, in attendance
JM
John Merry CBECommittee Member, present
TP
Teresa PepperCommittee Member, apologies
JY
Jack YoudChair, present

On this subject at Salford

Search all
  1. Approval to Award the Contract for Monton Canal Bridge VRS Protection Scheme (Jack McClung)This decision
  2. Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Approved
  3. Approval to Award the Contract for the continued use of the Line of Business System for Planning, Building Control and Local Land and Property Gazetteer (Anthony Stephenson)Approved
  4. Approval to Award the Contract for Statutory Homeless Supported Temporary Accommodation (Jane Barlow)Approved
  5. Approval to Award the Contract for the construction of affordable homes at Robert Hall St Ordsall (A2) Dylan VinceApproved
  6. Approval to Award the Contract for Better Bus Routes/ Improving Journeys - Salford Crescent to MediaCityUK - Site Investigation (Matthew Mollart)Approved

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open