CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Salford City Council
Procurement Board, Monday 22 June 2026 at 2.00pm

Approval for an Extension of Contract for Interpretation and Translation Services (Stephen Titley)

Approved Committee 1 paper

AI summarySalford City Council Procurement Board extends its interpretation and translation contract with DALS Ltd for 12 months to 31 July 2027, with forecast spend of £164,000 and a 3% price rise after negotiation.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedWith DALS Ltd, the final extension under the original award
Money£164,000 forecastCharges based on actual usage, so may vary with demand
What happens nextContract ends 31/07/2027Options for service from that date to be reported to Procurement Board
Who it affectsAll council directorates and wardsIncludes Children's, People, Place, Public Health and Adults services

What was decided

The Procurement Board approved a 12-month extension of the Interpretation and Translation Services contract with DALS Ltd, running from 01/08/2026 to 31/07/2027, at a forecast value of £164,000. Report P1, P8, 1.1

The City Mayor accepted the Procurement Board's recommendation under the Council Constitution.

The option not to award the extension was considered and rejected, as the Council would otherwise be in breach of its legal accessibility duties. Report P49

Why

The extension was provided for in the original 2022 award and the current provider is meeting its 95% delivery target and customer satisfaction benchmarks. Report 1.1, 2.1, 2.2

DALS is on average 17% cheaper than alternative providers on a comparable framework, and the only cheaper alternative would add substantial travel costs. Report 5.3, 5.2

After negotiation, DALS's proposed 7% price rise was reduced to a 3% increase applied only from 01/08/2026, and DALS will introduce video-on-demand interpretation with an estimated 9.5% cost reduction. Report 4.1, 4.2, 2.5

What happens next

The Executive Director will, before the extension ends, decide whether to decommission the service or run a compliant re-procurement for provision beyond 31/07/2027. Report P2, P44

The SLA will be updated to include the extension period following approval. Report P60

Activity and spend will be monitored closely across the 12 months, given this is the final year of the five-year term. Report P52, P54

The money

  • £164,000 Forecast total spend for 01/08/2026 to 31/07/2027, after negotiated 3% price increase Report P6, 3.1
  • £98,400 Forecast Children's Services share (60% of total) Report P26, P53
  • £59,040 Forecast People share (36% of total) Report P26
  • £3,280 Forecast Place share (2% of total) Report P26
  • £1,640 Forecast Public Health share (1% of total) Report P26
  • £1,640 Forecast Adults Reform share (1% of total) Report P26
  • £37,720 Forecast face-to-face interpretation spend Report P27
  • £52,480 Forecast telephone interpretation spend Report P27
  • £41,000 Forecast document translation spend Report P27
  • £32,800 Forecast video remote interpretation spend Report P27
  • £218,129 Forecast cost of the only cheaper alternative provider on the comparable framework, including £27,880 additional ad hoc costs and £37,720 travel Report P39

Options considered

  • Chosen: Extend the existing contract with DALS Ltd for a further 12 months. Best value, embedded service, lower cost than alternatives once travel is included, and avoids change during organisational reorganisation Report P44, 5.3
  • Rejected: Do not award the extension. Would leave the Council without an interpretation and translation service from 01/08/2026, breaching legal accessibility obligations Report P49

Implications

  • Legal: Without the service the Council would be in breach of legal obligations to ensure its services are accessible. Report P49
  • Financial: Charges are based on actual usage so costs may vary with demand; ongoing monitoring of activity and expenditure is needed to manage financial risk. Report P52
  • Financial: Children's Services forecast cost of £98,400 will be met from existing budgets, including inflation and demand allocations approved in the February 2026 Medium-Term Financial Plan. Report P53
  • Equalities: An Equality Impact Assessment exists and is being reviewed and refreshed, with equalities and community groups in Salford being consulted on future commissioning plans from 01/08/2027. Report P47, P48
  • Climate: DALS has committed to align with the Council's climate change objectives, reach net zero by 2050, offset emissions via National Trust woodland planting in Greater Manchester, and increase video interpreting to cut travel emissions. Report P62, P63, P64
  • Risk: Any switching to an alternative provider would carry a financial and operational cost-to-change during a period of organisational reorganisation integrating former NCA, Aspire and GMMH colleagues.

Who and where

  • Council customers needing interpretation and translation across all wards and directorates Report P67, 1.2
  • Children's Services (60% of forecast spend) Report P26, P53
  • People services (36% of forecast spend) Report P26
  • Place, Public Health and Adults Reform directorates (combined 4% of forecast spend) Report P26
  • Salford community groups and equalities groups being consulted on future commissioning Report P48

Timeline

  • 13.07.22: Procurement Board awarded original contract to DALS Ltd for 01/08/2022 to 31/07/2025 with two optional 12-month extensions Report 1.1, P9
  • 01/04/2026: DALS originally proposed to apply price rises; following negotiation the rise was deferred to 01/08/2026 and reduced from 7% to 3% Report 4.1, 4.2
  • 19/05/2026: Procurement implications provided by Emma Heyes, Category Manager Report P57
  • 20/05/2026: Financial advice obtained from Laura Morley, Senior Accountant, Children's Services; legal advice from Daniel Howard, Principal Lawyer Report P50, P55
  • 03/06/2026: Strategic Head of Finance advice from Samuel Russell Report P50
  • 22/06/2026: Procurement Board considered the report and recommended approval
  • 01/08/2026: Final 12-month extension begins, with 3% price increase Report P6, 4.2
  • 31/07/2027: Final extension ends; a further report to come to Procurement Board on options for service provision from this date Report P6, P44

Plain English for the jargon

  • DALS Ltd: The contractor, previously trading as D A Languages, providing interpretation and translation services
  • PCR2015: Public Contracts Regulations 2015, the procurement legislation governing the award
  • SME: Small and medium-sized enterprise; DALS is confirmed as an SME
  • DDN process: Delegated Decision Notice process used to approve the first extension in 2025
  • Video-on-demand interpretation: Pay-as-you-go video interpretation by the minute, rather than pre-booked blocks of time
  • Lot 6 (One Stop Shop): The NHS Shared Business Services framework lot for providers offering all interpretation and translation services
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5d

Resolved

Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Board and in exercise of the powers contained within the Council Constitution do hereby: · approve the extension of Contract for Approval for an Extension of Contract for Interpretation and Translation Services and award, as detailed in the table below: Detail required Answers Title/Description of Contracted Service/Supply/Project Contract for Interpretation and Translation Services Procurement Reference Number (DN and CR, supplied by Procurement) S1073 Name of Successful Contractor DALS Ltd Supplier Registration Number (to be supplied by Lead officer) 06207784 Supplier Identifier Reference (Central Digital Platform) above awards above £30,000 (inc VAT) Not applicable Proclass Classification No. (to be completed by procurement) 261100 Type of organisation (to be supplied by Lead Officer) Private Limited Company Status of Organisation (to be supplied by Lead Officer [CF1] ) SME Contract Value (£) £ 164,000 Total Contract Value including extensions (£) £ 164,000 Contract Duration 12 months Contract Start Date 01/08/2026 Contract End Date 31/07/2027 Optional Extension Period 1 Not applicable Optional Extension Period 2 Not applicable Who will approve each Extension Period? Procurement Board (extension > £150k) Contact Officer (Name & number) Stephen Titley 0161 793 2435 Lead Service Group Children's Services Procurement Legislation PCR2015 Funding Source Revenue Budget Ethical Contractor (EC): Mayor’s Employment Charter No EC: Committed to sign up to the Mayor’s Employment Charter Yes EC: Committed to the principles outlined in the Mayor’s Employment charter Yes EC: Accredited Living Wage Employer Yes EC: Committed to becoming Accredited Living Wage Employer N/A The reasons are : 1. This extension period was planned for in the original Procurement Board report that awarded the contract, following an open tender process (see Section 1 in the current report). 2. The provider is currently providing a good service (see Section 2 in the current report). 3. This extension represents Best Value for the Council (see Sections 3, 4 and 5 in the current report). 4. The provider contributes to Social Value in Salford (see Section 6 in the current report). Options considered and rejected were : to not award the extension. Assessment of risk : if an interpretation and translation service were not to be in place from 01.08.26 onwards, then the Council would be in breach of legal obligations to ensure that its services are accessible. Innovate/ Best Value – identify the relevant corporate priorities specific to Salford: The Salford Way: City Mayor’s Charter and Living Wage and Innovate, Salford Community Solutions. The source of funding and financial advice obtained : Laura Morley Senior Accountant Children’s Services (20/05/2026) and Samuel Russell, Strategic Head of Finance for People, Children's and Adults (03.06.26). The contract provides interpretation and translation services across the Council, including both core and revenue-funded areas within Children’s Services. Charges are based on actual usage, meaning costs may vary in line with demand. Ongoing monitoring of activity and expenditure will therefore be important to manage financial risk and ensure value for money. The forecast cost attributable to Children’s ...
Word for word from the decision Salford published for this meeting. Source: sccdemocracy.salford.gov.uk

Follow this further

Built from Salford's papers

What the report saysPro

Report to Procurement Board

Recommendation

That the Procurement Board recommends Councillor Cusack, Lead Member for Corporate Services and Chairman of the Procurement Board, to approve the extension of the contract for Interpretation and Translation Services.

Note: that prior to the end of the period of time covered by the extension as indicated above, the Executive Director will determine whether the service is to be decommissioned or, in consultation with the Corporate Procurement Team, will agree to undertake a compliant procurement process to re-let the contract by the end of the exception period.

Detail required Answers Title/Description of Contracted Contract for Interpretation and Translation Service/Supply/Project Services Procurement Reference Number (DN S1073 and CR, supplied by Procurement) Name of Successful Contractor DALS Ltd Supplier Registration Number (to be supplied by Lead officer) 06207784

Supplier Identifier Reference (Central Digital Platform) above awards above Not applicable £30,000 (inc VAT) Proclass Classification No. (to be completed by procurement) 261100

Type of organisation Private Limited Company (to be supplied by Lead Officer) Status of Organisation (to be supplied by Lead Officer) SME

1 Detail required Answers Contract Value (£) £ 164,000 Total Contract Value including £ 164,000 extensions (£) Contract Duration 12 months Contract Start Date 01/08/2026 Contract End Date 31/07/2027 Optional Extension Period 1 Not applicable Optional Extension Period 2 Not applicable Who will approve each Extension Procurement Board (extension > £150k) Period? Contact Officer (Name & number) Stephen Titley 0161 793 2435 Lead Service Group Children's Services Procurement Legislation PCR2015 Funding Source Revenue Budget Ethical Contractor (EC): Mayor’s No Employment Charter EC: Committed to sign up to the Yes Mayor’s Employment Charter EC: Committed to the principles Yes outlined in the Mayor’s Employment charter EC: Accredited Living Wage Yes Employer EC: Committed to becoming N/A Accredited Living Wage Employer

Executive summary

The purpose of this report is to seek request an extension to contract for Interpretation and Translation Services.

There is provision within the current contract to extend the agreement for a further period from 01/08/2026 to 31/07/2027

BACKGROUND DOCUMENTS: Report Of The Strategic Director For People To Procurement Board On 13th July 2022 - Approval to Award the Contract for Interpretation and Translation Services for Salford City Council.

KEY DECISION: No, the value of the decision is between £150,000 and £349,999.

2 DETAILS:

Background

1.1The current contract with Dals (previously trading as D A Languages) was awarded by Procurement Board on 13.07.22, for a contract from 01.08.22 to 31.07.25. The award included an option of two further annual extensions to 31.07.26 and 31.07.27. The first option to extend was approved by the Executive Director under delegated powers as the value was less than £150,000.00. This report is to request permission to take up the final extension from 01.08.26 to 31.08.27. Due to the projected value exceeding £150,000 due to increased demand approval of the Procurement Board is required.

1.2Dals provides face-to-face interpretation, video remote interpretation (with the interpreter joining the meeting via Microsoft Teams), telephone interpretation and document translation for the Council.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approval for an Extension of Contract for Interpretation and Translation Services (Stephen Titley)Report 142 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 10 attended
PC
Philip CusackChair, apologies
PD
Paul DennettCommittee Member, apologies
TK
Tracy KellyCommittee Member, present
MM
Mike McCuskerCommittee Member, present
MB
Michele BarnesCommittee Member, present
JC
Jim CammellCommittee Member, present
BB
Barbara BenthamCommittee Member, present
HR
Hannah Robinson-SmithCommittee Member, apologies
AH
Anthony HiltonOfficer, apologies
CH
Chris HowlClerk, present

On this subject at Salford

Search all
  1. Approval for an Extension of Contract for Interpretation and Translation Services (Stephen Titley)This decision
  2. Approval for an Extension of Contract for Statutory Homeless Supported Temporary Accommodation Contract at Abbott Lodge (Jane Barlow)Approved
  3. Approval for an Exception to Contractual Standing Orders to award an extension of the Technical and Highways Works Framework Agreement (Steve Hands/ Sharon Walls)Approved
  4. Approval for an Extension of Contract for the Management Agreement at Salford Innovation Forum (SIF) (Jo Ivison)Agreed
  5. Approval for an Extension of Contract for Occupational Health Services - Greater Manchester Collaboration OH Services (Optima Health) (Karen Bird)Approved
  6. Approval to the extension of the contract for Arboricultural Services (Jo Regan/ Ian Worsley/ Paul Jones)Approved

More from Salford Procurement Board

All decisions
MeetingDecisionOutcome
21 Sep 2026 Approval to Procure All Age Carers Service (Paul Walsh/ Emma Higham/ Jessica Ta'ati)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Renewal of over 100kW electricity contract for Salford City Council (Majid Maqbool)Salford City Council – Record of Decision I Paul Dennett, City Mayor, accept the recommendation of the Procurement Bo... Approved Open
21 Sep 2026 Approval to Award the Contract for Adult Social Care Delivery Partner (Jon Manzoni/ Lee Thompson/ Matt Drogan)Salford City Council – Record of Decision I (Councillor Cusack, Lead Member for Corporate Services and Chairman of th... Approved Open
21 Sep 2026 Charles House, Eccles – Completion of Demolition Works (Sarah Malone)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open
21 Sep 2026 Bury Old Road/ Singleton Road Junction Improvement Scheme (Usman Zubair)Salford City Council – Record of Decision I Councillor Cusack, Lead Member for Corporate Services and Chairman of the... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies