Approval for an Award of Contract Extension for Greater Manchester Collaborative Contract for the Provision of Temporary Workers (Sam Betts)

Approved Committee 1 paper

AI summarySalford City Mayor approves an 18 month extension of the Greater Manchester temporary workers contract with Reed Specialist Recruitment, worth an estimated £10m for Salford.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSalford joins 18 month contract extension via Trafford
Money£10m estimated for SalfordAverage over 18 month extension period
What happens nextContract runs 29/01/2026 to 27/07/2027Collaborative group explores future delivery model
Who it affectsCouncil agency worker supplyAcross all council services needing temporary staff

What was decided

The City Mayor approved Salford City Council's continued participation in the 18 month contract extension of the Greater Manchester Collaborative Contract for the Provision of Temporary Workers with Reed Specialist Recruitment Ltd. Report P1, P2

The contract extension runs from 29/01/2026 to 27/07/2027, following the expiry of the existing term on 28/01/2026. Report P3, P6, P17

Why

The extension provides continuity of agency worker supply while the 16 participating authorities audit services and decide whether to move provision in house or run a competitive procurement for a future model. Report P17, P18, P19, P20

Without approval, the council would face higher agency rates, weaker compliance and safeguarding standards, and reputational damage within the collaborative group. Report P32, P33, P34

All HR Directors across Greater Manchester have approved this approach, and there will be no implementation costs, fee increases or transition period with the incumbent supplier. Report P20, P23

What happens next

Salford will work with Reed's Social Value lead to maximise local employment, care leaver, NEET and apprenticeship commitments for the city. Report P24

The collaborative group will use the 18 months to assess options, build a business case and mobilise a future-fit resourcing model. Report P17, P19, P28

Each service area will draw on the contract as required using existing financial protocols; there is no minimum spend commitment for Salford. Report P22, P46

The money

  • £10m estimated average for full 18mths duration Estimated Salford value of the contract extension Report P2
  • £30m estimated (non-committal average) Total estimated value of the awarded contract including extension period Report P2
  • £160m Projected spend across the entire GM collaboration for the extended period Report P22

Options considered

  • Rejected: Withdraw from the GM collaborative arrangements. Would expose the council to higher agency rates, weaker compliance and loss of collaborative influence on a future model. Report P32, P33

Implications

  • Financial: Funded from existing revenue budgets; no minimum spend and no fee increases under the extension. Report P3, P23, P45, P46
  • Legal: Extension compliant with Public Contracts Regulations 2015 and Contractual Standing Orders, using a clear review clause in the original 2022 contract documents. Report P39, P40, P41, P55, P56
  • Equalities: No negative impact identified; agency engagement arrangements remain unchanged from the current collaboration. Report P30
  • Climate: No climate change implications identified at this point. Report P63
  • Staffing: Provides stability for contingent labour access while HR explores a future-fit, potentially in-house, resourcing model across Greater Manchester. Report P17, P28, P57, P58, P59, P60, P61
  • Risk: Overall risk assessed as Low; risk arises mainly from the wider market, including national shortages in roles such as qualified social workers. Report P16

Who and where

  • Council services that use agency workers, including those filling hard-to-fill and niche roles Report P15, P27
  • Residents reliant on statutory services that depend on temporary staffing to remain operational Report P27
  • 16 participating Greater Manchester authorities, plus Blackpool, Blackburn with Darwen, GMP and Warrington Report P6, P20
  • Reed Specialist Recruitment Ltd as the incumbent supplier Report P2, P16, P23

Timeline

  • 29/01/2022 to 28/01/2026: Existing Greater Manchester Collaborative Contract term Report P3, P6
  • Jan 2025: Final 12 month extension was approved under the original contract award Report P52
  • 27.01.26: Financial implications provided by Finance Manager Report P44
  • 28/01/2026: Collaborative contract expired Report P17
  • 29/01/2026 to 27/07/2027: New 18 month extension period Report P3, P6

Plain English for the jargon

  • Beneficiary agreement: An arrangement allowing Salford to use a contract awarded by another council, in this case Trafford, without being the direct contracting party.
  • STaR Procurement: A procurement shared service operating on behalf of Stockport, Trafford, Bury and Rochdale councils, which led the mini-competition and contract modification.
  • YPO framework: A framework agreement operated by the Yorkshire Purchasing Organisation, used here for the original mini-competition to select the supplier.
  • PCR 2015: The Public Contracts Regulations 2015, the UK rules governing how public bodies award contracts for goods, services and works.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5b

Resolved

Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Board and in exercise of the powers contained within the Council Constitution do hereby: · approve Salford City Council’s participation in the Contract Extension of the existing Greater Manchester Collaborative Contract for the Provision of Temporary Workers , as detailed in the table below: Detail required Answers Contract Reference (to be supplied by procurement) S1036 Title/Description of Contracted Service/Supply/Project Permission for Salford City Council’s continued participation in the Contract Extension of the existing Greater Manchester Collaborative Contract for the Provision of Temporary Workers Name of Contractor Reed Specialist Recruitment Ltd Type of organisation (to be supplied by Procurement) Private Limited Company Status of Organisation (to be supplied by CoProcurement) Non-SME Value of Contract Extension (£) £10m estimated average for full 18mths duration Total value of Awarded (including extension period) £30m estimated (non-committal average) Existing Contract Term 29/01/2022 to 28/01/2026 Extension Period 29/01/2026 to 27/07/2027 Contact Officer (Name & number) Sam Betts 0161 607 8602 Lead Service Group Resources and Transformation Funding Source Revenue Budget Ethical Contractor (EC): Mayor’s Employment Charter Yes EC: Committed to sign the Mayor’s Employment Charter Yes EC: Committed to the principles outlined in the Mayor’s Employment Charter Yes EC: Accredited Living Wage Employer Yes EC: Committed to becoming Accredited Living wage Employer Yes The reasons are : For over a decade, the Council has worked collaboratively with other Greater Manchester authorities and partners to reduce costs, minimise risk, and ensure a consistent and compliant approach to engaging temporary workers. The current Greater Manchester Collaborative Contract, led by Trafford Council as the contracting authority, has been in place since 2016, with Salford participating through a beneficiary agreement. The Council is not committed to any level of spend and can draw on the contract as required. Reed Specialist Recruitment, the current provider, continues to deliver a largely effective service despite national shortages in key occupations such as qualified social workers. The collaborative contract expired on 28 January 2026; however, STaR Procurement, on behalf of Trafford and all participating authorities, has recommended an 18 ? month extension using Modification provisions. This extension acts as a safeguard while the collaboration explores alternative delivery models for the future, including potential in ? house options. The extension ensures continuity of service, avoids disruption, and provides the time needed to assess market options, build a business case, and mobilise any future model. This modification is required in order to allow all participating authorities to audit current services and decide if the service should be moved in house or if this will continue as external service and therefore a competitive process will be undertaken. Options considered and rejected were : Withdrawal from the GM collaborative arrangements. Assessment of risk : Low. The source of funding is : Revenue budget. Legal advice obtained: Tony Hatton, Shared Legal Service When commissioning contracts for the procurement of goods, services, or the execution of works, the Council must comply with the Public Contracts Regulations ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

Recommendation

That Procurement Board approve Salford City Council’s participation in the Contract Extension of the existing Greater Manchester Collaborative Contract for the Provision of Temporary Workers

Detail required Answers Contract Reference S1036 Title/Description of Permission for Salford City Council’s continued participation Contracted in the Contract Extension of the existing Greater Manchester Service/Supply/Project Collaborative Contract for the Provision of Temporary Workers Name of Contractor Reed Specialist Recruitment Ltd Type of organisation (to be supplied by Corporate Private Limited Company Procurement) Status of Organisation (to be supplied by Corporate Non-SME Procurement) Value of Contract Extension (£) £10m estimated average for full 18mths duration

Existing Contract Term 29/01/2022 to 28/01/2026 Extension Period 29/01/2026 to 27/07/2027 Contact Officer (Name & Samantha Betts number) 0161 607 8602 Lead Service Group Resources and Transformation Funding Source Revenue Budget

Permission to participate in the extension of the GM agency supply Reed framework contract Detail required Answers Ethical Contractor (EC): Mayor’s Employment Charter EC: Committed to sign the Charter EC: Accredited Living Wage Employer

Executive summary

The purpose of this report is to seek approval to participate in a further eighteen month extension of the existing Greater Manchester Collaborative Contract for the Provision of Temporary Workers - via the use of a beneficiary agreement with Trafford Council who are the contracting authority with the provider.

Modification of the existing agreement is available via the STAR Procurement procedures on behalf of all 16 participating authorities, allowing for the current agreement to be extended for period 29/01/2026 to 27/07/2027

BACKGROUND DOCUMENTS:

GM Agency Business Case -May 2025 v.2 (PDF) Modification Request Form – GM Temporary Staffing Supply UID 16798 18.11.2025 (005) (MS Word)

KEY DECISION:

Yes – total value of spend is excess of £350,000

DETAILS:

The Council uses a range of strategic and operational workforce planning approaches to ensure we have the right people, with the right skills and behaviours, in place to deliver services now and in the future. However, both internal and external factors can create sudden workforce pressures that require immediate or temporary resourcing solutions beyond standard recruitment routes.

For over a decade, the Council has worked collaboratively with other Greater Manchester authorities and partners to reduce costs, minimise risk, and ensure a consistent and compliant approach to engaging temporary workers. The current Greater Manchester Collaborative Contract, led by Trafford Council as the contracting authority, has been in place since 2016, with Salford participating through a beneficiary agreement. The Council is not committed to any level of spend

Permission to participate in the extension of the GM agency supply Reed framework contract and can draw on the contract as required.

The collaboration provides a managed service that supports: • Strategic guidance on workforce planning and fulfilment methods • Operational advice on agency needs and market rates • Support for hard‑to‑fill and niche recruitment campaigns • Agency worker ordering and system support • Full supply‑chain management, compliance and due diligence • Vacancy fulfilment, timesheet management, invoicing and reporting • Issue resolution and performance oversight

Reed Specialist Recruitment, the current provider, continues to deliver a largely effective service despite national shortages in key occupations such as qualified social workers.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approval for an Award of Contract Extension for Greater Manchester Collaborative Contract for the Provision of Temporary Workers (Sam Betts)Report 131 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 10 attended
BB
Barbara BenthamInvitee, in attendance
JC
Jim CammellInvitee, in attendance
PD
Paul DennettCommittee Member, apologies due to council business
AH
Anthony HiltonOfficer, present, as expected, virtual
CH
Chris HowlClerk, present
TK
Tracy KellyCommittee Member, apologies
MM
Mike McCuskerInvitee, in attendance
JM
John Merry CBECommittee Member, present
TP
Teresa PepperCommittee Member, present
JY
Jack YoudChair, present

On this subject at Salford

Search all
  1. Approval for an Award of Contract Extension for Greater Manchester Collaborative Contract for the Provision of Temporary Workers (Sam Betts)This decision
  2. Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Approved
  3. Approval to Award the Contract for the continued use of the Line of Business System for Planning, Building Control and Local Land and Property Gazetteer (Anthony Stephenson)Approved
  4. Approval to Award the Contract for Statutory Homeless Supported Temporary Accommodation (Jane Barlow)Approved
  5. Approval to Award the Contract for the construction of affordable homes at Robert Hall St Ordsall (A2) Dylan VinceApproved
  6. Approval to Award the Contract for Better Bus Routes/ Improving Journeys - Salford Crescent to MediaCityUK - Site Investigation (Matthew Mollart)Approved

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies